Tab_14_-Att_1_Vol._II__Bulk_Equipment_Specifications_Final_3_26_15_-_Copy.pdf

PDF 1 MB Posted

Attached to
Bulk Equipment Purchase Federal contract opportunity
Solicitation number
R15PS00713
Issued by
Department of the Interior Bureau of Reclamation

About this file

Attachment 1 Vol II Bulk Equipment Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Bulk Equipment Purchase, newest first.
File Type Posted
Sol_R15PS00713_Amd_000001.pdf PDF
Sol_R15PS00713.pdf PDF
Tab_14_-Solicitation_R15PS00713_Vol_I.pdf PDF
Tab_14_-Att_2_Drawings_Rev_09042014_Final 1 _-_Copy.pdf PDF
Tab_14_-Att_3_PPQ_R15PS00713_-_Copy.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY15 P1 Bulk Equipment Solicitation No:R15PS00713

Table of Contents

00 01 10 - 1

BULK EQUIPMENT PURCHASE

SPECIFICATIONS

Volume II of II

SOLICITATION NO. R15PS00713

UNITED STATES DEPARTMENT OF THE INTERIOR

BUREAU OF RECLAMATION

UPPER COLORADO REGION

SALT LAKE CITY, UTAH

00 01 10 - 2

SECTION C - DESCRIPTION / SPECIFICATIONS

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work

01 33 00 Submittals

01 33 26 Electrical Drawings and Data

01 35 10 Material Safety Data Sheets

01 42 10 Reference Standards

01 60 00 Product Requirements

01 78 30 Project Record Documents

DIVISION 02 THROUGH 25 - NOT USED

DIVISION 26 - ELECTRICAL

26 12 19 Pad Mounted Oil-Filled Distribution Transformer

26 13 10 5kV Metal-enclosed Switchgear

26 24 24 Distribution Switchboards

26 29 23 Low-Voltage Variable Frequency Drive Systems

DIVISION 27 THROUGH 32 - NOT USED

DIVISION 33 - UTILITIES

33 12 82 Induction Motors

DIVISION 34 THROUGH 51 - NOT USED

DIVISION 52 - DRAWINGS

52 00 00 Drawings

DIVISION 53 – NOT USED

END OF CONTENTS

00 01 10 - 3

Summary of Work

01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 REQUIREMENT

A. The Dolores Water Conservancy District (DWCD) provides seasonal irrigation under pressure in southwest Colorado for the Dolores Project, owned by the Bureau of

Reclamation and operated by DWCD. Four pumping plants are being upgraded: Pleasant

View Pumping Plant (PP), Ruin Canyon PP, Dove Creek PP, and Cahone PP. The objective of this upgrade project, FY15 P1 Bulk Equipment, is to replace nine existing

Variable Frequency Drives (VFD) with modern VFDs, to be operated at 480 VAC. Two of the plants currently use medium voltage VFDs and motors, and the other two plants were previously converted to 480V with new drives and motors. The current 480V drives are old technology and significantly aged. The new equipment will be fully compliant with the harmonic distortion requirements of IEEE 519 using 18 pulse VFD technologies, backed up with alternate fixed speed motor controls using soft start controls installed within the same enclosures as the VFD. To support the change in pump operating voltage to 480 VAC at Pleasant View PP and Ruin Canyon PP, the equipment at each plant will include a new section of 5kV metal-enclosed switchgear, a new 750kVA, 2400 VAC to

480 VAC station service transformer, as well as new a 480VAC distribution switchboard.

New 480 VAC inverter duty motors will replace the 4 variable speed 2400 VAC motors on the existing pumps at those two plants and provide one spare. These new motors will be a hollow shaft design. Cahone PP and Dove Creek PP will simply have the existing

480V VFDs replaced.

B. The intent of this contract is to procure all the major long lead equipment for these upgrades. Supply the equipment required for the FY15 P1 Bulk Equipment in accordance with contract provisions and clauses, these specifications, and drawings listed in Division

52, Table 52 00 00A, “List of Drawings”.

C. The principal components of work consisting of supplying nine (9) low voltage variable frequency drives, two (2) distribution transformers, two (2) sections of medium-voltage metal-enclosed switchgear, five (5) 250Hp induction motors, low voltage motor controls and two (2) 480V distribution switchboards.

1.02 LOCATION

A. All equipment shall be delivered to the following address:

1. Great Cut Pumping Plant

20555 CR25

Dolores, CO 81323

01 11 00 - 2

1.03 SCHEDULE

A. The material shall be supplied in accordance with the table below. Equipment should be manufactured to meet the following schedule:

Delivery Item Pumping Plant Location

November

Two (2) 750kVA pad mounted transformers

Ruin Canyon and Pleasant

View

November

Two (2) MV metal-enclosed switchgear sections

Ruin Canyon and Pleasant

View

November

Two (2) distribution switchboards

Ruin Canyon and Pleasant

View

November

Four (4) 250Hp VFDs

Ruin Canyon and Pleasant

View

November

Five (5) 250Hp Induction Motors

Ruin Canyon and Pleasant

View

September

30, 2016 Two (2) 200Hp VFDs Dove Creek

September

30, 2016 Three (3) 400Hp VFDs Cahone

1.04 PRINCIPAL COMPONENTS OF WORK FOR SCHEDULE B

A. Supply two (2) pad mounted oil-filled distribution transformers, 750kVA, 2400V-480V.

B. Supply two (2) vertical sections of 5kV metal-enclosed load-interrupter switchgear to include fuses.

C. Supply two (2) 480V distribution switchboards.

D. Supply nine (9) low voltage variable frequency drive systems.

E. Supply five (5) 250Hp inverter duty induction motors.

1.05 OTHER GOVERNMENT CONTRACTS

A. Not Used

1.06

1.07 WORK BY OTHERS

A. None Used

01 11 00 - 3

1.08 SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

C. Where specifications are written in streamlined form, the words “shall be” are included by inference where a colon (:) is used within the sentence or phrase.

1.09 DEFINITIONS

A. When the specifications use a word or term defined in the Federal Acquisition

Regulations (FAR), the definition of the word or term shall be in accordance with FAR sections in effect at the time the solicitation was issued.

