PD02_03_79_52_18_ENG-SMA-UtillityConflictMatrix-Final.pdf

PDF 49 KB Posted

Attached to
St. Mary Avenue Drainage Improvements State and local contract opportunity
Solicitation number
PD 24-25.103
Issued by
Escambia County, Florida

About this file

The document is a Utility Conflict Matrix for the St. Mary Avenue Drainage Improvements project, prepared for Escambia County in Florida. The matrix details potential utility conflicts along the project route from North S Street to Q Street, involving multiple utility owners including Emerald Coast Utility Authority and Uniti Fiber LLC. The project involves multiple utility crossings, primarily focusing on 18" pipe crossings at various stations (S-1 to S-8), with most conflicts classified as level 6 or 7 utility investigations. The recommended action for most conflicts is "Protect during construction," indicating the need for careful utility management during the drainage improvement work.

The utility types include water lines (WL) and fiber optic communications (FOC), with most conflicts involving 18" pipe crossings at different station locations. The matrix provides detailed information about conflict locations, including start and end stations, drawing or sheet numbers, and utility investigation levels. While specific pricing details are not explicitly shown, the document suggests a comprehensive approach to identifying and mitigating potential utility conflicts during the drainage system improvement project, which aims to replace approximately 520 linear feet of existing drainage infrastructure with 18" RCP and type E curb and gutter.

View the file

Other files for this state and local contract opportunity

Other files attached to St. Mary Avenue Drainage Improvements, newest first.
File Type Posted
St._Mary_Avenue_Drainage_Improvements_(Addendum_#1_Revision).pdf PDF
PD02_03_79_52_18_ENG-SMA-Plans-Final.pdf PDF
Escambia_County_Technical_Specifications_07.01.2020.pdf PDF
PD02_03_79_52_18_ENG-SMA-DesignDocs-Final.pdf PDF
NWFWM_Permit.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date

Reviewed By

Date

Conflict ID

Size and/or

Material

Start

Station

End Station Start

Offset

End Offset

Test Hole Northing Easting

Ground Elev Utility

Elev (top)

1 0+17.40 0+17.98 103.06 125.56

2 0+20.07 0+21.37 125.9 61.4

3 0+19.38 - 24.68 -

4 0+24.35 - 12.25 -

5 0+25.35 - 12.25 -

6 0+33.03 - 12.25 -

7 2+10.00 - 15.34 -

8 2+10.00 - 19.79 -

9 3+28.21 - 12.25 -

10 3+28.85 - 47.26 -

11 3+31.83 - 16.28 -

12 3+31.84 - 19.62 -

13 3+31.85 - 23.82 -

14 3+31.85 - 26.06 -

15 3+65.83 - 12.25 -

16 3+83.23 - 12.25 -

17 3+83.73 - 12.25 -

18 3+85.13 - 12.25 -

Utility Conflict Matrix

Utility Owner and/or

Contact Name

Drawing or

Sheet No. Utility Type Utility Conflict Description

Utility

Investigation

Level Needed

Recommended Action or

Resolution

Estimated

Resolution Date Resolution Status

4/24/2024

Project Description:

Highway or Route:

Project Owner: Escambia County

ACP 5229762

Emerald Coast Utility

Authority 6 WL Crossing 15" Pipe, S-4A to S-4 Water line to be relocated

Unknown 6 UNK Drainage Structure, S-4A Protect during construction

Emerald Coast Utility

Authority 6 WL Crossing 18" Pipe, S-6 to S-5 Water line to be relocated

Unknown 6 UNK Crossing 18" Pipe, S-6 to S-5

Protect during construction

Protect during construction

Utility Conflict Matrix Developed/Revised By:

4/24/2024

Consor

Project No. :

From North S Street to Q Street

St. Mary's Ave

Uniti Fiber LLC? 6 FOC 18" Pipe, S-2 to S-1 Protect during construction

Unknown 6 UNK 18" Pipe, S-2 to S-1 Protect during construction

Crossing 18" Pipe, S-2 to S-1

Water line to be relocated

Unknown 6 UNK Protect during construction

Unknown 6 UNK Crossing 18" Pipe, S-4 to S-3

Crossing 18" Pipe, S-4 to S-3

Protect during construction

Emerald Coast Utility

Authority

6 WL

Unknown 6 UNK Crossing 18" Pipe, S-4 to S-3 Protect during construction

Uniti Fiber LLC? 6 FOC Crossing 18" Pipe, S-6 to S-5 Protect during construction

Unknown 6 UNK Crossing 18" Pipe, S-5 to S-4

Unknown 6 UNK Drainage Structure, S-6

Protect during construction

Uniti Fiber LLC? 6 FOC Crossing 18" Pipe, S-6 to S-5 Protect during construction

Uniti Fiber LLC? 7 FOC Crossing 18" Pipe, S-8 to S-5 Protect during construction

Uniti Fiber LLC? 7 FOC Crossing 18" Pipe, S-8 to S-5 Protect during construction

Uniti Fiber LLC? 7 FOC Crossing 18" Pipe, S-8 to S-5 Protect during construction

Uniti Fiber LLC? 7 FOC Crossing 18" Pipe, S-8 to S-5 Protect during construction