PD02_03_79_52_18_ENG-SMA-DesignDocs-Final.pdf
PDF 5 MB Posted
- Attached to
- St. Mary Avenue Drainage Improvements State and local contract opportunity
- Solicitation number
- PD 24-25.103
- Issued by
- Escambia County, Florida
About this file
The document is a design documentation package prepared by Consor North America, Inc. for Escambia County, Florida, concerning the St. Mary Avenue Drainage Improvements project. The project aims to install a new storm drain system and replace the existing ditch at the intersection of N S St and St Mary Avenue to alleviate flooding problems. The scope of work includes surveying, geotechnical reporting, subsurface utility exploration, plan preparation, coordination meetings, permitting, bidding assistance, and construction administration. The design must meet current standards from Escambia County, Safe Routes to School, Americans with Disability Act, Florida Department of Transportation, and other relevant guidelines.
The engineer's estimate for the project totals $341,100.50, including a 10% contingency. The construction cost breakdown includes various line items such as mobilization, clearing and grubbing, earthwork, asphalt and concrete work, drainage infrastructure (including 524 linear feet of 18" RCP pipe), curb inlets, manholes, traffic signs, and erosion control. The unit prices are derived from the Escambia County General Paving and Drainage Pricing Agreement, valid from January 1, 2024, to December 31, 2024. The project appears to be funded through FEMA, with a focus on improving drainage infrastructure and road conditions in the specified area.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| St._Mary_Avenue_Drainage_Improvements_(Addendum_#1_Revision).pdf | ||
| PD02_03_79_52_18_ENG-SMA-Plans-Final.pdf | ||
| Escambia_County_Technical_Specifications_07.01.2020.pdf | ||
| NWFWM_Permit.pdf | ||
| PD02_03_79_52_18_ENG-SMA-UtillityConflictMatrix-Final.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
St. Mary Avenue Drainage Improvements
Design Documentation
Prepared for:
Escambia County
Prepared by:
4489 Woodbine Road Pace, Florida 32571
April 2024
THIS ITEM HAS BEEN DIGITALLY SIGNED AND SEALED BY:
ON THE DATE ADJACENT TO THE SEAL.
PRINTED COPIES OF THIS DOCUMENT ARE NOT CONSIDERED
SIGNED AND SEALED AND THE SIGNATURE MUST BE VERIFIED
ON ANY ELECTRONIC COPIES
ENGINEER OF RECORD:
ERIC K. NELSON, PE
PE NO. 79361
(850) 289-1013
CONSOR ENGINEERS, LLC
4489 WOODBINE ROAD
PACE, FLORIDA 32571
Consor North America, Inc.
St. Mary’s Avenue Design Documentation
DESIGN DOCUMENTATION
1. Scope of Services
2. Technical Specifications
3. Survey / Alignment Control
4. Drainage Analysis
5. Estimate of Construction Cost
1. Scope of Services
St Mary Ave Drainage Improvements Project
Scope of Work
Escambia County Construction Management Division is seeking the design services for the installation of a new storm drain system as well as removal and replacing of the existing ditch located at the intersection of
N S St / St Mary Ave and N Q St and St Mary Ave in order to alleviate flooding problem.
If required, the selected A/E shall assist in the acquisition of all property needed to complete the project, provide any legal descriptions, exhibits or other documents required to acquire any and all properties including but not limited to, right-of-way, easements, and property purchases. The A/E will be responsible for acquiring any survey, if not provided by the County, and it must meet the current Florida
Minimum Technical Standards as set forth by the Board of Professional Surveyors and Mappers. The design shall meet all required current standards and specifications including, but not limited to, Escambia
County Technical Specification, Safe Routes to School (SRTS), Americans with Disability Act (ADA), Architectural Barriers Act (ABA), Florida Department of Transportation (FDOT), Public Rights-Of-Way
Accessibility Guidelines (PROWAG), Manual on Uniform Traffic Control Devices (MUTCD), Florida Green
Book and the latest addition of Design Standards.
Description of Work Activities The consultants and/or its sub-consultants will perform the following activities in completing the construction plans:
Task 1: Data Collection & Review, Plan preparation, and Estimates:
• Provide a project schedule that will meet or exceed expectations.
