Performance Specifications-W912EQ20B0004.pdf
PDF 574 KB Posted
- Attached to
- Ditch 251 Lower Channel Cleanout Federal contract opportunity
- Solicitation number
- W912EQ20B0004
About this file
This is a solicitation for a federal construction contract to perform ditch cleaning and related work. The solicitation seeks clearing, snagging, excavation, disposal, seeding, mulching and other services along Ditch 251 from station 2+13 to 1129+63 in Dunklin and Pemiscot Counties, Missouri. The work will be divided into phases including a base contract and optional additional sections. The estimated value is between $5 million and $10 million. This is a Service-Disabled Veteran Owned Small Business set-aside procurement using sealed bid procedures. The NAICS code is 237990. Offers must be registered in SAM to receive an award. The agency is the Department of the Army Corps of Engineers Engineering District Memphis. Additional details are available by contacting the named representative.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract of Bids.pdf | ||
| Amendment 2.pdf | ||
| Performance Specifications-Updated-W912EQ20B0004.pdf | ||
| Amendment 1.pdf | ||
| Drawing-Plans.pdf | ||
| Solicitation-W912EQ20B0004..pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00.00 11 SUMMARY OF WORK
01 22 00.00 11 MEASUREMENT AND PAYMENT
01 33 00 SUBMITTAL PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.00 11 CONTRACTOR QUALITY CONTROL
01 57 20.00 11 ENVIRONMENTAL PROTECTION
01 57 25.00 11 STORM WATER POLLUTION PREVENTION PLAN
01 58 01.00 11 PROJECT SIGNS, BARRICADES, AND TRAFFIC CONTROL SIGNS
DIVISION 31 - EARTHWORK
31 11 00.00 11 CLEARING AND SNAGGING
31 23 00.00 11 CHANNEL CLEANOUT EXCAVATION
31 24 00.00 12 EMBANKMENT
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 92 35.00 13 SEEDING AND MULCHING - SOUTHEAST MO (LRDD)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
Ditch 251 (Unimproved) Channel Cleanout D251UCHANCO
SECTION 01 11 00.00 11 Page 1
SECTION TABLE OF CONTENTS
SECTION 01 11 00.00 11
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
1.1.2 Location
1.2 EXISTING WORK
1.3 LOCATION OF UNDERGROUND FACILITIES
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
SECTION 01 11 00.00 11 Page 2
SECTION 01 11 00.00 11
SUMMARY OF WORK
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work consists of furnishing all plant, labor and materials for clearing
& snagging, top bank shaping, channel excavation, disposal of excavated materials, and seeding & mulching for Ditch 251 (Unimproved) Cleanout and any incidental related work according to the specifications and plans. The project limits are CL STA 2+13 to STA 1129+63 as shown on the plans. The estimated value of the work is between $5,000,000 and $10,000,000. The work shall be divided into phases:
Base Contract: CL STA 2+13 to STA 341+71 - Clearing & Snagging and Channel
Cleanout
Option 1: CL STA 341+71 to STA 886+75 - Clearing & Snagging
Option 2: CL STA 341+71 to STA 886+75 - Channel Cleanout
Option 3: CL STA 886+75 to STA 1129+63 - Clearing & Snagging
Option 4: CL STA 886+75 to STA 1129+63 - Channel Cleanout.
Prior to construction completion of the Base Contract, determination will be made whether to award either Option 1 or Options 1 and 2. Prior to construction completion of Option 1 (or Options 1 and 2), determination will made whether to award either Option 3 or Options 3 and 4.
1.1.2 Location
The work shall be located in Dunklin & Pemiscot Counties, Missouri, within the Little River Floodway. The exact location will be indicated on the contract drawings. The Contracting Officer's Representative will be available to show the exact location of the work at the two organized site visits.
1.2 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
SECTION 01 11 00.00 11 Page 3
1.3 LOCATION OF UNDERGROUND FACILITIES
Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated to be installed or removed, but indicated or discovered during work to be conducted or installed. For further instructions and details, see the paragraph entitled, "OBSTRUCTIONS" in Section 00 80 00.00 11 SPECIAL CONTRACT REQUIREMENTS.
PART 2 PRODUCTS (Not Used)
-- End of Section --
SECTION 01 22 00.00 11 Page 1
SECTION 01 22 00.00 11
MEASUREMENT AND PAYMENT
1.1 JOB PAYMENT ITEMS
1.1.1 Mobilization and Demobilization
1.1.2 Environmental Protection
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 Storm Water Pollution Prevention
1.2.1.1 Write/Amend and Maintain SWPPP
1.2.1.2 Erosion Control Berm
1.2.1.3 Construction Entrance/Exit
1.2.2 Clearing and Snagging
1.2.3 (NOT USED)
1.2.4 Channel Excavation
1.2.5
1.2.6 Seeding and Mulchinge
SECTION 01 22 00.00 11 Page 2
SECTION 01 22 00.00 11
MEASUREMENT AND PAYMENT
1.1 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 Mobilization and Demobilization
a. Payment
Payment will be made for costs associated with mobilization and demobilization, as defined in Contract Clauses PAYMENT FOR
MOBILIZATION AND DEMOBILIZATION.
