R16PS00663 - Amendment No. 003

View the file

Other files for this federal contract opportunity

Other files attached to Lake Woolomes Recreation Area Asphalt Replacement, newest first.
File Type Posted
R16PS00663_-_Amendment_No._002.pdf PDF
R16PS00663_-_Amendment_No._001.pdf PDF
Solicitation_No._R16PS00663.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

R16PS00663

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Sacramento CA 95825-1898 2800 Cottage Way, Room E-1815

R20

Division of Acquisition Services Regional Office Mid-Pacific Region Bureau of Reclamation

06/29/2016003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/16/2016

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Legacy Doc #: BOR

A. TITLE: Lake Woolomes Recreation Area Asphalt Replacement

B. PURPOSE: This amendment incorporates the following changes:

(1) Remove and Replace Specification Section 32 01 13

(2) Remove and Replace Continuation of Section B - Supplies or Services and Prices/Costs

The bid due date remains unchanged at July 6, 2016 at 10:00 AM, Pacific Time.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Matthew T. Byrne

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Amendment No. 003 Lake Woollomes Recreation Area Asphalt Replacement Central Valley Project, California Solicitation No.

Double Seal Coat

32 01 13 - 1

SECTION 32 01 13

DOUBLE SEAL COAT

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Screenings:

1. Measurement: Weight of material placed, measured at a certified scale.

2. Payment: Ton price offered in the Price Schedule.

A. Asphalt:

1. Measurement: Weight of material placed, measured at a certified scale.

2. Payment: Ton price offered in the Price Schedule.

a. Includes:

1) Furnishing and applying asphalt:

2) Rollings.

3) Sweeping.

b. Does not include:

1) Screenings.

1.02 REFERENCE STANDARDS

A. ASTM International (ASTM)

1. ASTM D977-13 Emulsified Asphalt

B. California Department of Transportation (CALTRANS)

1. Standard Specifications Standard Specifications, 2006

a. Maintain a copy of CALTRANS Standard Specifications at jobsite during paving work.

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 32 01 13-1, Certifications:

1. Certificates of compliance for materials and construction in accordance with CALTRANS Standard Specifications.

32 01 13 - 2

1.04 ENVIRONMENTAL REQUIREMENTS

A. Comply with CALTRANS Standard Specifications for weather limitations for seal coat placement.

PART 2 PRODUCTS

2.01 GENERAL

A. Asphalt shall consist of refined petroleum or a mixture of refined liquid asphalt and refined solid asphalt, prepared from crude petroleum. Asphalt shall be:

1. Free from residues caused by the artificial distillation of coal, coal tar, or paraffin.

2. Free from water.

3. Homogeneous.

B. Furnish asphalt in conformance with CALTRANS’s "Certification Program for Suppliers of Asphalt."

C. Ensure the safe transportation, storage, use, and disposal of asphalt.

D. Prevent the formation of carbonized particles caused by overheating asphalt during manufacturing or construction.

2.02 SURFACINGS AND PAVEMENTS

A. Bituminous Seals:

1. Seal Coats:

a. Description:

1) Double seal coat shall consist of an application of asphalt followed with an application of screenings followed by rolling followed by sweeping, and another application of asphalt followed with another application of screenings followed by rolling followed by sweeping

b. Performance based asphalt (PBA) binder shall conform to Specification Grade PBA 6a in accordance with CALTRANS Table “SECTION 92 ASPHALTS Performance Based Asphalt Binder” page 784 of 2006 version of CALTRANS Standard specifications.

c. The size of screenings for the seal coats shall be as follows:

1) First application1/2-inch X No. 4.

2) Second application1/4-inch X No. 10.

32 01 13 - 3

d. Screenings shall conform to the following requirements prior to depositing on the roadbed.

e. Screenings shall consist of broken stone, crushed gravel or both. At least 90 percent by weight of the screenings shall consist of crushed particles as determined by California Test 205.

f. Screenings shall be clean and free from dirt and other deleterious substances.

g. Screenings shall also conform to the following quality requirements:

1) Los Angeles Ratter Loss at 100 Rev. (max) California test 211 Requirements 10 percent.

2) Los Angeles Ratter Loss at 500 Rev. (max) California test 211 Requirements 40 percent.

3) Film Stripping (max) California test 302 Requirements 25 percent.

4) Cleanness Value (min) California test 227 Requirements 80 percent.

h. If the results of the aggregate grading for screenings does not meet the gradation specified, remove the seal coat represented by the test.

