QASP.pdf
PDF 186 KB Posted
- Attached to
- Giant Voice Upgrade Federal contract opportunity
- Solicitation number
- HC101921R0006
- Issued by
- Defense Information Systems Agency
About this file
This document includes a Quality Assurance Surveillance Plan (QASP) and related appendices for the engineering, design, furnishing, installing, and testing of an upgraded Giant Voice turn-key system at Kunsan Air Base in Korea. The QASP outlines monitoring methods and performance standards to evaluate a contractor's upgrade of the existing Very High Frequency communication infrastructure to use the secured Astro 25 network. Monitoring will include periodic inspections and random sound level testing at defined distances from communication stacks to ensure intelligible emergency notifications. Contractors must meet a 90% acceptable quality level threshold. The appendices provide templates for performance reports, customer complaints, and corrective action reports. Related solicitation HC101921R0006 seeks proposals for the Giant Voice upgrade as a 100% small business set-aside for Service Disabled Veteran-Owned Small Businesses. Offers are due by July 16, 2020 to the Defense Information Systems Agency.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| HC101921R0006 Revision 2.pdf | ||
| KUNSAN GV PWS posted 18 Oct 2021.pdf | ||
| KUNSAN GV Q and As 18OCT21.pdf | ||
| Justification and Approval Redacted.pdf | ||
| HC101921R0006 Revision 1.pdf | ||
| DD254 Solicitation.pdf | ||
| DD254 Solicitation.pdf | ||
| ATTACHMENT- Fig. 1, Sound Coverage.pdf | ||
| ATTACHMENT- Fig. 3, Typical HAS 2432.pdf | ||
| ATTACHMENT- Fig. 2, Typical New-built HAS 9.pdf | ||
| HC101921R0006.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Encl 4, QASP
23Jun2017/v3
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
1. Contract or Task Order Title (Add contract/task order number at award): Kunsan AB Giant Voice Upgrade
2. Purpose:
This QASP provides a systematic method to evaluate performance for the stated contract. This QASP explains the following:
• What will be monitored?
• How monitoring will take place.
• Who will conduct the monitoring?
• How monitoring efforts and results will be documented.
This QASP does not detail how the contractor accomplishes the work. Rather, the QASP is created with the premise that the contractor is responsible for management and quality control actions to meet the terms of the contract. It is the Government’s responsibility to be objective, fair, and consistent in evaluating performance. In addition, the
QASP should recognize that unforeseen and uncontrollable situations may occur.
This QASP is a “living document” and the Government may review and revise it on a regular basis. Updates shall ensure that the QASP remains a valid, useful, and enforceable document. Copies of the original QASP and revisions shall be provided to the contractor and Government officials implementing surveillance activities.
3. Roles and Responsibilities:
The following personnel shall oversee and coordinate surveillance activities.
Program/Project Manager (PM) – The PM provides program oversight and supports the COR’s performance as-sessment activities.
Contracting Officer (KO) – The KO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The KO shall also ensure that the contractor receives impartial, fair, and equitable treatment under this contract. Determine the final assessment of the contractor’s performance.
Contracting Officer’s Representative (COR) – The COR is responsible for providing continuous technical over-sight of the contractor’s performance. The COR uses the QASP to conduct the oversight/surveillance process. The
COR shall keep a Quality Assurance file that accurately documents the contractor’s actual performance. The pur-pose is to ensure that the contractor meets the performance standards contained in the contract. The COR is respon-sible for reporting early identification of performance problems to the KO. The COR is required to provide an an-nual performance assessment to the KO which will be used in documenting past performance. The QASP is the pri-mary tool for documenting contractor performance. The COR is not empowered to make any contractual commit-ments or to authorize any contractual change on the Government’s behalf.
Subject Matter Expert (SME) – The SME will be a representative from the Radio Frequency (RF) transmissions shop and will work closely with the COR on determining the final performance meets the intent of the PWS.
4. Primary Method of Surveillance: Periodic Inspection and Random Sampling. The government will periodi-cally inspect the installation of the equipment. After all stacks are in place and operational, prior to the cut over from the old equipment, government representatives will post at random spots around the installation to hear a
“test count” over the live voice capability and a music/random tone to gage the audibility of the new stacks. A sound meter will be used to determine adequate decibel levels from a predefined distance. After a successful test, the cut over plan will be approved.
Surveillance Matrix
The Surveillance Matrix (Appendix 1) is the list of performance objectives and standards that must be performed by the contractor. This matrix details the method of surveillance the COR will use to validate and inspect these perfor-mance elements. Inspection of each element will be documented in the COR file.