b. Unit of measure, Job: JA
1.1.2 Environmental Protection
a. Measurement
No measurement will be made for Environmental Protection.
b. Payment
Payment will be made for costs associated with operations necessary for environmental protection as specified in Section 01 57 20.00 11
ENVIRONMENTAL PROTECTION. This price and payment shall be considered full compensation for furnishing all plant, labor, materials, and equipment and for performing all operations necessary for
"Environmental Protection." This price and payment does not include those items covered under "Storm Water Pollution Prevention;" however, it does include items incidental thereto. The Contractor shall be responsible for payment of fees associated with environmental permits, application, and/or notices obtained by the Contractor. The
Contractor shall be responsible for payment of all fines/fees arriving from violation or non-compliance with Federal, State, Regional, and local laws or regulations. The Government will not provide any compensation for payments of fines/fees, in the event that fines/fees are incurred by the Contractor.
c. Unit of measure, Job: JA
SECTION 01 22 00.00 11 Page 3
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract for which unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, meeting safety requirements, tests and reports, and for performing all related work required for which separate payment is not otherwise provided.
1.2.1 Storm Water Pollution Prevention
No separate measurement or payment will be made for the work "Storm Water
Pollution Prevention" required by Section 01 57 25.00 11 STORM WATER
POLLUTION PREVENTION PLAN (SWPPP) except as described in the paragraphs
WRITE/AMEND AND MAINTAIN SWPPP, EROSION CONTROL BERM OR EQUIVALENT, and
CONSTRUCTION ENTRANCE/EXIT below. Any additional costs associated with
Storm Water Pollution Prevention, other than these listed, shall be included in the contract price under Environmental Protection. The
Government will pay all costs for the "Storm Water Pollution Prevention" at the contract unit price for each sub-item list below as follows:
(1) Sixty percent of the unit price upon completion of the installation.
(2) The remaining 40 percent throughout the contract life, with a maximum of 20 percent being retained until final removal and cleanup of the premises.
The Contracting Officer will require the Contractor to furnish cost data to calculate the exact percentage to be paid upon installation.
1.2.1.1 Write/Amend and Maintain SWPPP
No measurement will be made for Write/Amend and Maintain SWPPP.
Payment for development of, amending as required, and maintaining the
SWPPP will be made at the contract unit price for "Write/Amend and
Maintain SWPPP." Price and payment shall constitute full compensation for furnishing all plant, labor, materials and equipment to complete the work, according to Section 01 57 25.00 11 STORM WATER POLLUTION
PREVENTION PLAN, of writing, amending as needed, and maintaining the
SWPPP for erosion prevention and sediment control throughout the project duration, submitting the SWPPP to the USACE Contracting
Officer for approval, conducting any and all inspections, submitting all appropriate reports to the USACE Contracting Officer, and all other operations incidental thereto for the duration of the construction project.Payment will not be made for any permit application rejected or revision of the SWPPP required by the governing body. SWPPP will be written and implemented in accordance with all rules and regulations outlined by USACE specifications, the
Missouri State Operating Permit for stormwater pollution prevention, and the National Pollution Discharge Elimination System (NPDES)
SECTION 01 22 00.00 11 Page 4 permit. No notice by the contractor to MO DNR is required. The
Contractor shall implement the stormwater requirements according to the Corps specifications and SWPPP, modify and maintain the SWPPP throughout the project, conduct the stormwater inspections, and submit the appropriate reports to the Contracting Officer.
c. Unit of measure, Each: EA.
1.2.1.2 Erosion Control Berm
Measurement for Erosion Control Berm satisfactorily placed will be made by the linear foot.
Payment for Erosion Control Berm or equivalent as specified herein will be made at the contract unit price per linear foot for "Erosion
Control Berm or Equivalent" as broken down by the percentages in the
"sub-item list" above. Price and payment shall constitute full compensation for furnishing all plant, labor, materials and equipment, and performing all operations necessary for the installation and maintenance of the Erosion Control Berm throughout the contract period, including final dressing and cleanup. Lateral or point erosion control structures such as check dams will be considered incidental to this item. No additional payment will be made when other measures are used in lieu of the measures or Best Management Practices (BMPs) indicated in the plans and specifications.
c. Unit of measure, Linear Foot: LF.
1.2.1.3 Construction Entrance/Exit
Measurement for Construction Entrance/Exit will be for each constructed and maintained by the Contractor during construction and completely removed by the Contractor at the completion of construction.
Payment for the Construction Entrance/Exit as specified herein will be made at the contract unit price per each "Construction Entrance/Exit."
Price and payment shall constitute full compensation for furnishing all plant, labor, equipment, traffic control measures, and for performing all operations necessary for the installation and maintenance of the Construction Entrance/Exit throughout the contract period, including final removal, dressing, and cleanup.
c. Unit of measure, Each: EA.
1.2.2 Clearing and Snagging
Measurement for satisfactory Clearing and Snagging as specified in
SECTION 01 22 00.00 11 Page 5
SECTION 31 11 00.00 11 - CLEARING shall be made by the 100 Linear Feet.