B. Quality Assurance: Inspection and tests performed by CO to ensure compliance with the terms of the contract.

C. Quality Control: Activities performed by Contractor to ensure work conforms to contract requirements.

D. Contractor Quality Testing: Specified tests to be performed by the Contractor.

1. The Government may use the test results for Quality Assurance.

2. The Contractor may use the test results as part of Contractor quality control.

a. The CO anticipates that these tests will be part of the Contractor’s quality control program, however the tests do not relieve the Contractor of providing adequate quality control measures in accordance with the clause at FAR 52.246-12, Inspection of Construction.

1.10 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 53:

1. CO: Contracting Officer

2. COR: Contracting Officer’s Representative

3. DWCD: The operating water conservancy district for the Dolores Project

PART 2 PRODUCTS

Not Used

01 11 00 - 4

PART 3 EXECUTION

END OF SECTION

Submittals

01 33 00 - 1

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the schedule for other items of work.

1.02 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.

1.03 SUBMITTAL REQUIREMENTS

A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.

B. General:

1. Prepare in English.

2. Label with contract number and title, and RSN.

3. Measurement units: US Customary Units.

C. Drawings:

1. Minimum identification in title block:

a. Contract number and title.

b. Contractor’s or supplier’s title and drawing number.

c. Date.

2. Reserve 3- by 3-inch space next to title block for review stamps.

3. Size: D size (22 inches by 34 inches).

4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.

a. Lettering shall be neat when drawing preparation with drafting equipment is allowed.

5. Final drawings:

01 33 00 - 2

a. Drawing format: AUTOCAD, Version 2007 or later.

b. Show as-built changes, including revision dates, made during installation.

Indicate changes by clouding.

c. Electronic files: On CD or DVD discs.

d. Government will provide an electronic AutoCAD template.

D. Product Data:

1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.

a. Identify manufacturer's name, type, model, size, and characteristics.

b. Illustrate that product or equipment meets requirements of specifications.

c. Mark items to be furnished in a manner that will photocopy (no highlighter).

d. Strike through items that do not apply.

E. Certifications:

1. Certifications by a registered professional: Signed and sealed by registered professional.

2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.

F. Manuals:

1. Copies:

a. Printed copies: Bound and indexed.

b. Electronic copies: Adobe pdf on CD or DVD discs.

1) Bookmark longer files to assist in navigating file.

2. Contents:

a. Parts identification lists, lists of special tools, and accessories.

b. Schematics and wiring diagrams.

c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.

G. As-built drawings, photographs, and test records or reports if required by the specifications.

01 33 00 - 3

1.04 SUBMITTALS PROCEDURES

A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.

B. Submit sets specified in “Number of sets to be sent to:” columns in Table 01 33 00A -

List of Submittals. A complete set includes all listed items for RSNs with multiple parts.

1. Electronic submittals:

a. In Portable Document Format (PDF).

b. Include RSN transmittal letter.

c. Do not include Personally Identifiable Information (PII) in electronic submittals.

2. Submit electronic submittals via email or CD/DVD based on size:

a. The Government can receive e-mails up to 25MB. However, e-mails over

10MB should be considered extra-large. E-mailing of electronic submittals exceeding 10MB should only occur after transmittal of extra-large size e-mail has been verified.

b. Include electronic submittals that are too large to e-mail with paper copy of submittal. These electronic submittals shall be on CD or DVD.

C. Include the following information in transmittal letters:

1. Contract number and title.

2. RSN for each attached submittal.

3. Responsible code.

4. Number of sets for each RSN.

5. Identify submittal as initial or resubmittal.

D. Resubmittal of submittals not approved:

1. Mark changes such that they are readily identifiable and show revision date.

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 14 days after receiving the comments, unless otherwise directed.

4. Requirements for initial submittals apply to resubmittals.

E. Each RSN shall be submitted under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned to the Contractor for resubmittal.

01 33 00 - 4

1.05 REVIEW OF SUBMITTALS

A. Time Required:

1. Submittal review will require up to 21 days for review of each submittal or resubmittal, unless otherwise specified.

B. Time in Excess of Specified:

1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.

a. The time extension will be to the extent that excess review time caused delay to the contract completion date.

b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.

c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.

2. No time extension will be allowed if the Contractor fails to make complete action submittals in sequence and within time periods specified.

3. Adjustment for delay will be made only to the extent that:

a. Approval was required under the contract, and

b. Requests for approval were properly and timely submitted and were approved.

4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR

52.242-14, Suspension of Work, however, no such delay shall be deemed to be a

“suspension order” as the term is used in that clause.

C. Submittal Response:

1. A response letter from the COR for each submittal will be sent to the Contractor indicating whether the submittal is approved, approved subject to identified changes, or not approved.

a. Revise and resubmit submittals not approved.

b. Do not change designs without approval of the COR after drawings, documentation, and technical data have been approved.

1.06 TRANSMITTAL

A. Addresses for codes listed in Table 01 33 00A - List of Submittals:

1. Where the recipient is the Contracting Officer, address the transmittal letter to

Bureau of Reclamation, 125 South State Street, Room 8100, Salt Lake City, UT

84138-1147.

01 33 00 - 5

2. Where the recipient is the Contracting Officer’s Representative, address the transmittal letter to Bureau of Reclamation, Attention: Vern Harrell, PO Box

1150, 60 S. Cactus St., Cortez, CO 81321.

a. In addition to the paper copy submissions mailed to the above referenced address, electronic .pdf submittals 10MB or less shall be e-mailed to the following address: vharrell@usbr.gov.

b. Electronic .pdf submittals 10MB or larger shall be submitted to

Reclamation via CD or DVD along with the paper copy.

PART 2 PRODUCTS

Not Used

01 33 00 - 6

Table 01 33 00A. - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.