Performance objectives define the desired outcomes. Performance Standards define the level of service required under the contract to successfully meet the performance objective. The inspection methodology defines how, when, and what will be assessed in measuring performance. The Government performance surveillance, using this QASP, to determine the quality of the contractor’s performance as it relates to the performance element standards. The
AQL performance Standard Table should be used to form the foundation of the COR’s inspection checklist.
5. Performance Standards: The nature of the Giant Voice is to adequately notify the base population of any emer-gencies (natural or manmade) that would impact day to day mission or operations tempo. The quality levels pre-sented in the surveillance matrix, if met, would meet the intent of the over-all function and design.
6. Documenting Performance:
Acceptable Performance.
The Government shall document positive performance. A Performance Assessment Report (PAR) template is at-tached (Appendix 2). Any report may become part of the supporting documentation for fixed price payments, award/incentive fee payments, Contractor Performance Assessment Reporting System (CPARS) entries, or other actions. Government acceptance of services permits the contractor to invoice for the service fee.
Unacceptable performance.
Unacceptable contractor performance can be identified by customer complaints (Appendix 3) or upon schedule sur-veillance evaluations. When unacceptable performance occurs, the COR shall inform the contractor. This will nor-mally be in writing unless circumstances necessitate verbal communication. The COR shall document the discus-sion and place it in the COR file and provide a copy to the KO.
When the COR determines formal written communication is required, the COR shall prepare a Corrective Action
Report (CAR). The CAR is forwarded to the KO for dissemination to the contractor. A CAR template is attached to this QASP (Appendix 4).
The contractor shall acknowledge receipt of the CAR in writing. The CAR will specify if the contractor is required to prepare a corrective action plan to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The CAR will also state how long after receipt the contractor has to present this corrective ac-tion plan to the KO and COR. The Government may withhold payment for services until corrective action is taken.
The Government shall review the contractor's corrective action plan to determine acceptability. Upon Government acceptance of the corrected services the contractor will be permitted to invoice for the service fee.
Any CAR may become a part of the supporting documentation for contract payment deductions, fixed fee deduc-tions, award fee nonpayment, CPARS or other actions deemed necessary by the KO.
7. Mandatory or regulatory compliance items: The contractor will provide initial proof of compliance with reg-ulatory and compliance items contained in the contract. The Contracting Officer's Representative (COR) and the
Contracting Officer (KO) will evaluate the initial submission and will conduct ad hoc reviews of the contractor's compliance throughout the remainder of the contract. The contractor will monitor compliance as required by FAR
52.222-50, Combating Trafficking in Persons, and report any issues to the KO.
8. Acceptable Quality Level (AQL): The AQL for this project is 90% of the Target criteria in the Surveillance
Matrix.
9. Evaluation Method: The COR will document the time of verbal notification to the contractor. The COR will document the official time and date of notification on the Maintenance Call Record. The COR will review self-diag-nostic systems logs, conduct a comparison with actual maintenance performance and otherwise verify and validate contractor performance. The contractor shall enter in the record the official time the system is restored to full opera-tional status. The COR will confirm the date and time of problem resolution in the record.
10. Performance Rating
In evaluating the quality of contractor’s performance, the following performance ratings may be used (same as
CPAR ratings).
Performance
Rating Criteria
Exceptional
Performance meets contractual requirements and exceeds many to the govern-ment’s benefits. The contractual performance of the element or sub-element being assessed was accomplished with no problems and contractor actions were highly ef-fective.
Very Good
Performance meets contractual requirements and exceeds some to the government benefits. The contractual performance was accomplished with few minor problems for which corrective actions taken by the contractor were effective.
Satisfactory
Performance meets contractual requirements. The contractual performance con-tains some minor problems for which corrective actions taken by the contractor were satisfactory.
Marginal
Performance does not meet some contractual requirements. The contractual perfor-mance reflects a serious problem for which the contractor has not yet identified cor-rective actions. The contractor’s proposed actions appear marginally effective or were not fully implemented.
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
Appendix 1 - Surveillance Matrix
Performance
Standards
Acceptable
Quality
Levels
Methods of
Calculation Surveillance Results/Ratings
The nature of the Giant
Voice is to ad-equately no-tify the base population of any emergen-cies (natural or manmade) that would im-pact day to day mission or operations tempo. The quality levels presented, if met, would meet the in-tent of the over-all func-tion and de-sign.