No reduction of the contract quantity will be made for locations within the specified areas to be cleared which require no clearing or which are partly cleared. No allowance will be made for clearing outside of the limits indicated in the drawings. Additional clearing required for construction operations shall be considered incidental.
Payment for Clearing and Snagging, measured as prescribed above, will be made at the contract unit price per centerline station for
"Clearing and Snagging", which price and payment shall constitute full compensation for furnishing all materials, equipment, and labor and for performing all operations as necessary for clearing, snagging, painting, burning, and removal as specified in 31 11 00.00 11 within the limits indicated in the drawings. No additional payment shall be made for incidental clearing required for construction operations or clearing outside of the limits indicated in the drawings.
c. Unit of measure, 100 Linear Feet: HL.
1.2.3 (NOT USED)
1.2.4 Channel Excavation
Measurement for Channel Excavation as specified in SECTION 31 23 00.00
11 - CHANNEL EXCAVATION shall be made by the cubic yard. The
Contractor shall provide as-built cross sections in accordance with the CONTRACT CLAUSES entitled "Quantity Surveys." The Government will use these sections to ensure the design grade and sections between right top bank and left top bank have been met in accordance with the plans and specifications. No reduction of the contract quantity will be made for locations within the specified areas to be excavated which require no excavation for channel cleanout or which are partly cleaned out. No allowance will be made for over-depth excavation, for the removal of any material outside of the required side slope lines, nor for additional surveys for the removal of shoaling as specified in
SECTION 31 23 00.00 11 - CHANNEL EXCAVATION in the paragraph entitled
SLIDES & SHOALS, except as indicated in SECTION 31 23 00.00 11 -
CHANNEL EXCAVATION in the paragraph entitled EXISTING CHANNEL.
Payment for Channel Excavation, measured as prescribed above, will be made at the contract unit price per cubic yard for "Channel
Excavation", which price and payment shall constitute full compensation for furnishing all materials, equipment, and labor and for performing all operations as necessary for excavation of the channel (between right top bank and left top bank) and inlet ditches, disposal of excavated material including construction of structures for the control of excavated material, drifting/hauling of excavated material to meet Excavated Material Embankment design sections; and/or relocation of excavation equipment as construction progresses, and all other operations incidental thereto as specified in SECTION 31 23
00.00 11 - CHANNEL EXCAVATION.
c. Unit of measure, cubic yard: CY.
1.2.5 (NOT USED)
1.2.6 Seeding and Mulchinge
Measurement for Seeding and Mulching as specified in SECTION 32 92
35.00 13 - SEEDING AND MULCHING - SOUTHEAST MO (LRDD) shall be made by the 100 Linear Feet.
Payment for Seeding and Mulching satisfactorily placed, measured as prescribed above, will be made at the contract unit price per station for "Seeding and Mulching", which price and payment shall constitute full compensation for furnishing all materials, equipment, and labor and for performing all operations as necessary for seeding and mulching all locations throughout the contract denuded of vegetation and/or ground cover.
c. Unit of measure, 100 Linear Feet: HL.
SECTION 01 22 00.00 11 Page 6
SECTION 01 33 00 Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
1.1 DEFINITIONS
1.1.1 Submittal
1.1.2 Submittal Descriptions (SD)
1.1.3 Approving Authority
1.1.4 Work
1.2 SUBMITTALS
1.3 SUBMITTAL REGISTER
1.4 CONTRACTOR USE OF SUBMITTAL REGISTER
1.5 APPROVING AUTHORITY USE OF SUBMITTAL REGISTER
1.6 COPIES DELIVERED TO THE GOVERNMENT
1.7 PROCEDURES FOR SUBMITTALS
1.7.1 Reviewing, Certifying, Approving Authority
1.7.2 Constraints
1.7.3 Scheduling
1.7.4 Variations
1.8 CONTRACTOR'S RESPONSIBILITIES
1.9 FORMAT OF SUBMITTALS
1.9.1 Transmittal Sheet
1.9.2 Identifying Submittals
1.10 SUBMISSION AND CONTROL OF SUBMITTALS
1.10.1 Submittals Required from the Contractor
1.10.1.1 Submittal Procedures and Deviations
1.10.1.2 Control of Submittals
1.10.1.3 O&M Data
1.11 SUBMITTAL CLASSIFICATION
1.11.1 Government Approved
1.11.2 Information Only
1.12 APPROVED SUBMITTALS
1.13 DISAPPROVED SUBMITTALS
1.14 GENERAL
1.15 SUBMITTAL REGISTER
1.16 SCHEDULING
1.17 TRANSMITTAL SHEET (ENG FORM 4025)
1.18 GOVERNMENT APPROVED SUBMITTALS
1.19 INFORMATION ONLY SUBMITTALS
1.20 STAMPS
SECTION 01 33 00 Page 3
SECTION 01 33 00
SUBMITTAL PROCEDURES
1.1 DEFINITIONS
1.1.1 Submittal
Contract Clauses "FAR 52.236-5, Material and Workmanship," paragraph (b) and "FAR 52.236-21, Specifications and Drawings for Construction," paragraphs (d), (e), and (f) apply to all "submittals."
1.1.2 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by SD numbers and titles as follows.
SD-01 Preconstruction Submittals
Certificates of Insurance.
Surety Bonds.