However, if requested in writing by the Contractor and approved by the COR, the seal coat may remain in place.

i. If the results of the Cleanness Value test for screenings is below 80, the seal coat represented by the test shall be removed. However, if requested in writing by the Contractor and approved by the COR, seal coat containing screenings with a Cleanness Value below 80, but not less than 75, may remain in place. When both the aggregate grading and the Cleanness Value for screenings do not conform to the requirements specified, both payments to the Government shall apply. The Government may deduct these amounts from any moneys due, or that may become due, the Contractor under the contract. No single aggregate grading or Cleanness Value test shall represent more than 300 tons or one day's production, whichever is smaller.

j. Samples for the aggregate grading and Cleanness Value tests will be taken from the conveyor belt of the spreader prior to application.

PART 3 EXECUTION

3.01 PREPARATION FOR SEAL COAT

A. Immediately before applying the asphaltic emulsion, the surface to be sealed shall be clean and dry. Cleaning shall be performed by sweeping, flushing or other means necessary to remove all loose articles of paving, all dirt and all other extraneous material.

32 01 13 - 4

B. When seal coats are to be applied to an untreated material, a prime coat consisting of liquid asphalt shall be applied to the material in place at a rate of from 0.35-gallon per square yard.

3.02 APPLYING ASPHALT

A. Unless otherwise specified, heat and apply asphalt in conformance with the provisions in Section 93, "Liquid Asphalts" of CALTRANS Standard Specifications, 2006. The application rates of shall be 0.35 gallons per square yard for the first application and 0.25 gallons per square yard for the second application.

B. Asphalt shall not be applied when weather conditions are unsuitable. Seal coats requiring screenings shall not be applied until sufficient screenings are on hand to immediately cover the asphaltic emulsion, or when the atmospheric temperature is below 65 degrees Fahrenheit or above 110 degrees Fahrenheit, or when the pavement temperature is below 80 degrees Fahrenheit. Fog seal coat shall not be applied when the atmospheric temperature is below 40 degrees Fahrenheit.

C. The COR will notify the Contractor, no later than 4:00 PM, if it is anticipated that the next working day will not be suitable for the application of seal coat. This notice may be given on the day preceding the date the Contractor intends to begin work, any working day after the Contractor has begun work, and any day previously named by the COR as a day unsuitable for applying seal coat. When the COR has declared a day to be unsuitable by reason of expected low temperature or unsuitable weather conditions, the Contractor shall not apply any new seal coat. If maintenance of previously applied seal coat can be performed, the Contractor shall continue to perform the maintenance. These unsuitable days will not be counted as working days regardless of the actual weather conditions and the fact that seal coat maintenance work is performed by the Contractor.

D. If the Contractor has not been notified by the COR of an anticipated unsuitable day and at the beginning of the work day the weather is unsuitable for the application of seal coats, but maintenance of previously applied seal coat can be performed, the Contractor shall not apply any seal coat. Binder and screenings brought to the project shall be returned, stored or disposed of as directed by the COR. The Contractor shall continue maintenance of previously applied seal coat. Applying asphalt shall be discontinued sufficiently early in the day to permit the termination of traffic control prior to darkness. Asphalt shall be applied to the pre-approved areas.

E. Asphalt shall not be applied a greater distance than can be immediately covered by screenings, unless otherwise permitted by the COR.

F. The cut off of asphalt shall be made on building paper or similar material spread over the surface. Paper shall also be placed over the treated surface for a sufficient length at the beginning of a spread to avoid spraying existing pavement or previously placed screenings and so that the nozzles are spreading properly when the uncovered surface is

32 01 13 - 5 reached. The building paper shall then be removed and disposed of in a manner satisfactory to the COR.

G. The distribution of asphalt shall not vary more than 15 percent transversely from the average as determined by tests, nor more than 10 percent longitudinally from the specified rate of application as determined by CALTRANS’s California Test 339.

3.03 SPREADING SCREENINGS

A. Screenings for seal coats shall be spread immediately following the application of the asphaltic emulsion. The spread rate of screenings for the various types of seal coats shall be:

1. First Application spread rate of 26 pounds/square yard.

2. Second application spread rate of 16 pounds/square yard.

B. Screenings shall be spread by means of a self-propelled chip spreader, equipped with a mechanical device which will spread the screenings at a uniform rate over the full width of a traffic lane in one application. The joint between adjacent applications of screenings shall coincide with the line between designated traffic lanes.

C. Operating the chip spreader at speeds which cause the chips to roll over after striking the bituminous covered surface will not be permitted.

D. The transverse cut off of screenings shall be complete and any excess screenings shall be removed from the surface prior to resuming operations.

E. Stockpiling of screenings prior to placing will be permitted; however, any contamination resulting during storage or from reloading operations will be cause for rejection.

F. Screenings shall be surface damp at the time of application, but excess water on the aggregate surface will not be permitted. Screenings shall be redampened in the vehicles prior to delivery to the spreader when directed by the COR.

