The document is a Price Schedule for a trail resurfacing project at Hopewell Culture National Historical Park in Chillicothe, Ohio. The pricing template shows line items for materials and labor for trail resurfacing, with columns for unit, quantity, price per unit, and subtotal, though the specific pricing cells are currently blank.
The related federal contract opportunity (Solicitation Number 140P6425Q0028) is a small business set-aside project valued between $25,000 and $100,000, targeted for award by June 2025. The project requires repairing and resurfacing approximately 2,100 linear feet of the Adena trail, including crack repair, patching asphalt, seal coating approximately 48,500 square feet of pavement, and implementing specific crack filling techniques. The contract will be firm-fixed price, with evaluation factors including technical merit, past experience, and pricing. Contractors must be registered in SAM, have a UEI number, and comply with construction wage rate requirements for Ross County, Ohio. The full solicitation will be posted on SAM.gov in April 2025, with performance expected to begin in June 2025.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Notice_to_Contractors.pdf | ||
| Construction_Contract_Administration.pdf | ||
| Submittals.pdf | ||
| Sol_140P6425Q0028.pdf | ||
| Wage_Determination.pdf | ||
| Statement_of_Work.pdf | ||
| Provisions_to_be_Completed.pdf | ||
| Price_Schedule.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| U.S. Department of Interior | Hopewell Culture | 16062 State Route 104 |
| National Park Service | National Historical Park | Chillicothe, OH 45601 |
| PROJECT: Resurface Trail | ||||
| Price Schedule | ||||
| Unit | Quantity | Price/ Unit | Subtotal | |
| Painting | ||||
| Resurface Trail Materials | LS | 1 | $ - 0 | |
| Resurface Trail Labor | LS | 1 | $ - 0 | |
| Subtotal | $ - 0 |
| Overhead | % | $ - 0 |
| Profit | % | $ - 0 |
| Bonds | % | $ - 0 |
| Grand Total | $ - 0 |