Construction Progress Schedule.
Work Plan.
SUBMITTAL REGISTER
Schedule of Prices.
Accident Prevention Program.
Quality Control Plan.
Environmental Protection Plan.
List of Proposed Subcontractors.
List of Proposed Products.
List of Barges.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
SECTION 01 33 00 Page 4
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-05 Design Data
Calculations, mix designs, analyses or other data pertaining to a part of work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accordance with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a supplier, installer or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
1.1.3 Approving Authority
Approving authority rests with the Contracting Officer and his/her
Authorized Representative(s). Approval actions and correspondence with
SECTION 01 33 00 Page 5 the Contractor shall be made through the Caruthersville Area Office.
1.1.4 Work
As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the
Government. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Submittal register.; G
1.3 SUBMITTAL REGISTER
Submit the submittal register at least seven days prior to the prework conference. Verify that all submittals required for the project are listed and add any missing submittals. Complete the following on the register:
Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
1.4 CONTRACTOR USE OF SUBMITTAL REGISTER
Update the following fields.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record
Contractor's review when forwarding submittals to Area Engineer.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.5 APPROVING AUTHORITY USE OF SUBMITTAL REGISTER
Update the following fields.
Column (b).
Column (l) List date of submittal receipt.
Column (m) through (p).
SECTION 01 33 00 Page 6
Column (q) List date returned to Contractor.
1.6 COPIES DELIVERED TO THE GOVERNMENT
Deliver one copy of submittal register updated by Contractor to Government with each invoice request.
1.7 PROCEDURES FOR SUBMITTALS
1.7.1 Reviewing, Certifying, Approving Authority
The Contractor Quality Control (CQC) organization shall be responsible for reviewing and certifying that submittals are in compliance with contract requirements. Approving authority on submittals ultimately rests with the
Contracting Officer, and his/her Authorized Representative(s). Approval of all submittals will be made through the Caruthersville Area Office.
1.7.2 Constraints
a. Submittals listed or specified in this contract shall conform to provisions of this section, unless explicitly stated otherwise.
b. Submittals shall be complete for each definable feature of work;
components of definable feature interrelated as a system shall be submitted at same time.
c. When acceptability of a submittal is dependent on conditions, items, or materials included in separate subsequent submittals, submittal will be returned without review.
d. Approval of a separate material, product, or component does not imply approval of assembly in which item functions.
1.7.3 Scheduling
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential requirements to resubmit.
b. Except as specified otherwise, allow review period, beginning with receipt by approving authority, that includes at least 15 working days for submittals for Contracting Officer's Authorized
Representative approval and 20 working days for submittals for
Contracting Officer approval. Period of review for submittals with Contracting Officer approval begins when Government receives submittal from CQC organization. Period of review for each resubmittal is the same as for initial submittal.
1.7.4 Variations
Variations from contract requirements require Government approval pursuant to contract Clause entitled "FAR 52.236-21, Specifications and Drawings for Construction" and will be considered where advantageous to Government.
Discussion with Caruthersville Area Office prior to submission, will help ensure functional and quality requirements are met and minimize rejections and resubmittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change
Proposal (VECP).
SECTION 01 33 00 Page 7
1.8 CONTRACTOR'S RESPONSIBILITIES
a. Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and contract documents.
b. Transmit submittals to the Government in accordance with the approved Submittal Register. To prevent delays in the work, delays to Government, or delays to separate Contractors transmit submittals using ENG FORM 4025 (Transmittal Sheet).
c. Stamp submittal data to certify that the submittal meets contract requirements.
d. Advise Contracting Officer of variation, as required by paragraph entitled "Variations."
e. Correct and resubmit submittal as directed by approving authority. When resubmitting disapproved transmittals or transmittals noted for resubmittal, the Contractor shall provide copy of that previously submitted transmittal including all reviewer comments for use by approving authority. Direct specific attention in writing or on resubmitted submittal, to revisions not requested by approving authority on previous submissions.
f. Furnish additional copies of submittal when requested by
Contracting Officer, to a limit of 20 copies per submittal.
g. Complete work which must be accomplished as basis of a submittal in time to allow submittal to occur as scheduled.
h. Ensure no work has begun until submittals for that work have been returned as "Approved as submitted" or "Approved, except as noted...", except the portions of said work that the contractor can complete that does not require submittal approval.
1.9 FORMAT OF SUBMITTALS
1.9.1 Transmittal Sheet
Transmit each submittal, except sample installations and sample panels, to office of approving authority. Transmit submittals on ENG FORM 4025
(Transmittal Sheet) located at the following website:
http://www.mvm.usace.army.mil/BusinessWithUs/Contracting/Forms.aspx. The transmittal sheet shall identify Contractor, indicate date of submittal, and include information prescribed by transmittal sheet and required in paragraph entitled "Identifying Submittals." Process transmittal sheets to record actions regarding sample panels and sample installations.
1.9.2 Identifying Submittals
Identify submittals, except sample panel and sample installation, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal sheet. Mark each copy of each submittal identically, with the following:
a. Project title and location.
http://www.mvm.usace.army.mil/BusinessWithUs/Contracting/Forms.aspx
SECTION 01 33 00 Page 8
b. Construction contract number.
c. Section number of the specification section by which submittal is required.
d. Submittal description (SD) number of each component of submittal.
e. When a resubmission, add alphabetic suffix on submittal description, for example, SD-10A, to indicate resubmission.
f. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other second tier Contractor associated with submittal.
g. Product identification and location in project.