• Provide Geotechnical Reports on Soil Data (if required)
• Provide Subsurface Utility Exploration (SUE) Reports (if required)
• If necessary, provide surveying services for the project based on, but limited to, the following:
a) Certified Boundary Survey (with delineations of MHWL, wetlands, conservation easements, etc.); Topographic Survey; and Bathymetric Survey (to -5 ft MLLW, in the area proximate to intended ramp, docks and living shoreline/breakwater construction) that meets the current Florida Minimum Technical Standards as set forth by the Board of Professional Surveyors and Mappers.
b) Minimum of two Benchmarks referenced to NAVD 1988 Datum. Maximum distance between Benchmarks not to exceed 1000 feet.
c) Cross-section data intervals shall not exceed 100 feet. Where possible, topographic data shall exceed the right-of-way width by a minimum of 5 feet to ensure complete DTM coverage of right-of-way.
d) Roads rights-of-way and parcel lines depicted on topographic survey shall be based on field located property corners, where such corners exist.
e) Coordinate with County Surveyor and staff for the collection of surveying data for project.
f) Electronic files submitted shall be based on State Plane Coordinates, NAD 83/90, and
North Florida Zone.
* If a discrepancy between the requirements above and the current Florida minimum Technical Standards, the more stringent standard will apply.
• Provide 30%, 60%, 90% and 100% plans for review by County. In some cases, a simplified design track may be appropriate. 60% and or 90% plans may be omitted if approved by the County Project Manager. Cursory reviews at the time of submittal will apply.
• Plans should be reproducible to 40 scale 11"x17” and 20 scale 24" X 36" sheets size plans.
• Submit cost estimates via pricing agreement or bid tab at each stage of plan development.
Task 3: Coordination Meetings:
• If required, attend public meetings with stakeholders and the general public to receive input.
• Meet with County Staff for input on maintenance and historical complaints.
• If required, utility coordination and plans-in-hand walk through with Utility Companies at all phase submittals.
Task 4: Permitting (if required)
• Obtain any required regulatory Environmental, Wetland, and Stormwater permitting. Include permit fee allowances. Utilize any Emergency Orders and procedures where applicable.
Task 5: Bidding (if required)
• Prepare all bid documents throughout bidding process.
• Attend pre-solicitation conference.
• Respond to all Requests for Information and issue any necessary addendums.
• Tabulate and verify bid tab totals.
Task 6: Construction Administration & Inspections (Limited Allowance Based upon actual time):
• Consultant will attend a Preconstruction Conference.
• Consultant will prepare as-built certification and as-built drawings based upon contractor mark-ups & milestone inspections, and post construction meetings and inspections.
• Consultant will be available during construction to provide interpretation of their design as necessary and during post construction project closeout. Construction Administration services for unforeseen construction issues needed to monitor construction will be an allowance requiring pre-approval to proceed. The County will inspect all construction improvements.
Task 7: Optional Services (if required)
• List any Optional Services that may be required for this project such as Geotechnical Services, Subsurface Utility Exploration (SUE), etc.
Deliverables
• One 11”x17” set of the plans at each stage of plan development.
• One copy of the cost estimates via the pricing agreement or bid tab at each stage of plan development.
• One copy of the drainage documentation, if applicable
• One copy of hydraulic analysis, if applicable
• One copy of the geotechnical investigation, if applicable
• Five copies of the signed and sealed survey, if applicable
• One copy of the required permits, if applicable
• Four paper copies (11”x17”) of the approved construction plans.
• One copy of the ICPR model, if applicable.
• One copy of the ACAD drawing files, if applicable
• One copy of the Bid Package, if applicable
• One copy of as-builts (hard copy and AutoCAD copy)
• Digital copy (pdf format) of all the above listed items
Initial Design Estimate < $10K Initial Repair In-Kind Construction Estimate < $100K
2. Technical Specifications
TECHNICAL SPECIFICATIONS
Governing Standards and Specification shall be Florida Department of
Transportation, Standard Plans dated FY 2023-24. And Standard
Specifications for Road and Bridge Construction dated July 2023, as amended by contract documents.
For Standard Plans for Road Construction follow the link:
https://www.fdot.gov/design/standardplans/current/default.shtm
For the Standard Specifications for Road and Bridge Construction click on the “Specifications” link at the following website:
http://www.fdot.gov/programmanagement/implemented/SpecBooks
Specifications identified for this project include:
Section 100 Construction Equipment – General Requirements
Section 101 Mobilization
Section 102 Maintenance of Traffic
Section 104 Prevention, Control and Abatement of Erosion and Water Pollution
Section 105 Contractor Quality Control General Requirements
Section 110 Clearing and Grubbing
Section 120 Excavation and Embankment
Section 125 Excavation for Structures and Pipe
Section 160 Stabilizing
Section 162 Prepared Soil Layer
Section 204 Graded Aggregate Base
Section 234 Superpave Asphalt Base
Section 283 Reclaimed Asphalt Pavement Base
Section 285 Optional Base Course
Section 334 Superpave Asphalt Concrete
Section 400 Concrete Structures
Section 415 Reinforcing for Concrete
Section 425 Inlets, Manholes, and Junction Boxes
Section 430 Pipe Culverts
Section 520 Concrete Gutter, Curb Elements, and Traffic Separator
Section 522 Concrete Sidewalks and Driveways
Section 527 Detectable Warnings
Section 570 Performance Turf
Section 710 Painted Pavement Markings
Section 713 Permanent Tape Pavement Markings
Note: All 900 series materials specifications referenced within the above list shall be considered applicable as directed in the specification.