RSN

Clause or

Section

Title

Submittals required Due date or delivery time

Respon-sible code

No. of sets to be sent to: *

CO COR

01 78 30-1 Project Record

Documents

Warranties Within 14 days of completion of work

CO 0 3 paper +

1 electronic

26 12 19-1 Distribution

Transformer

Manufacturer’s

Data

45 days after contract CO 0 1 electronic

26 12 19-2

Distribution

Transformer

Certified Factory

Test Report

At Shipment CO 0 1 electronic

26 12 19-3 Distribution

Transformer

Operation and

Maintenance

Instruction Book

At Shipment CO

3 paper +

1 electronic

26 12 19-4 Distribution

Transformer

Record Drawings At Shipment CO

26 13 10-1 5kV SWGR Approval Data

45 days after contract CO

26 13 10-2 5kV SWGR Approval Drawings 45 days after contract CO 0 1 electronic

26 13 10-3 5kV SWGR Fuse Curves 45 days after contract CO 0 1 electronic

26 13 10-4 5kV SWGR Certified Factory

Test Reports

At Shipment CO 0 1 electronic

26 13 10-5 5kV SWGR Operation and

Maintenance Manual

At Shipment CO

3 paper +

1 electronic

26 13 10-7 5kV SWGR Record Drawings At Shipment CO 0 1 electronic

26 24 24-1 480V SWBD Product data 30 days after contract CO 0 1 electronic

26 24 24-2 480V SWBD Shop Drawings 45 days after contract CO 0 1 electronic

26 24 24-3 480V SWBD Operating Manuals At Shipment CO

3 paper +

1 electronic

26 24 24-4 480V SWBD Factory Testing At Shipment CO 0 1 electronic

26 24 24-5 480V SWBD Record Drawings At Shipment CO 0 1 electronic

26 29 23-1 Variable

Frequency

Drive Systems

Approval Data

26 29 23-2 Variable

Frequency

Drive Systems

Informational

Submittals

45 days after contract CO

3 paper + 1 electronic

26 29 23-3 Variable

Frequency

Drive Systems

Factory Testing At Shipment CO

0 1 electronic

26 29 23-4 Variable

Frequency

Drive Systems

Record Drawings At Shipment CO

01 33 00 - 7

Table 01 33 00A. - List of Submittals

* CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.

RSN

Clause or

Section

Title

Submittals required Due date or delivery time

Respon-sible code

No. of sets to be sent to: *

CO COR

33 12 82-1 Induction

Motors

Product Data

33 12 82-2 Induction

Motors

Equipment layout drawings & bill of material

45 days after contract CO

0 1 electronic

33 12 82-3 Induction

Motors

Schematic and wiring diagrams

45 days after contract CO 0 1 electronic

33 12 82-4 Induction

Motors

Motor Design Data 45 days after contract CO 0 1 electronic

33 12 82-5 Induction

Motors

Motor Test Reports At Shipment CO 0 1 electronic

33 12 82-6 Induction

Motors

Motor Installation, Operation &

Maintenance

Manuals

At Shipment CO

Electrical Drawings and Data

01 33 26 - 1

SECTION 01 33 26 - ELECTRICAL DRAWINGS AND DATA

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the schedule for items requiring electrical drawings and data.

1.02 REFERENCES

A. American Society of Mechanical Engineers (ASME)

1. ASME Y14.1 – 2005 Decimal Inch Drawing Sheet Size And Format

B. Institute of Electrical and Electronic Engineers (IEEE)

1. IEEE 315 -1975(1993) Graphic Symbols For Electrical And Electronics

Diagrams (Including Reference Designation Class

Designation Letters)

2. IEEE C37.2-1996(2001) Standard Electrical Power System Device Function

Numbers and Contact Designations

3. IEEE Y32.9-1972(1989) Graphic Symbols for Electrical Wiring and Layout

Diagrams Used in Architecture and Building

Construction

C. National Electrical Manufacturers Association (NEMA)

1. NEMA ICS 1-2000(2008) Industrial Control and Systems: General

Requirements

1.03 SUBMITTAL PROCEDURES

A. In addition to the requirements in Section 01 33 00 – Submittals, prepare electrical drawings and data submittals in accordance with the following.

B. Drawings, general:

1. Device designations and symbols:

a. Conform to IEEE 315, IEEE C37.2, IEEE Y32.9, and NEMA ICS-1.

2. Size: D-size prints as defined in ASME Y14.1 made from original drawings.

3. Indicate changes on revised drawings to distinguish them from previous submittals. Describe reasons for significant changes in submittal letters.

01 33 26 - 2

C. Approval Drawings and Data:

1. Equipment Layout Drawings:

a. Indicate dimensions of equipment.

b. Indicate location of devices and items of equipment in their relative physical location.

c. Identify each device and item of equipment with a bill of material reference number.

2. Bill of Material List:

a. Provide information on manufacturer, style, type, rating, quantity, and other identifying information for each device or item of equipment.

b. Provide unique reference number for each device or item of equipment listed on bill of material.

3. Schematic Diagrams:

a. Identify devices and items of equipment with appropriate device number in IEEE C37.2 and NEMA ICS 1.

b. Provide unique wire numbers for control circuits.

4. Wiring Diagrams:

a. Show devices and items of equipment in their relative physical location.

b. Identify devices and items of equipment with designations shown on schematic diagrams.

c. Indicate wiring of devices and items of equipment including terminal block numbers.

d. Identify location of future connection to external devices and equipment.

5. Manufacturer’s Technical Catalog Data:

a. Provide technical data for each device or item of equipment.

b. Include manufacturer=s name and address; catalog number, type, style, or model number; electrical ratings; and dimensions.

c. Where several items are listed on same sheet, indicate items being submitted for approval.

d. Demonstrate proposed device or item of equipment meets specifications requirements.

e. Mark catalog data sheet with appropriate bill of material (BOM) item number.

f. Assemble catalog data sheet into one enclosing cover with bill of material

(BOM) index, 01 33 26 - 3

D. Test Reports:

1. Typed, 8 1/2- by 11-inch sheets.

2. Multi-page reports shall be bound in folder or three-ring binder.

3. Certified.

E. Operation and Maintenance Manuals:

1. Print copies:

a. Assemble each set of material into one or more books with enclosing covers.

2. Electronic copies:

a. Adobe Acrobat (.pdf) format on CD-ROM discs.

b. Conform to print copies.

c. Bookmark file(s) to aid in navigating.