1.10 SUBMISSION AND CONTROL OF SUBMITTALS
1.10.1 Submittals Required from the Contractor
Within 15 calendar days after receipt of notice to proceed, the Contractor shall complete and submit to Mr. DAIMON M. MCNEW, Area Engineer, Caruthersville Area Office, 706 Harry S. Truman Blvd., Caruthersville, Missouri 63830-1268 submittals required in the technical sections of this specification, including shop drawings, product data and samples.
1.10.1.1 Submittal Procedures and Deviations
The Government will further discuss detailed submittal procedures with the
Contractor at the Preconstruction Conference. For submittals which include proposed deviations requested by the Contractor, the column
"variation" of ENG Form 4025 shall be checked. The Contractor shall set forth in writing the reason for any deviations and annotate such deviations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.
1.10.1.2 Control of Submittals
The Contractor shall carefully control his procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
1.10.1.3 O&M Data
Contracting Officer will review and approve the O&M Data to verify the submittals comply with the contract requirements; submit data specified for a given item within 30 calendar days after the item is delivered to the contract site. In the event the Contractor fails to deliver O&M Data within the time limits specified, the Contracting Officer may withhold from progress payments up to 10 percent of the price of the item with which such O&M Data are applicable.
1.11 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
SECTION 01 33 00 Page 9
1.11.1 Government Approved
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting
Officer. Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction," they are considered to be "shop drawings."
1.11.2 Information Only
All submittals not requiring Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
1.12 APPROVED SUBMITTALS
The Contracting Officer's approval of submittals shall not be construed as a complete check, but will indicate only that the general method of construction, materials, detailing and other information are satisfactory. Approval will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the
CQC requirements of this contract is responsible for design, dimensions, all design extensions, such as the design of adequate connections and details, etc., and the satisfactory construction of all work. After submittals have been approved by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.13 DISAPPROVED SUBMITTALS
The Contractor shall make all corrections required by the Contracting
Officer and promptly furnish a corrected submittal in the form and number of copies specified for the initial submittal.
1.14 GENERAL
The Contractor shall make submittals as required by the specifications.
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals shall be the same as those used in the contract drawings. Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Prior to submittal, all items shall be checked and approved by the CQC System
Manager and each item shall be stamped, signed, and dated by the CQC
System Manager indicating action taken. Proposed deviations from the contract requirements shall be clearly identified. Submittals shall include items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders;
samples; O&M manuals (including parts list); certifications; warranties;
and other such required submittals. Submittals requiring Government approval shall be scheduled and made prior to the acquisition of the material or equipment covered thereby. Samples remaining upon completion of the work shall be picked up and disposed of in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
SECTION 01 33 00 Page 10
1.15 SUBMITTAL REGISTER
At the end of this section is a submittal register showing items of equipment and materials for which submittals are required by the specifications; this list may not be all inclusive and additional submittals may be required. The Government will provide the initial submittal register in electronic format. Thereafter, the Contractor shall maintain a complete list of all submittals, including completion of all data columns. Dates on which submittals are received and returned by the
Government will be tracked. The Contractor shall monitor the progress of all submittals.
1.16 SCHEDULING
Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of 21 calendar days exclusive of mailing time) shall be allowed and shown on the register for review and approval. No delay damages or time extensions will be allowed for time lost in late submittals.
1.17 TRANSMITTAL SHEET (ENG FORM 4025)
A sample transmittal sheet (ENG Form 4025), which can be found at http://www.mvm.usace.army.mil/BusinessWithUs/Contracting/Forms.aspx shall be used for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. Additionally, these forms are included in the QCS software that is available for Contractor use. The transmittal sheet shall be properly completed by filling out all the heading blank spaces and identifying each item submitted. Special care shall be exercised to ensure proper listing of the specification paragraph and/or sheet number of the contract drawings pertinent to the data submitted for each item.
1.18 GOVERNMENT APPROVED SUBMITTALS
Upon completion of review of submittals requiring Government approval, the submittals will be identified as having received approval by being so stamped and dated. Three copies of the submittal will be retained by the
Contracting Officer and three copies of the submittal will be returned to the Contractor.