County Technical Specifications
SECTION 01000 DEFINITIONS AND TERMS
SECTION 01300 SUBMITTALS
SECTION 02230 CLEARING & GRUBBING
SECTION 02300 EARTHWORK
SECTION 02400 GRADED AGGREGATE BASE
SECTION 02500 SUPERPAVE ASPHALT CONCRETE
SECTION 02580 HOT IN-PLACE RECLAIMED ASPHALT AND RESURFACING
SECTION 02600 STORMWATER SYSTEM
SECTION 02900 GRASSING
SECTION 03300 PORTLAND CEMENT CONCRETE
SECTION 04000 TRAFFIC CONTROL SIGNS
SECTION 04040 PAVEMENT MARKINGS
SECTION 04060 MAINTENANCE OF TRAFFIC
3. Survey / Alignment Control
4. Drainage Analysis
4/12/2024CONSORDrainage Improvements PensacolaFLStMary 4/12/2024EKNSt. Mary Ave EscambiaPD02.03.79.52.18.ENG
0.130.95 0.13 1.700.00P-5 0.03 4.00S-6 200+47 L S-10.000.130.007.500.0160.00300.083
0.130.95 0.13 1.710.00P-5 0.03 4.00S-7 200+47 R S-10.000.130.007.500.0160.00300.083
2.020.95 2.02 3.460.00P-5 0.53 4.00S-8 3+95 L S-40.091.930.007.500.0160.01770.083
0.570.95 0.66 3.040.09P-5 0.15 4.00S-4 2+10 L S-30.000.660.007.500.0160.00370.083
0.640.95 0.64 3.140.00P-6 0.17 4.00S-3 0+50 L SAG0.000.640.777.500.0160.00300.083
FLORIDA DEPARTMENT OF TRANSPORTATION
Page:SPREAD TABULATION REPORT
Designed:County: Rainfall Zone:Financial Prj Id: Date:
Checked:Description: Organization: State Road: Date:
Structure Station Side Type Drainage Bypass toRainfall Overland CrossTotalComposite Previous LongitudinalManning'sCalculated SumpedAllowable InterceptedBypass Flow No. of Area StructureRunoff SlopeRunoff Intensity Runoff Inlet Bypass Slope n Spread SpreadSpread Flow to Nxt Inlet
(acres)Structure No.(in/hr) (cfs) (cfs) (ft/ft)Coefficient (cfs) (ft/ft) (ft) (ft)(ft) (cfs) (cfs)
Automated Storm sewer Analysis & Design (ASAD), copyright 1992-2007, Hiteshew Engineering Systems, Inc. Ph: (352) 383-4191 T61v3FDOT.RPT 11/25/2007Portions of ASAD were developed by Kenneth J. Leeming, P.E. at International Engineering Consultants, Inc.
14/12/2024
StMary
PD02.03.79.52.18.ENG 72.37American Consulting Prof.
Drainage Improvements EKN 0.09
0.300.650.95Escambia KEA 72.46 PensacolaFL 25yr
HGL method: Standard FDOT (Jump HGL to pipe crown).
