PD02_03_79_52_18_ENG-SMA-UtillityConflictMatrix-Final.pdf
PDF 49 KB Posted
- Attached to
- St. Mary Avenue Drainage Improvements State and local contract opportunity
- Solicitation number
- PD 24-25.103
- Issued by
- Escambia County, Florida
About this file
The document is a Utility Conflict Matrix for the St. Mary Avenue Drainage Improvements project, prepared for Escambia County in Florida. The matrix details potential utility conflicts along the project route from North S Street to Q Street, involving multiple utility owners including Emerald Coast Utility Authority and Uniti Fiber LLC. The project involves multiple utility crossings, primarily focusing on 18" pipe crossings at various stations (S-1 to S-8), with most conflicts classified as level 6 or 7 utility investigations. The recommended action for most conflicts is "Protect during construction," indicating the need for careful utility management during the drainage improvement work.
The utility types include water lines (WL) and fiber optic communications (FOC), with most conflicts involving 18" pipe crossings at different station locations. The matrix provides detailed information about conflict locations, including start and end stations, drawing or sheet numbers, and utility investigation levels. While specific pricing details are not explicitly shown, the document suggests a comprehensive approach to identifying and mitigating potential utility conflicts during the drainage system improvement project, which aims to replace approximately 520 linear feet of existing drainage infrastructure with 18" RCP and type E curb and gutter.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| St._Mary_Avenue_Drainage_Improvements_(Addendum_#1_Revision).pdf | ||
| PD02_03_79_52_18_ENG-SMA-Plans-Final.pdf | ||
| Escambia_County_Technical_Specifications_07.01.2020.pdf | ||
| PD02_03_79_52_18_ENG-SMA-DesignDocs-Final.pdf | ||
| NWFWM_Permit.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date
Reviewed By
Date
Conflict ID
Size and/or
Material
Start
Station
End Station Start
Offset
End Offset
Test Hole Northing Easting
Ground Elev Utility
Elev (top)
1 0+17.40 0+17.98 103.06 125.56
2 0+20.07 0+21.37 125.9 61.4
3 0+19.38 - 24.68 -
4 0+24.35 - 12.25 -
5 0+25.35 - 12.25 -
6 0+33.03 - 12.25 -
7 2+10.00 - 15.34 -
8 2+10.00 - 19.79 -
9 3+28.21 - 12.25 -
10 3+28.85 - 47.26 -
11 3+31.83 - 16.28 -
12 3+31.84 - 19.62 -
13 3+31.85 - 23.82 -
14 3+31.85 - 26.06 -
15 3+65.83 - 12.25 -
16 3+83.23 - 12.25 -
17 3+83.73 - 12.25 -
18 3+85.13 - 12.25 -
Utility Conflict Matrix
Utility Owner and/or
Contact Name
Drawing or
Sheet No. Utility Type Utility Conflict Description
Utility
Investigation
Level Needed
Recommended Action or
Resolution
Estimated
Resolution Date Resolution Status
4/24/2024
Project Description:
Highway or Route:
Project Owner: Escambia County
ACP 5229762
Emerald Coast Utility
Authority 6 WL Crossing 15" Pipe, S-4A to S-4 Water line to be relocated
Unknown 6 UNK Drainage Structure, S-4A Protect during construction
Emerald Coast Utility
Authority 6 WL Crossing 18" Pipe, S-6 to S-5 Water line to be relocated
Unknown 6 UNK Crossing 18" Pipe, S-6 to S-5
Protect during construction
Protect during construction
Utility Conflict Matrix Developed/Revised By:
4/24/2024
Consor
Project No. :
From North S Street to Q Street
St. Mary's Ave
Uniti Fiber LLC? 6 FOC 18" Pipe, S-2 to S-1 Protect during construction
Unknown 6 UNK 18" Pipe, S-2 to S-1 Protect during construction
Crossing 18" Pipe, S-2 to S-1
Water line to be relocated
Unknown 6 UNK Protect during construction
Unknown 6 UNK Crossing 18" Pipe, S-4 to S-3
Crossing 18" Pipe, S-4 to S-3
Protect during construction
Emerald Coast Utility
Authority
6 WL
Unknown 6 UNK Crossing 18" Pipe, S-4 to S-3 Protect during construction
Uniti Fiber LLC? 6 FOC Crossing 18" Pipe, S-6 to S-5 Protect during construction
Unknown 6 UNK Crossing 18" Pipe, S-5 to S-4
Unknown 6 UNK Drainage Structure, S-6
Protect during construction
Uniti Fiber LLC? 6 FOC Crossing 18" Pipe, S-6 to S-5 Protect during construction
Uniti Fiber LLC? 7 FOC Crossing 18" Pipe, S-8 to S-5 Protect during construction
Uniti Fiber LLC? 7 FOC Crossing 18" Pipe, S-8 to S-5 Protect during construction
Uniti Fiber LLC? 7 FOC Crossing 18" Pipe, S-8 to S-5 Protect during construction
Uniti Fiber LLC? 7 FOC Crossing 18" Pipe, S-8 to S-5 Protect during construction