1.19 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
http://www.mvm.usace.army.mil/BusinessWithUs/Contracting/Forms.aspx
SECTION 01 33 00 Page 11
1.20 STAMPS
Stamps used by the Contractor on the submittal data to certify that the submittal meets contract requirements shall be similar to the following:
SECTION 01 33 00 Page 12
| CONTRACTOR |
| (Firm Name) |
| Approved |
| Approved with corrections as noted on submittal data and/or |
| attached sheets(s). |
| SIGNATURE: |
| TITLE: |
| DATE: |
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 2 PAGES
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION
Ditch 251 (Unimproved) Channel Cleanout
CONTRACTOR
A C T I V I T Y
N O
R A N S M I T T
L
S P E
DESCRIPTION
ITEM SUBMITTED
R A G # R A
H
G
V
C T L A O S R S I A F / I E C A R T E I V O W N R
CONTRACTOR:
SCHEDULE DATES
ACTION
APPROVING AUTHORITY
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH
REMARKS
SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
T I
D
DATE
OF
DATE FWD
TO APPR
AUTH/
FROM
CONTR
TO OTHER
REVIEWER
FROM OTH
T I
ACTION
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
00 70 00.00 11 SD-07 Certificates
Certificate or Written Evidence of 1.7 G
Insurance
Field Notes and All Other 1.13 G
Records Relating to the Survey
00 80 00.00 11 SD-01 Preconstruction Submittals
Activity Hazard Analysis 1.7 G
Accident Prevention Program 1.7 G
Hazard Communication Program 1.7 G
List of all Personnel, Vehicles and 1.28 G
Equipment
SD-03 Product Data
Material Safety Data Sheets of 1.7
Each Substance
Authenticated Copy of the 1.4
Conveyance under which the
Contractor Acquired the
Rights-of-Way
SD-05 Design Data
Pre-Construction Survey; 1.5 G EC-D
Post-Construction Surveys; 1.5 G EC-D
SD-11 Closeout Submittals
Final As-Built Drawings 1.11 G
Findings of the Accident 1.7
Investigation
01 45 04.00 11 SD-01 Preconstruction Submittals
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 2 PAGES
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION
Ditch 251 (Unimproved) Channel Cleanout
T I V I
Y
R A N S M I T T
L
DESCRIPTION
ITEM SUBMITTED
R A G # R A
H
G
V
C T L A O S R S I A F / I E C A R T E I V O W N R
CONTRACTOR:
SCHEDULE DATES
APPROVING AUTHORITY
MAILED
TO
CONTR/
FRM APPR
AUTH
REMARKS
SUBMIT
APPROVAL
MATERIAL
T I
TO APPR
AUTH/
FROM
CONTR
TO OTHER
FROM OTH
T I
ACTION
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
01 45 04.00 11 Contractor Quality Control (CQC) 3.2 G
Plan
01 57 20.00 11 SD-01 Preconstruction Submittals
Environmental Protection Plan 1.6 G CAO
31 11 00.00 11 SD-04 Samples
Tree wound paint 2.1
31 23 00.00 11 SD-03 Product Data
Equipment 1.4 G
Equipment 1.4 G
SD-04 Samples
Equipment 1.4 G
Equipment 1.4 G
SD-06 Test Reports
Tests and Surveys
SD-07 Certificates
Agreement between the
Contractor and each Landowner
32 92 35.00 13 SD-03 Product Data
Seed Invoices 2.2.1
Native Grass Seeding Equipment G EC-D
SD-04 Samples
Mulch Material
Alternate Seeding Mixture 3.4.1 G EC-D
SD-07 Certificates
AMS Seed Act Certification 2.2.1
Mulch Supplier Certification 2.1.3
SECTION 01 42 00 Page 1
SECTION 01 42 00
SOURCES FOR REFERENCE PUBLICATIONS
1.1 REFERENCES
1.2 ORDERING INFORMATION
SECTION 01 42 00 Page 2
SECTION 01 42 00
SOURCES FOR REFERENCE PUBLICATIONS
Various publications are referenced in other sections of the specifications to establish requirements for the work. These references are identified in each section by document number, date and title. The document number used in the citation is the number assigned by the standards producing organization, (e.g. ASTM B 564 Nickel Alloy
Forgings). However, when the standards producing organization has not assigned a number to a document, an identifying number has been assigned for reference purposes.
1.2 ORDERING INFORMATION
The addresses of the standards publishing organizations whose documents are referenced in other sections of these specifications are listed below, and if the source of the publications is different from the address of the sponsoring organization, that information is also provided. Documents listed in the specifications with numbers which were not assigned by the standards producing organization should be ordered from the source by title rather than by number.