S-1 EX-2 2.38Full0.093124.0076.550.000.000.000.950.00 0.02872.56 72.49 72.460.00
101+27.97 16.00 0.012010.96 72.430.000.0012.37 0.00 8.47 0.880.880.000.650.00 72.377.480.00
1 30.00MH-8 3.490.200024.0070.430.073.990.000.000.880.000.300.00 0.06070.377.48
S-2 S-1 4.30Full0.446718.0075.760.000.000.000.950.00 0.48273.27 73.04 72.560.00
0+19.38 -17.83 0.01205.14 72.150.000.0011.95 0.42 8.61 0.880.880.000.650.00 71.937.610.00
1 108.00MH-8 2.910.203718.0070.650.232.490.000.000.880.000.300.00 0.22070.437.61
S-3 S-2 4.32Full0.450618.0075.350.000.160.160.950.16 0.12673.54 73.40 73.270.00
0+50 -12.25 0.01205.27 72.210.000.0011.84 0.11 8.65 0.880.720.000.650.00 72.157.640.00
1 28.00CI-6-A 2.980.214318.0070.710.151.810.000.000.880.000.300.00 0.06070.657.64
S-4 S-3 3.64Full0.319718.0075.850.000.140.140.950.14 0.51274.16 74.05 73.540.00
2+10 -12.25 0.01205.09 72.530.000.0011.11 0.73 8.90 0.720.580.000.650.00 72.216.430.00
1 160.00CI-5-B 2.880.200018.0071.030.101.690.000.000.720.000.300.00 0.32070.716.43
S-4A S-4 0.09Full0.000315.0075.600.000.010.000.950.00 0.00074.16 74.16 74.160.00
2+10 -18.25 0.01206.26 73.670.000.0010.00 0.04 9.29 0.010.000.000.650.00 73.630.110.00
1 5.00Yard Dra 5.100.800015.0072.420.001.440.000.000.010.010.300.04 0.04072.380.11
S-5 S-4 2.94Full0.208718.0076.400.000.000.000.950.00 0.24874.48 74.40 74.160.00
3+31.82 -12.25 0.01205.42 72.800.000.0010.43 0.67 9.14 0.560.560.000.650.00 72.535.200.00
1 119.00MH-8 3.070.226918.0071.300.081.920.000.000.560.000.300.00 0.27071.035.20
S-6 S-5 0.33Full0.002618.0076.050.000.030.030.950.03 0.00174.49 74.49 74.480.00
200+47 -12.25 0.01206.36 73.500.000.0010.17 0.27 9.23 0.060.030.000.650.00 73.400.590.00
1 32.00CI-5-B 3.600.312518.0072.000.001.560.000.000.060.000.300.00 0.10071.900.59
S-7 S-6 0.17Full0.000718.0076.250.000.030.030.950.03 0.00074.49 74.49 74.490.00
200+47 12.25 0.01208.05 73.600.000.0010.00 0.17 9.29 0.030.000.000.650.00 73.500.300.00
1 20.00CI-5-B 4.550.500018.0072.100.001.760.000.000.030.000.300.00 0.10072.000.30
S-8 S-5 2.66Full0.170218.0077.410.000.500.500.950.53 0.10274.64 74.59 74.480.00
3+95 -12.25 0.01204.65 72.900.000.0010.00 0.38 9.29 0.500.000.000.650.00 72.804.700.00
1 60.00CI-5-B 2.630.166718.0071.400.052.770.000.000.500.000.300.00 0.10071.304.70
Page:STORM SEWER HYDRAULICS System:
PROJECT CONDITIONS
Number: Organization: Outfall Tailwater El: Runoff Coefficients (default)Storm Event - User Defined
Area 3Description: Area 1 Area 2Designed by: Exit Loss at Outfall: Location Frequency County: Checked by: Storm Sewer Control El:
FROM TO Mann'gCapacityFlowFall Tc TravelInten. Total VelocityHGLPipe Pipe ElevationsInlet ElevationsFlow (cfs) Drainage Areas
OffsetStation 'N' Type(%)Height HGLHGLInletQb S-Qb Time CA ActualArea Runoff Lcl CAC*A LenType Brls FLWidth Crown Line Qfd S-Qfd Physical Min HGL CIA UpStrmCoeff
(cfs)(fps) (%)(in)(ft) Flow LineJnc LossClear.TOTALS-Qdw Qdw(min) (min) (in/hr) (ac)Tot CA(A) (C) (CA)
Units: ENGLISH Automated Storm sewer Analysis & Design (ASAD), copyright 1992-2003, Hiteshew Engineering Systems, Inc. Ph: (352) 383-4191
T60v11U.RPT 10/14/2003Portions of ASAD were developed by Kenneth J. Leeming, P.E. at International Engineering Consultants, Inc.