3. Provide following items:

a. Index sheet at front of each book which provides page or index tab number information for each device or item of equipment in book.

b. Manufacturer's operation and maintenance procedures; installation details, as necessary; and catalog data sheets for each device or item of equipment.

c. List of recommended spare parts and components.

d. Complete parts lists for all replacement parts.

e. Copies of all factory test reports.

f. Copies of bills of materials.

g. Copies of all drawings.

1) Revised to reflect approval comments.

2) Size: 11- by 17-inch.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

01 33 26 - 4

This page intentionally left blank.

Material Safety Data Sheets

01 35 10 - 1

SECTION 01 35 10

MATERIAL SAFETY DATA SHEETS

PART 1 None Used

Reference Standards

01 42 10 - 1

SECTION 01 42 10

REFERENCE STANDARDS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Referenced editions of standard specifications, codes, and manuals form a part of this specification to the extent referenced.

B. These specifications take precedence when conflicting requirements occur between specifications and referenced standard.

1.03 JOBSITE REFERENCE STANDARDS

A. Maintain at fabrication site, a copy of referenced standard specifications, codes, and manuals required for work in progress at fabrication site. Make available for use by the

Government.

B. Maintain onsite, a copy of referenced standard specifications, codes, and manuals required for onsite work in progress. Make available for use by the Government.

1.04 AVAILABILITY

A. Code of Federal Regulation (CFR):

1. Available online, authorized by the National Archives and Records

Administration (NARA) and the Government Printing Office (GPO), at www.gpoaccess.gov/cfr/index.html.

B. Federal Specifications, Standards, and Commercial Item Descriptions; and Military

Specifications:

1. Copies of Federal Specifications, Standards, and Commercial Item Descriptions may be obtained from GSA Federal Supply Service, see the provision at FAR

52.211-1, Availability of Specifications Listed in the GSA Index of Federal

Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29.

2. Copies of Military Specifications may be obtained from Department of Defense, see the provision at FAR 52.211-2, Availability of Specifications, Standards, and

Data Item Descriptions Listed in the Acquisition Streamlining and

Standardization Information System (ASSIST).

01 42 10 - 2

C. Bureau of Reclamation Documents:

1. Bureau of Reclamation Standard Specifications are designated with an M-number. Copies of individual standards may be obtained from Bureau of

Reclamation, Attn 86-68170, PO Box 25007, Denver CO 80225-0007. Specify which standard(s) is needed when requesting a copy.

2. Bureau of Reclamation manuals and other publications including significant scientific, technical, and engineering works are available from the National

Technical Information Service (NTIS). Information regarding availability and pricing may be obtained by contacting NTIS at the following address:

United States Department of Commerce

National Technical Information Service

5285 Port Royal Road

Springfield, Virginia 22161

Telephone: (703)487-4650 or 1-800-553-6847

D. Industrial and Governmental Documents

1. When a reference has a joint designation (e.g. ANSI/IEEE) these specifications generally cite the proponent organization (e.g. IEEE).

2. Addresses for obtaining industrial and governmental (other than Federal and

Bureau of Reclamation specifications and standards) specifications, standards, and codes are listed in table 01 42 10A - Addresses for Specifications, Standards, and

Codes.

Table 01 42 10A - Addresses for Specifications, Standards, and Codes

Acronym Name and Address Telephone

ABMA American Bearing Manufacturers Association

2025 M Street NW Suite 800

Washington DC 20036-3309 www.americanbearings.org

(202) 367-1155

AISC American Institute of Steel Construction

One East Wacker Dr., Suite 3100

Chicago, IL 60601-2001 www.aisc.org

(312) 670-2400

ANSI American National Standards Institute

1819 L. Street, N.W.

Washington, DC 20036 www.ansi.org

(202) 293-8020 http://www.americanbearings.org/ http://www.aisc.org/ http://www.ansi.org/

01 42 10 - 3

Table 01 42 10A - Addresses for Specifications, Standards, and Codes

Acronym Name and Address Telephone

ASME American Society of Mechanical Engineers

3 Park Ave.

New York, NY 10016-5990 www.asme.org

(800) 843-2763

ASTM ASTM International

100 Barr Harbor Dr.

West Conshohocken, PA 19428-2959 www.astm.org

(601) 832-9585

AWS American Welding Society

550 NW LeJeune Rd.

Miami, FL 33126 www.amweld.org

(800) 443-9353

(305) 443-9353

HI Hydraulic Institute

6 Campus Drive

First Floor North

Parippany, NJ 07054-4406 www.pumps.org

(973) 267 9700

IEEE Institute of Electrical and Electronics Engineers

3 Park Ave.,17th Floor

New York, NY 10016-5997 www.ieee.org

(212) 419-7900

ISO International Organization for Standardization

1, ch.de la Voic-Crense

CP 56

CH-1211 Geneva, Switzerland www.iso.org

+41 22 749 01 11

NACE NACE International

1440 South Creek Drive

Houston, TX 77084 www.nace.org

(281) 228-6200

NEMA National Electrical Manufacturers Association

1300 N 17th St., Suite 1847

Rosslyn, VA 22209 www.nema.org

(703) 841-3200 http://www.asme.org/ http://www.astm.org/ http://www.amweld.org/ http://www.pumps.org/ http://www.ieee.org/ http://www.iso.org/ http://www.nace.org/ http://www.nema.org/

01 42 10 - 4

Table 01 42 10A - Addresses for Specifications, Standards, and Codes

Acronym Name and Address Telephone

NFPA National Fire Protection Association

One Batterymarch Park

P.O. Box 9101

Quincy, MA 02269-9101 www.nfpa.org

(800) 344-3555

(617) 770-3000

SAE Society of Automotive Engineers

400 Commonwealth Drive

Warrendale, PA 15096-0001 www.sae.org

(724) 776 4841

SSPC SSPC: The Society for Protective Coatings

40 24th St., 6th Floor

Pittsburgh, PA 15222-4656 www.sspc.org

(800) 837-8303

(412) 281-2331

UL Underwriters Laboratories Inc.