ASTM INTERNATIONAL (ASTM)
100 Barr Harbor Drive, P.O. Box C700
West Conshohocken, PA 19428-2959
Ph: 610-832-9500
Fax: 610-832-9555
E-mail: service@astm.org
Internet: http://www.astm.org
U.S. ARMY CORPS OF ENGINEERS (USACE)
Order CRD-C DOCUMENTS from:
U.S. Army Engineer Waterways Experiment Station
ATTN: Technical Report Distribution Section, Services
Branch, TIC
3909 Halls Ferry Road
Vicksburg, MS 39180-6199
Ph: 601-634-2664
Fax: 601-634-2388
E-mail: mtc-info@erdc.usace.army.mil
Internet: http://www.wes.army.mil/SL/MTC/handbook.htm
Order Other Documents from:
USACE Publications Depot
Attn: CEHEC-IM-PD
2803 52nd Avenue
Hyattsville, MD 20781-1102
Ph: 301-394-0081
Fax: 301-394-0084
E-mail: pubs-army@usace.army.mil mailto:service@astm.org http://www.astm.org/ mailto:mtc-info@erdc.usace.army.mil http://www.wes.army.mil/SL/MTC/handbook.htm mailto:pubs-army@usace.army.mil
Internet:http://www.publications.usace.army.mil/Home.aspx or http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx
U.S. DEPARTMENT OF AGRICULTURE (USDA)
Order AMS Publications from:
AGRICULTURAL MARKETING SERVICE (AMS)
Seed Regulatory and Testing Branch
801 Summit Crossing Place, Suite C
Gastonia, NC 28054-2193
Ph: 704-810-8870
Fax: 704-852-4189
Internet: http://www.ams.usda.gov/lsg/seed.htm
E-mail: seed.ams@usda.gov
Order Other Publications from:
U.S. Department of Agriculture, Rural Utilities Service
14th and Independence Avenue, SW, Room 4028-S
Washington, DC 20250
Ph: 202-720-2791
Fax: 202-720-2166
Internet: http://www.usda.gov/rus
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
8601 Adelphi Road
College Park, MD 20740-6001
Ph: 866-272-6272
Fax: 301-837-0483
Internet: http://www.archives.gov
Order documents from:
Superintendent of Documents
U.S.Government Printing Office (GPO)
732 North Capitol Street, NW
Washington, DC 20401
Ph: 202-512-1800
Fax: 202-512-2104
E-mail: contactcenter@gpo.gov
Internet: http://www.gpoaccess.gov
SECTION 01 42 00 Page 3 http://www.publications.usace.army.mil/Home.aspx http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx http://www.ams.usda.gov/lsg/seed.htm mailto:seed.ams@usda.gov http://www.usda.gov/rus http://www.archives.gov/ mailto:contactcenter@gpo.gov http://www.gpoaccess.gov/
SECTION 01 45 00.15 10 Page 1
SECTION 01 45 00.15 10
RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
1.2 MEASUREMENT AND PAYMENT
1.3 CONTRACT ADMINISTRATION
1.3.1 Correspondence and Electronic Communications
1.3.2 Other Factors
1.4 RMS SOFTWARE
1.5 SYSTEM REQUIREMENTS
1.6 CONTRACT DATABASE - GOVERNMENT
1.7 CONTRACT DATABASE - CONTRACTOR
1.7.1 Administration
1.7.1.1 Contractor Information
1.7.1.2 Subcontractor Information
1.7.1.3 Correspondence
1.7.1.4 Equipment
1.7.1.5 Reports
1.7.1.6 Request For Information (RFI)
1.7.2 Finances
1.7.2.1 Pay Activity Data
1.7.2.2 Payment Requests
1.7.3 Quality Control (QC)
1.7.3.1 Quality Control (QC) Reports
1.7.3.2 Deficiency Tracking.
1.7.3.3 Three-Phase Control Meetings
1.7.3.4 Labor and Equipment Hours
1.7.3.5 Accident/Safety Reporting
1.7.3.6 Definable Features of Work
1.7.3.7 Activity Hazard Analysis
1.7.4 Submittal Management
1.7.5 Schedule
1.7.6 Closeout
1.8 IMPLEMENTATION
1.9 NOTIFICATION OF NONCOMPLIANCE
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 45 00.15 10 Page 2
SECTION 01 45 00.15 10
RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
EM 385-1-1 (2014) Safety and Health Requirements
Manual
1.2 MEASUREMENT AND PAYMENT
The work of this section is not measured for payment. The Contractor is responsible for the work of this section, without any direct compensation other than the payment received for contract items.
1.3 CONTRACT ADMINISTRATION
The Government will use the Resident Management System (RMS) to assist in its monitoring and administration of this contract. The Government accesses the system using the Government Mode of RMS (RMS GM) and the
Contractor accesses the system using the Contractor Mode (RMS CM). The term RMS will be used in the remainder of this section for both RMS GM and
RMS CM. The joint Government-Contractor use of RMS facilitates electronic exchange of information and overall management of the contract. The
Contractor accesses RMS to record, maintain, input, track, and electronically share information with the Government throughout the contract period in the following areas:
Administration
Finances
Quality Control
Submittal Monitoring
Scheduling
Closeout
Import/Export of Data
1.3.1 Correspondence and Electronic Communications
For ease and speed of communications, exchange correspondence and other documents in electronic format to the maximum extent feasible. Some correspondence, including pay requests and payrolls, are also to be provided in paper format with original signatures. Paper documents will govern, in the event of discrepancy with the electronic version.
1.3.2 Other Factors
Other portions of this document have a direct relationship to the
SECTION 01 45 00.15 10 Page 3 reporting accomplished through RMS. Particular attention is directed to
FAR 52.236-15 Schedules for Construction Contracts; FAR 52.232-27 Prompt
Payment for Construction Contracts; FAR 52.232-5 Payments Under
Fixed-Priced Construction Contracts; Section 00 80 00.00 11 SPECIAL
CONTRACT REQUIREMENTS; Section 01 33 00 SUBMITTAL PROCEDURES; Section
00 80 00.00 11 SPECIAL CONTRACT REQUIREMENTS; and Section 01 45 04.00 11
CONTRACTOR QUALITY CONTROL.
1.4 RMS SOFTWARE
RMS is a Windows-based program that can be run on a Windows-based PC meeting the requirements as specified in paragraph SYSTEM REQUIREMENTS.
