This solicitation requests quotes for a large wheel loader to be used in support of ballistic testing. Offerors are to provide pricing for the wheel loader as well as data items including an operator's manual and training certificates. The award will be made based on best value considering technical specifications of the proposed equipment, warranty coverage, and price. Quotes are due by July 15, 2020 and award is anticipated within 30 days thereafter. The wheel loader must meet requirements detailed in the statement of work. The Army Contracting Command - New Jersey at Picatinny Arsenal will evaluate proposals and make award without discussions to the responsible offeror providing the best overall value.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| CDRL_A001_Manuals_METC_LargeWheelLoader.pdf | ||
| CDRL_A002_SecurityTraining_METC_LargeWheelLoader.pdf | ||
| SOW_METC_LargeWheelLoader.docx | DOCX document | |
| Directions Eval Plan_METC_AEED_Wheel Loader.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quality Assurance Surveillance Plan (QASP) for Large Wheel Loader
| Performance Requirements |
| Performance |
Measure Performance Standard
Acceptable Performance Level
(APL)
Method of Surveillance Compliance (Exceeded, Met or Partially Met)
3.1.12 Operator’s Manual
CDRL A004
| Completeness |
| Contractor shall provide an Operator’s Manual that includes the necessary information regarding the LDM upgrade. |
| 100% Compliance |
| Received and tracked by COR |
4.2, 4.4, 4.8 Mandatory Training AT Level 1, iWATCH, and OPSEC Training
CDRL A002
Completeness
| Training Certificates from the contractor 30 days after contract award and annually thereafter. |
| 100% compliance |
| Received and tracked by COR |
4.3 Installation access & security policies/ procedures
| Completeness |
| Contractor shall report all incident reporting. As received. |
COR in coordination with the installation & organization Operations office.
| 100% compliance |
| Received and tracked by COR |