G. Asphalt shall be covered with screenings before setting or “breaking” of the asphalt occurs.

3.04 FINISHING

A. After the screenings have been spread upon the asphaltic emulsion, piles, ridges or uneven distribution shall be carefully removed to ensure against permanent ridges, bumps or depressions in the completed surface. Additional screenings shall be spread in whatever quantities may be required to prevent picking up by the rollers or traffic, after which the surface shall be rolled.

32 01 13 - 6

B. Rollers shall be pneumatic-tired type. A minimum of 2 pneumatic-tired rollers conforming to the provisions in Section 39-5.02, Compacting Equipment, shall be furnished.

C. Initial rolling shall consist of one complete coverage and shall begin immediately behind the spreader. Asphalt and screenings shall not be spread more than 2,500 feet ahead of completion of initial rolling operations. Secondary rolling shall begin immediately after completion of the initial rolling. The amount of secondary rolling shall be sufficient to adequately seat the screenings and in no case shall be less than 2 complete coverages.

D. Unless otherwise provided in the special provisions or directed by the COR, seal coat surfaces shall be maintained, including the traffic control required for maintenance operations, for a period of 4 consecutive calendar days beginning on the day screenings are applied to the asphaltic emulsion. Maintenance of the surface shall include brooming and the distribution of screenings over the surface to absorb any free bituminous material, to cover any area deficient in cover coat material and to prevent formation of corrugations. Clean sand may be used in lieu of screenings to cover any excess of asphalt which comes to the surface. The use of roadside material for this purpose will not be permitted.

E. Brooms for finishing and maintaining seal coat screenings shall be the self-propelled type. When brooming is required adjacent to curbs, gutters, dikes, berms, railings or other barriers which would prevent loose screenings from being swept completely off the roadway, the self-propelled brooms shall also be capable of removing the loose screenings from the surface during brooming. In addition to the self-propelled brooms required for maintaining previously placed screenings, at each location where screenings are to be spread, a minimum of 3 self-propelled brooms shall be available, prior to the start of spreading the screenings at a location.

F. The surface of the seal coat shall be broomed as often as necessary during the 4 calendar day maintenance period to maintain the surface free of loose screenings. At the end of the 4 consecutive calendar day maintenance period, any excess screenings shall be removed from paved areas. Brooming of seal coat surfaces shall be performed in such a manner that the screenings set in the asphalt will not be displaced. The exact time of brooming will be determined by the COR. As a minimum, brooming will be required at the following approximate times:

1. Immediately prior to opening any lane to public traffic, not controlled with pilot cars.

2. As a first order of work on the morning following application of screenings, on any lane that has been open to public traffic, not controlled with pilot cars.

3. At the end of the 4 calendar day maintenance period.

G. Excess screenings remaining on the surface after the first application of a "double" seal coat shall be removed prior to the second application of asphaltic emulsion.

32 01 13 - 7

H. When directed by the COR, excess screenings shall be salvaged and stockpiled at designated locations.

I. Excess screenings which in the opinion of the COR are not salvable and which interfere with drainage shall be removed and disposed of by the Contractor at the Contractor's expense. The removed screenings shall be disposed of in conformance with the provisions in Section 7-1.13, Disposal of Material Outside the Highway Right of Way, or along embankment slopes, or at other suitable locations if permitted by the COR.

J. The completed surface shall present a uniform appearance and shall be free from ruts, humps, depressions or irregularities due to an uneven distribution of asphalt or screenings.

3.05 MAINTENANCE

A. Maintain paved areas until acceptance of work by Government.

END OF SECTION

32 01 13 - 8

This page intentionally left blank.

R16PS00663 – Lake Woolomes Recreation Area Asphalt Replacement

Price Schedule

B - 1

CONTINUATION OF

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

LAKE WOOLOMES RECREATION AREA ASPHALT REPLACEMENT

CENTRAL VALLEY PROJECT

B.1 PRICE SCHEDULES

(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.

(b) Offers are subject to the terms and conditions of this solicitation.

(c) Quantities in the Price Schedule are estimated quantities for comparison of offers only.

Except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated Quantity does not apply to lump sum items.

(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.

(e) Definitions:

(1) CLIN – Contract Line Item Number.

SCHEDULE

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

1 WBR

1452.232

-81

Mobilization and Preparatory Work

For the lump sum of $

2 32 01 13 Screenings 570 Ton $ $

3 32 01 13 Liquid Asphalt 70 Ton $ $

TOTAL FOR PRICE SCHEDULE $______________________________________________

END OF SUPPLIES OR SERVICES AND PRICES/COSTS

R16PS00663 – Lake Woolomes Recreation Area Asphalt Replacement

Price Schedule

B - 2