333 Pfingsten Rd.

Northbrook, IL 60062-2096 www.ul.com

(847) 272-8800

PART 2 PRODUCTS

PART 3 EXECUTION

Not Used

END OF SECTION

http://www.nfpa.org/ http://www.sae.org/ http://www.sspc.org/ http://www.ul.com/

Product Requirements

01 60 00 - 1

SECTION 01 60 00

PRODUCT REQUIREMENTS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. When the schedule includes a separate item for furnishing a material, include cost of furnishing, hauling, storing, and handling in the price offered in the schedule for the item.

2. When the schedule does not included a separate item for furnishing a material, include cost of furnishing, hauling, storing, and handling in the price offered in the schedule for work for which the material is required.

1.02 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME B1.1-2003 Unified Inch Screw Threads, (UN and UNR

Thread Form)

2. ASME B1.20.1-1983(2006) Pipe Threads, General Purpose, Inch

B. Bureau of Reclamation (USBR)

1. RSHS-2009 Reclamation Safety and Health Standards

1.03 DEFINITIONS

A. Essential Characteristics: As used in these specifications, the term "essential characteristics" is synonymous with the term "salient characteristics."

B. Salient Characteristics: Those qualities of an item essential to ensure that the intended use of the item can be satisfactorily realized.

1.04 DELIVERY, STORAGE, AND HANDLING

A. Transport and handle manufactured products in accordance with manufacturer's instructions.

B. Store and protect manufactured products in accordance with manufacturer's instructions and RSHS. Submit instructions from the manufacturer before delivery of materials to jobsite.

C. Remove and replace damaged items with new items.

01 60 00 - 2

D. Protect materials subject to adverse effects from moisture, sunlight, ultraviolet light, or weather until delivered to jobsite.

1.05 MAINTENANCE

A. None Used

1.06 WORKMANSHIP

A. Accurately manufacture and fabricate materials in accordance with best modern practice and requirements of these specifications, notwithstanding minor errors or omissions therein.

B. Use liberal factors of safety and adequate shock-absorbing features in designs, especially for parts subjected to variable stress or shock, including alternating or vibrating stress or shock.

C. Include provisions which prevent components from loosening for shock-absorbing features and parts subject to vibration.

1.07 SOURCE QUALITY ASSURANCE

A. Materials will be subject to inspection at any one or more of the following locations, as determined by the CO:

1. At place of production or manufacture.

2. At delivery point.

B. To allow sufficient time to provide for inspection, submit at time of issuance, copies of purchase orders, including drawings and other pertinent information, covering material on which inspection will be made as advised by the CO, or submit other evidence if such purchase orders are issued verbally or by letter.

C. Inspection of materials at any location specified above or waiving of inspection shall not be construed as being conclusive as to whether materials and equipment conform to contract requirements under the clause at FAR 52.246-12 "Inspection of Construction ," nor shall the Contractor be relieved thereby of the responsibility for furnishing materials meeting the requirements of these specifications.

PART 2 EXECUTION

2.01 INSTALLATION

NOT USED

01 60 00 - 3

2.02 FIELD QUALITY ASSURANCE

Project Record Documents

01 78 30 - 1

SECTION 01 78 30

PROJECT RECORD DOCUMENTS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the schedule for other items of work.

1.02 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. Record Drawings as listed in the technical specifications

C. RSN 01 78 30-1, Warranties for individual purchased components and as described in the technical specifications.

1.03 WARRANTIES

A. Provide warranties in accordance with the technical specifications to meet the requirements of the specifications, and this section.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Project Record Documents

01 78 30 - 2

Pad-mounted Oil-filled Distribution Transformer

26 12 19 - 1

SECTION 26 12 19

PAD-MOUNTED OIL-FILLED DISTRIBUTION TRANSFORMER

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Medium-Voltage Pad-mounted Oil-filled Distribution Transformers:

1. Payment: Unit price offered in Schedule Section B.

1.02 REFERENCE STANDARDS

A. The transformer shall be designed, manufactured and tested to the applicable standards of the following:

1. Institute for Electrical and Electronics Engineers (IEEE)

2. National Electrical Manufacturers Association (NEMA)

3. National Fire Protection Association (NFPA)

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals and

Section 01 33 26 - Electrical Drawings and Data.

B. RSN 26 12 19-1 Shop Drawings and Manufacturer’s Data:

1. Shop Drawings.

a. Complete detailed, scaled drawings showing the equipment being furnished, with all pertinent information, including the following:

1) Dimensions and locations of conduit entrance windows.

b. Complete nameplate schedule.

2. Manufacturer’s Data.

a. Complete installation instructions.

b. Complete storage and handling instructions.

c. KVA rating, including derating calculations.

d. Primary / Secondary connections.

e. Primary voltage and available taps.

f. Secondary voltage.

g. BIL rating.

h. %Z, %X, %R, X/R.

26 12 19 - 2

i. Rise temperature

j. Gross weight.

k. Torque values for all bolted connections for secondary cable connections.

l. MANUFACTURER'S suggested hi-potential test procedures and test levels for field testing.

3. Manufacturer’s standard warranty.

C. RSN 26 12 19-2, Certified Factory Test Reports for requirements specified in Section

2.03 below.

D. RSN 26 12 19-3, Operation and Maintenance Instruction Book with the following:

1. Recommended periodic maintenance requirements.

2. Maintenance instructions including schedules, parts identification, troubleshooting, assembly instructions, parts list and predicted life of parts subject to wear and deterioration.

3. Recommended field test levels and procedures prior to installation, and for maintenance purposes after being placed in service.

4. Periodic and preventative maintenance torque values for all bolts.

5. Copies of factory test reports.

E. RSN 26 12 19-4, Record Drawings.

1.04 SYSTEM DESCRIPTION

A. Transformer is an oil-filled pad-mounted compartmentalized distribution type.

B. Primary terminations connected to 2.4kV fusible load-interrupter switch with medium-voltage cables.

C. Secondary terminations connected to MLO switchboard with low-voltage cables.

1.05 DELIVERY, STORAGE, AND HANDLING

A. Handle and deliver the transformer per the MANUFACTURER’s recommendations.

B. Offloading will be by OTHERS.

1.06 WARRANTY

A. Warrant equipment free of defects in material and workmanship per Manufacture’s standard warranty period (typically 1 year or 18 months) from first energizing.