Download, install and be able to utilize the latest version of the RMS software within 7 calendar days of receipt of the Notice to Proceed. RMS software, user manuals, access and installation instructions, program updates and training information are available from the RMS website ( https://rms.usace.army.mil). The Government and the Contractor will have different access authorities to the same contract database through RMS.
The common database will be updated automatically each time a user finalizes an entry or change.
1.5 SYSTEM REQUIREMENTS
The following is the recommended system configuration to run the
Contractor Mode RMS for full utilization of all features for all types and sizes of contracts. Smaller, less complicated, projects may not require the configuration levels described below. Required configuration also noted below.
Recommended RMS System Requirements
Hardware
Windows-based PC 1.7 GHz i3; AMD A6 3650 GHz or higher processor (REQUIRED)
RAM 8 GB
Hard drive disk 100 GB space for sole use by RMS system
Monitor Screen resolution 1366 x 768
Mouse or other pointing device
Windows compatible printer Laser printer must have 4 MB+ of RAM
Connection to the Internet minimum 4 Mbs per user
Software
MS Windows Windows 7 x 64 bit (RMS requires 64 bit
O/S) or newer (REQUIRED)
Word Processing software Viewer for MS Word 2013, MS Excel 2013 or newer (REQUIRED)
SECTION 01 45 00.15 10 Page 4
Recommended RMS System Requirements
E-mail MAPI compatible (REQUIRED)
Virus protection software Regularly upgraded with all issued
Manufacturer's updates and is able to detect most zero day viruses (REQUIRED)
1.6 CONTRACT DATABASE - GOVERNMENT
The Government will enter the basic contract award data in RMS prior to granting the Contractor access. The Government entries into RMS will generally be related to submittal reviews, correspondence status, and
Quality Assurance(QA)comments, as well as other miscellaneous administrative information.
1.7 CONTRACT DATABASE - CONTRACTOR
Contractor entries into RMS establish, maintain, and update data throughout the duration of the contract. Contractor entries generally include prime and subcontractor information, daily reports, submittals, RFI's, schedule updates and payment requests. RMS includes the ability to import attachments and export reports in many of the modules, including submittals. The Contractor responsibilities for entries in RMS typically include the following items:
1.7.1 Administration
1.7.1.1 Contractor Information
Enter all current Contractor administrative data and information into RMS within 7 calendar days of receiving access to the contract in RMS. This includes, but is not limited to, Contractor's name, address, telephone numbers, management staff, and other required items.
1.7.1.2 Subcontractor Information
Enter all missing subcontractor administrative data and information into
RMS CM within 7 calendar days of receiving access to the contract in RMS or within 7 calendar days of the signing of the subcontractor agreement for agreements signed at a later date. This includes name, trade, address, phone numbers, and other required information for all subcontractors. A subcontractor is listed separately for each trade to be performed.
1.7.1.3 Correspondence
Identify all Contractor correspondence to the Government with a serial number. Prefix correspondence initiated by the Contractor's site office with "S". Prefix letters initiated by the Contractor's home (main) office with "H". Letters are numbered starting from 0001. (e.g., H-0001 or
S-0001). The Government's letters to the Contractor will be prefixed with
"C" or "RFP".
1.7.1.4 Equipment
Enter and maintain a current list of equipment planned for use or being
SECTION 01 45 00.15 10 Page 5 used on the jobsite, including the most recent and planned equipment inspection dates.
1.7.1.5 Reports
Track the status of the project utilizing the reports available in RMS.
The value of these reports is reflective of the quality of the data input. These reports include the Progress Payment Request worksheet, Quality Control (QC) comments, Submittal Register Status, and Three-Phase
Control worksheets.
1.7.1.6 Request For Information (RFI)
Create and track all Requests For Information (RFI) in the RMS
Administration Module for Government review and response.
1.7.2 Finances
1.7.2.1 Pay Activity Data
Develop and enter a list of pay activities in conjunction with the project schedule. The sum of pay activities equals the total contract amount, including modifications. Each pay activity must be assigned to a Contract
Line Item Number (CLIN). The sum of the activities assigned to a CLIN equals the amount of each CLIN.
1.7.2.2 Payment Requests
Prepare all progress payment requests using RMS. Update the work completed under the contract at least monthly, measured as percent or as specific quantities. After the update, generate a payment request and prompt payment certification using RMS. Submit the signed prompt payment certification and payment request as well as supporting data either electronically or by hard copy. Unless waived by the Contracting Officer, a signed paper copy of the approved payment certification and request is also required and will govern in the event of discrepancy with the electronic version.
1.7.3 Quality Control (QC)
Enter and track implementation of the 3-phase QC Control System, QC testing, transferred and installed property and warranties in RMS.
Prepare daily reports, identify and track deficiencies, document progress of work, and support other Contractor QC requirements in RMS. Maintain all data on a daily basis. Insure that RMS reflects all quality control methods, tests and actions contained within the Contractor Quality Control
(CQC) Plan and Government review comments of same within 7 calendar days of Government acceptance of the CQC Plan.
1.7.3.1 Quality Control (QC) Reports
The Contractor's Quality Control (QC) Daily Report in RMS is the official report. The Contractor can use other supplemental formats to record QC data, but information from any supplemental…