Target Criteria:
Below are ap-proximate dis-tances and deci-bel (dB) levels from any stack:
0 ft – 125 dB
300 ft – 105 dB
750 ft – 90 dB
1500 ft – 85 dB
2500 ft - 70 dB
Minimum Ac-ceptable:
0 ft – 113 dB
300 ft – 95 dB
750 ft – 81 dB
1500 ft – 74 dB
2500 ft - 63 dB
Calculation: A sound meter, pro-vided by the gov-ernment, will be used to measure the sound levels from approximate distances (± 10 % distance given).
The contractor is encouraged to provide their own sound meter as a second verifiable source of data. If there are any ma-jor (greater than
10%) discrepan-cies, an average between the two will be taken and recorded.
Measurement Interval:
After any stack has been replaced/upgraded/in-stalled a sound level will be recorded. Upon com-pletion of the controllers, another sound level will be measured.
Measurement Period:
Voice/tone testing will be limited to the duty hours of
0800 to 1700
Source of Measurement
Data: Sound meter pro-vided by the Bio Environ-mental shop, +82 063-470-
5417. If /when a sound meter is not available, a subjective hearing test will be conducted by members of the RF transmissions shop.
Timing of Measurement:
After installation of any stack equipment or control unit.
Reporting Frequency:
TBD during installation schedule
(Exceptional
Very Good
Satisfactory
Marginal
Unsatisfactory)
(A rollup of assess-ment of the Surveil-lance Inspection Re-sults to develop an overall rating for this objective)
Appendix 2 – Performance Assessment Report
PERFORMANCE ASSESSMENT REPORT (PAR)
(If more space is needed, use reverse and identify by number)
1. CONTRACT/TASK ORDER
NUMBER
2. CONTRACTOR 3. TYPE OF SERVICES
4. QUALITY ASSURANCE PERSONNEL (COR) SIGNATURE AND DATE
5. COR PHONE 6. SUSPENSE DATE
I. PERFORMANCE
7. DEFICIENCY (CHECK ALL BOXES THAT
APPLY)
NEW
REPEAT
NO DEFICIENCY NOTED
8. SERVICES SUMMARY or PWS PARAGRAPH ITEM
REVIEWED
9. BRIEF DESCRIPTION OF DEFICIENCY (IF DEFICIENCY
BOX WAS CHECKED)
10. DETAILED PERFORMANCE ASSESSMENT
II. CONTRACTOR VALIDATION
11. CONTRACTOR REPRESENTATIVE CONCUR
NON-CONCUR
12. CORRECTIVE ACTION ESTIMATED COMPLETION
DATE
13. CONTRACTOR REPRESENTATIVE CORRECTIVE ACTION AND PREVENTION OF RECURRENCE OR REASON
FOR NON-CONCURRENCE OF COR CITED DEFICIENCY
III. ACTION CORRECTED
14. CONCUR NON-CONCUR COR SIGNATURE AND DATE
15. COR REMARKS (REQUIRED)
6. CONTRACTOR REPRESENTATIVE REMARKS
Appendix 3 – Customer Complaint Record
CUSTOMER COMPLAINT RECORD
DATE/TIME OF COMPLAINT
SOURCE OF COMPLAINT
ORGANIZATION
BUILDING NUM-
BER
INDIVIDUAL
PHONE NUMBER
NATURE OF COMPLAINT
CONTRACT REFERENCE
VALIDATION
DATE/TIME CONTRACTOR INFORMED OF COMPLAINT
ACTION TAKEN BY CONTRACTOR
RECEIVED/VALIDATED BY
Appendix 4 – Corrective Action Report
CORRECTIVE ACTION REPORT (CAR)
(If more space is needed, use reverse and identify by number)
1. CONTRACTOR
2. CONTRACT NUMBER
3. TYPE OF SERVICES
4. FUNCTIONAL AREA
5. SUSPENSE DATE
6. CONTROL NUMBER
7. DEFICIENCY MAJOR MINOR
FINDING:
FINDING IMPACT:
Please respond with a written corrective action plan that details the corrective action of the cited deficiency, the cause of the defi-ciency, and actions taken to prevent recurrence by Suspense Date in Block 5. If date was not entered in Block 5, the contractor is not required to provide a response.
8. QUALITY ASSURANCE PERSONNEL (COR)
TYPED NAME AND GRADE
SIGNATURE AND DATE
9. ISSUING AUTHORITY
TYPED NAME AND GRADE
SIGNATURE AND DATE
10. COR RESPONSE TO CONTRACTOR CORRECTIVE ACTION AND ACTION TAKEN TO PREVENT RECURRENCE
11. COR DETERMINATION
ACCEPTED REJECTED
12. CLOSE DATE