B. All materials and equipment shall be guaranteed against defective materials, design and workmanship.

26 12 19 - 3

C. During the warranty period, the equipment supplier or his authorized dealer will be required to make the necessary repairs or replacements on site.

D. Warranties which mention that the part must be returned to the factory will not be acceptable.

E. During the warranty period, the CO will not accept charges for

1. Travel time.

2. Mileage.

3. On-site repair labor.

F. Warranty shall list any and all items excluded.

G. If necessary, as determined by the CO, any repairs must be made on a premium time basis without cost to the CO.

PART 2 PRODUCTS

2.01 MANUFACTURERS

A. Acceptable manufacturers:

1. ABB

2. General Electric GE.

3. Eaton/Cutler Hammer.

4. Square D

5. Or equal.

2.02 TRANSFORMER

A. Quantity required: Two (2)

B. General Construction:

1. The transformer and associated terminal compartments shall be so designed and constructed as to be tamper- resistant. There shall be no screws, bolts, or other devices which are externally removable.

C. Ratings:

1. 750kVA.

2. 3-phase, 60-hertz.

3. Primary voltage: 2.4-kV delta connection.

4. Secondary voltage: 480Y/277 volt wye connection.

26 12 19 - 4

5. BIL: as required by ANSI C57 for the primary voltage rating.

6. Impedance: Manufacturer’s standard.

7. Transformer shall be rated for 55°/65°C rise, 750kVA at 55°C, 840kVA at 65°C.

8. Suitable for continuous operation at full load as shown at the project location and elevation after applying any derating factors.

D. Winding Features:

1. Windings: Copper.

2. Four 2-1/2 percent, high-voltage taps, 2 above and 2 below normal rated voltage, at rated kVA capacity.

3. With de-energized tap changer externally operable.

E. Components

1. Terminal compartments.

a. Full-height, air filled primary and secondary terminal compartments with hinged doors shall be located side-by- side separated by a steel barrier, with the primary compartment on the left.

b. To facilitate making connections and permit cable pulling, the doors and compartment hood shall be removable. Removable door sill on compartments shall be provided to permit rolling or skidding of unit into place over conduit stubs in foundations.

c. The doors in both the high voltage section and the low voltage section shall be able to be latched in the open position.

d. The entire terminal compartment for the transformer shall be bolted to the transformer so that the terminal compartment may be unbolted from the transformer and the transformer removed without disturbing conduits that enter the compartment from the side or top.

e. The terminal compartments shall be a minimum of 36" deep.

f. Secondary compartment.

1) The secondary compartment shall enclose the low voltage bushings and provide for incoming cable from below the compartment.

2) This compartment shall also house:

a) Liquid level indicator.

b) Drain valve with sampling device.

c) Dial type thermometer.

d) Pressure relief valve.

e) Vacuum pressure gauge.

26 12 19 - 5

3) Door to low voltage section shall have a three point latching mechanism with pad-locking provision.

g. Primary compartment.

1) The primary line compartment shall enclose the high voltage bushings and provide for incoming cables from below the compartment.

2) This compartment shall also house:

a) No-load tap changer.

b) Parking stands for 3 elbows.

3) The primary compartment shall be accessible only after the door for the secondary compartment has been opened. The door shall be held closed by a captive bolt, access to this bolt shall be provided only when the door to the low voltage section is opened.

h. Primary terminals.

1) Shall be dead front construction, conforming with ANSI

C57.12.26, utilizing high voltage elbows for connections to primary cable and lightning arrestors.

2) Radial feed terminal arrangement with 3 bushing wells.

i. Secondary terminals.

1) Four low voltage, spade bushings with 2 holes for each cable, conforming with ANSI C57.12.26.

2) The low voltage bushings shall be extended as necessary to accommodate four (4) 500kcmil conductors per phase. Extension

(if required) shall be via a fully rated, silver (tin) plated, copper, bus system braced to withstand the available fault current.

3) Neutral brought out through an insulated bushing and externally grounded to the tank with a removable ground strap.

F. Accessories

1. Dial type thermometer.

a. Direct stem mounted in a closed well so that the thermometer can be removed without breaking the tank seal.

1) The well shall be threaded into a fitting that is welded to the transformer tank wall.

b. The thermometer shall have a slave hand which is moved by the indicating hand to indicate maximum oil temperature. The slave hand shall be externally resettable.

2. Sampling device.

26 12 19 - 6

a. This device shall allow for quick and easy sampling of the transformer oil.

b. The sampling device shall be threaded into a fitting that is welded to the transformer tank wall.

3. Liquid level gauge.

a. Dial type liquid level gauge.

4. Vacuum pressure gauge.

5. Pressure relief device.

a. A pressure relief device shall be located in the air space in the transformer tank to provide a method of relieving internal tank pressure.

b. Self-relieving.

c. Indicating.

6. Nameplates

a. Provide complete nameplates identifying equipment, caution, voltage, etc.

1) Provide complete nameplates for both inside and outside of the transformer terminal compartments.

G. Finish: Manufacturer’s standard grey coating.

2.03 CONTRACTOR SOURCE QUALITY TESTING

A. The following factory tests shall be performed in accordance with ANSI/IEEE C57.12.90:

1. Routine tests as identified in ANSI/IEEE C57.12.00.

2. Insulation resistance.

3. Insulation power factor.

PART 3 EXECUTION

5-kV Metal-Enclosed Switchgear

26 13 10 - 1

SECTION 26 13 10

5-KV METAL-ENCLOSED SWITCHGEAR

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. 5-kV Metal-Enclosed Switchgear:

1. Payment: Unit price offered in Schedule B.

1.02 REFERENCE STANDARDS

A. Institute of Electrical and Electronics Engineers (IEEE)

1. IEEE C37.20.3-2001 Metal-Enclosed Interrupter Switchgear

B. National Equipment Manufacturers Association (NEMA)

1. NEMA FU 1-2002 Low Voltage Cartridge Fuses

C. National Fire Protection Association (NFPA)

1. NFPA 70-2014 National Electrical Code (NEC)

1.03 DESIGN REQUIREMENTS

A. Design layout of switchgear vertical section to be installed in space shown on drawings.

B. Design switchgear to be close-coupled to existing Siemens Series 81000 2.4kV motor control center without using a transition section.