5. Estimate of Construction Costs
Date:
Project No:
Item No. Description Unit Quantity Unit Price Proposed Amount
2100-00101 Mobilization, 0 - 15 Miles EA 1 3,412.50$ 3,412.50$
3100-00101 Clearing and Grubbing AC 0.387 10,819.17$ 4,190.54$
3100-00115 Relocate Existing Standard Mailbox EA 3 167.00$ 501.01$
4100-00101 Earthwork Excavation by Machine CY 16.32 9.56$ 155.94$
4100-00104 Earthwork Borrow (Fill) CY 64.10 19.20$ 1,230.83$
5200-00108 2" Type SP 12.5 Asphalt, over 1500sy SY 1811 14.33$ 25,948.61$
5500-00103 Mill Existing Asphalt, 1.5" - 3" Thickness, less than 1500sy SY 1270 5.17$ 6,559.55$
5600-00101 Lateral pavement patch as per County Detail (Full depth Asphalt) SY 27 77.66$ 2,071.21$
5600-00106 Remove Existing Asphalt, 3" Average Depth (Driveways) SY 31 5.77$ 178.82$
5600-00107 Remove Existing Asphalt (2" SP-12.5, 8" Base, 12" Subgrade - 22" Thickness) CF 8917 4.57$ 40,781.94$
5600-00108 Saw Cut Existing Asphalt LF 734 3.08$ 2,259.50$
6100-00105 12" Stabilized Subgrade, less than 1000sy SY 662 4.05$ 2,681.10$
6200-00105 8" Graded aggregate Base "Min. LBR 100 at 100% Modified Proctor", less than 1000sy SY 1811 35.40$ 64,103.36$
7300-00115 Thermoplastic 24” White or Yellow Solid Stripe LF 25 12.99$ 324.71$
7300-00117 Thermoplastic White High Intensity Pedestrian Crosswalk LF 178 39.85$ 7,093.30$
7400-00101 Relocate Traffic Signs EA 8 112.92$ 903.33$
7900-00103 MOT (for contracts $200,000 to $250,000) LS 1 9,054.79$ 9,054.79$
8100-00104 FDOT Type E Curb and Gutter, FDOT Index 300 LF 726 26.95$ 19,563.28$
8200-00104 6" Fiber Reinforced Concrete Driveway, over 30sy SY 139 73.42$ 10,204.69$
8300-00103 5' Fiber Reinforced Concrete Sidewalk, less than 80lf LF 14 35.68$ 499.54$
8300-00108 Detectable Handicap Warning Mat, FDOT Index 304 SF 9 58.00$ 522.03$
8500-00103 Remove Existing Concrete, up to 6" thick SY 335 8.19$ 2,743.09$
N/A Remove Existing Gravel Driveway SY 23 8.19$ 188.33$ 9100-00205 Curb Inlet Top, Type 5 EA 4 4,539.85$ 18,159.40$ 9100-00206 Curb Inlet Top, Type 6 EA 1 4,583.77$ 4,583.77$ 9100-00614 12" X 15" X 15" Yard Drain with concrete pad (per County Detail) EA 1 2,211.32$ 2,211.32$ 9100-00701 3'6" X 3'6" Structure Bottom, FDOT Index 200, 0-6' depth EA 4 4,356.44$ 17,425.74$ 9100-00735 3'6" Dia. Structure Bottom, FDOT Index 200, 0-6' depth EA 1 4,098.03$ 4,098.03$
9100-00801 Storm Manhole, 0-6ft depth EA 3 4,489.50$ 13,468.50$
9100-00905 Remove Ditch Bottom Inlet (Including Top and Bottom) EA 1 617.97$ 617.97$
9100-00912 Tie to Existing Inlets, Pipe, Manhole EA 2 1,472.19$ 2,944.38$
9200-00503 15" PVC Pipe, 0'-6' depth LF 5 53.64$ 268.18$
9200-00603 18" RCP Pipe, 0'-6' depth LF 524 62.74$ 32,874.01$
9200-00605 24" RCP Pipe, 0'-6' depth LF 30 80.26$ 2,407.83$
9500-00102 Pipe Removal, 6"-24" LF 6 20.55$ 123.27$
13100-00101 Centipede Sod, Staked SY 971 3.82$ 3,709.22$
13300-00109 Establish, quantify, and submit an approved erosion control plan prepared by a certified technician. EA 1 2,027.77$ 2,027.77$
Construction Total 310,091.36$
Contingencies (10%) 31,009.14$
Total 341,100.50$
NOTES: 1. UNIT PRICES DERIVED FROM ESCAMBIA COUNTY GENERAL PAVING AND DRAINAGE PRICING AGREEMENT, VALID JANUARY 1, 2024 - DECEMBER 31, 2024
ST. MARY AVENUE DRAINAGE IMPROVEMENTS
Engineer's Estimate
Apr-24
FEMA PD 02.03.79.52.18.ENG
FINAL CONSTRUCTION COST ESTIMATE
| 2025-05-20T15:33:18-0400 | |
| Eric K Nelson | |
| I am approving this document |