1.04 SUBMITTALS

A. Submit in accordance with Section 01 33 00 - Submittals and Section 01 33 26 -

Electrical Drawings and Data.

B. RSN 26 13 10-1, Approval Data:

1. Manufacturer's technical data.

2. Total weight of switchgear assembly.

3. Dimensioned equipment layout diagrams.

4. Nameplate list.

5. Bill of materials.

6. Time-Current Characteristic Curves.

7. Manufacturer’s standard warranty.

26 13 10 - 2

C. RSN 26 13 10-2, Approval Drawings.

D. RSN 26 13 10-3, Certified Factory Test Reports:

1. Manufacturer’s standard factory production tests.

E. RSN 26 13 10-4, Operation and Maintenance Instruction Book.

1.05 DELIVERY, STORAGE, AND HANDLING

A. Store indoors in a clean, dry space. Maintain factory wrapping or provide additional canvas or plastic cover to protect equipment from dirt, water, and construction debris.

B. Handle in accordance with manufacturer’s instructions and recommendations and in a manner to avoid damage to internal components, metal enclosure, and finish.

PART 2 PRODUCTS

2.01 FUSED LOAD INTERRUPTER SWITCH

A. Quantity required: Two (2) individual switch sections containing one (1) fused disconnect switch each for installation at two different plants.

B. Type: Three-pole gang operated switch with quick-make, quick-break spring mechanism.

C. The overall width of the new switchgear section cannot be more than 36 inches. Depth shall not exceed 36 inches.

D. Ratings:

1. Maximum voltage: 4.76 kV.

2. Basic impulse insulation level: 60 kV peak.

3. Continuous current: 600 amperes.

E. Speed of opening and closing independent of switch operator.

F. Separate main and break contacts to provide maximum endurance for fault close and load interrupting duty.

G. Provide insulating barriers between each phase and between switch and fuse compartment.

H. Operating Mechanism: Chain drive or mechanical linkage with two position handle.

I. Provide provisions for padlocking switch in OPEN position.

J. Provide permanent OPEN and CLOSED switch position indicators.

26 13 10 - 3

K. Provide inspection window in switch compartment door.

L. Blade position: Visible through door

M. Fuses:

1. Type: Medium-voltage, current limiting, rating 200E.

2. Accessible through separate door that is mechanically interlocked with load interrupter switch such that switch must be open before door is opened and switch cannot be closed with door open.

3. Positively held in position with provision for easy removal and replacement from front of enclosure without special tools.

N. Conform to IEEE C37.20.3.

2.02 FABRICATION

A. Close-coupling:

1. The new section will be close-coupled to a Siemens 81000 motor control center lineup. It must be constructed to bolt up with no transition section.

B. General:

1. Construct fused interrupter switches to consist of individual vertical sections that are bolted together to form a rigid switchgear assembly.

2. Provide access panels for inspections and maintenance of bus, wiring, and other apparatus.

3. Attach nameplates with pan head self-tapping screws. Use of adhesives is not acceptable.

2.03 FINISHES

A. Manufacturer’s standard grey finish.

2.04 CONTRACTOR SOURCE QUALITY TESTING

A. Load Interrupter Switch: Perform production tests specified in IEEE C37.20.3.

PART 3 EXECUTION

26 13 10 - 4

Distribution Panelboards

26 24 24 - 1

SECTION 26 24 24

SWITCHBOARDS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Distribution Switchboards:

1. Payment: Unit price offered in Schedule B.

1.02 REFERENCE STANDARDS

A. National Electrical Manufacturers Association (NEMA)

1. NEMA 250-2008 Enclosures for Electrical Equipment (1000 Volts

Maximum)

2. NEMA PB 2 Deadfront Distribution Switchboards

B. National Fire Protection Association (NFPA)

1. NFPA 70-2014 National Electrical Code (NEC)

C. Underwriters Laboratories, Inc. (UL)

1. UL 891 Switchboards

2. UL 489-2002 Molded-Case Circuit Breakers, Molded-Case Switches, and

Circuit-Breaker Enclosures

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals and Section 01 33

26 - Electrical Drawings and Data.

B. RSN 26 24 24-1, Shop Drawings and Manufacturer’s Data:

1. Manufacturer’s technical data.

2. Nameplate list.

3. Manufacturer’s standard warranty.

PART 2 PRODUCTS

2.01 DISTRIBUTION PANELBOARDS

A. Quantity required: Two (2) switchboards for installation in two different plants.

26 24 24 - 2

B. Enclosure: NEMA 250 Type 3R for outdoor installation. Manufactured from sheet steel with hinged door, three-point latch, padlockable.

C. Cables shall be bottom-entry and bottom-exit.

D. Ratings: 480V, three-phase, three-wire, 1,000A main bus, 65kAIC.

E. Solid neutral bus.

F. Bus Material: Copper.

G. Mains: Main lugs only.

H. Branch Circuits: Molded-case circuit breakers.

1. Qty. One (1), 3-pole, 150AT, LSIG

2. Qty. Two (2), 3-pole, 400AT, LSIG

I. Mounting: Outdoor, freestanding.

J. Neutral and ground bus provided with sufficient number of points to singularly terminate each individual conductor requiring a connection.

K. Accessories:

1. Copper ground bus.

2. Circuit Directory:

a. Show breaker number and connected load.

b. Use machine lettering for directory entries. Hand written directory entries are not acceptable.

c. Provide transparent cover for directory.

L. UL listed.

M. Finish: Manufacturer’s standard grey coating.

2.02 MOLDED CASE CIRCUIT BREAKER

A. Adjustable-trip, LSIG.

B. Voltage, Trip Rating, and Number of Poles: As specified.

C. Interrupting Rating: Not less than interrupting rating of panelboard.

D. Quick-make and quick-break toggle mechanisms.

E. Trip-free operating handle.

26 24 24 - 3

F. Single operating handle. Use of handle ties on multiple-pole circuit breakers is not acceptable.

G. Equip with padlock attachments for locking breakers in “OFF” position.

H. Conform to UL 489 and be UL listed.

2.03 FABRICATION

A. Mount ground bus at bottom of panelboard enclosure. Bond bus to enclosure.

B. Provide blank cover for unused panelboard spaces.

C. Mount circuit directory on inside of door.

PART 3 EXECUTION

26 24 24 - 4

Low-Voltage Variable Frequency Drive Systems

26 29 23 - 1

SECTION 26 29 23

LOW-VOLTAGE VARIABLE FREQUENCY DRIVE SYSTEMS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Low-Voltage Variable Frequency Drive Systems:

1. Payment: Unit price offered in Schedule Section B.

1.02 REFERENCE STANDARDS

A. Institute of Electrical and Electronics Engineers (IEEE)

1. IEEE C 62.41.1-2002 Surge Environment in Low-Voltage (100V and less)

AC Power Circuits

2. IEEE 519 Guide for Harmonic Control and Reactive

Compensation of Static Power Converters

B. National Electrical Manufacturers Association (NEMA)

1. NEMA ICS 6 Industrial Control Systems and Enclosures

2. NEMA CP 1-2000(2008) Shunt Capacitors

3. NEMA MG 1-2006 Motors and Generators (with Revision 1, 2007)

C. National Fire Protection Association (NFPA)

1. NFPA 70 2014

1.03 DEFINITIONS

A. VFD: Variable frequency drive.

B. MPR: Motor protection relay.

C. MTBF: Mean time between failure

D. PWM: Pulse width modulation.

E. ROM: Read only memory.

F. RTD: Resistance temperature detector.

G. Rated Load: Load specified for the equipment.

H. Rated Speed: Nominal rated (100 percent) speed specified for the equipment.

I. TDD: Total demand distortion.

26 29 23 - 2

J. RVSS: Reduced-voltage solid-state motor starter.

K. THD: Total harmonic distortion.

L. Also as found in:

1. National Electrical Code.

2. Institute of Electrical and Electronic Engineers.

3. Instrument Society of America.

4. National Fire Protection Association.

1.04 SYSTEM DESCRIPTION

A. The MANUFACTURER will provide, per this specification and drawings, nine (9) drive units, each sized to operate squirrel cage induction pump motor as detailed in the table.

Each drive shall be equipped with an RVSS to provide soft-start capability and bypass the

VFD; this combination shall be referred to as the VFD unit, which shall be integrated into a single enclosure whose maximum footprint is given the drawings. The RVSS’s provide the system with a solid state starter for bypass reduced-voltage starting during variable frequency drive downtime. The drives shall be properly rated for the site altitude, 7,000 feet.

Location Horsepower Quantity

Pleasant View 250Hp 2

Ruin Canyon 250Hp 2

Cahone 400Hp 3

Dove Creek 200Hp 2

B. The VFDs shall be delivered in a staggered fashion. The drives for Pleasant View and

Ruin Canyon shall be delivered in the fall of 2015. The drives for Dove Creek shall be delivered in the fall of 2016. The drives for Cahone shall be delivered in the fall of 2017.

C. The VFD MANUFACTURER shall provide suitable equipment to ensure that no damage can occur to the motor as a result of standing waves, high carrier frequency, high levels of dv/dt, etc. Any changes that may need to be made in order to protect the equipment shall be made by the MANUFACTURER at no additional costs to the CO.

D. The MANUFACTURER shall provide guidance on the purchase of the new pump motors to determine compatibility of the new drive units and new motors. It is expected that this support will include reviewing motor data and making a recommendation to the CO as to the motor’s suitability.

26 29 23 - 3

E. Performance Requirements:

1. Input Power: 480V, three-phase, 60-hertz.

2. Output: 0- to 480-volt, three-phase, Pulse Width Modulated waveform suitable for variable frequency control of a squirrel cage induction motor.

3. Output Frequency: 0 to 66-hertz, (constant horsepower above 60-hertz).

4. Output Current: As indicated.

5. Overload Capability: 110 percent of full load for 1 minute every 10 minutes.

6. Minimum Efficiency: 96 percent at full load, full speed.

7. Input Power Factor: Minimum 95 percent for 20 to 100 percent load.

F. Design Requirements:

1. Drive System: Convert incoming three-phase, 60-hertz ac power to variable voltage, variable frequency output for variable speed operation of a standard ac induction squirrel-cage motor, using the pulse-width-modulation (PWM) technique to produce the variable frequency output.

2. Provide full bypass capability with RVSS starter.

3. System rated for continuous industrial duty and suitable for use with Standard

NEMA MG 1, Design B motors.

4. Incoming Line Circuit Breaker: Provide positive means of disconnecting incoming power, and overcurrent protection for the drive system.

5. Incoming Line Reactor or Choke: Design to minimize harmonic distortion on the incoming power feeder if required.

6. Protection from external transient voltages, e.g. lightning strike to the power system, switching surges, etc.

1.05 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals and

Section 01 33 26 - Electrical Drawings and Data.

B. RSN 26 29 23-1, Approval Data:

1. Overall drive system operating data, including efficiencies, input currents, and power factors, at driven equipment actual load and rated system input voltage, at

0, 40, 60, 80, 100, and 110 percent of rated speed.

2. Complete system rating, including all nameplate data, continuous operation load capability throughout speed range of 0 to 120 percent of rated speed.

3. Complete variable frequency controller rating coordinated with motor full load nameplate current rating; list any controller special features being supplied.

26 29 23 - 4

4. Controller, reactor, and isolating transformer (if applicable) dimensional drawings; information on size and location of space for incoming and outgoing conduit, shipping splits, and shipping weights.

5. Maximum heat dissipation from enclosure.

6. Layout of controller face showing pushbuttons, switches, instruments, indicating lights, etc.

7. Complete system operating description.

8. Complete system schematic, wiring, and interconnection diagrams.

9. Complete system interconnection diagrams between controller, drive motor, and all related components or controls external to system, including wire numbers and terminal board point identification.

10. One-line diagram of system, including component ratings.

11. Description of diagnostic features being provided.

12. Descriptive literature for all control devices such as relays, timers, etc.

13. Catalog cut sheets of major components.

14. Confirmation that the drive is sized for the full…

This is the start of the file's text. The full file is on GovTribe.