SOW.pdf
PDF 1 MB Posted
- Attached to
- REPLACE SCHOODIC PROPANE BOILERS Federal contract opportunity
- Solicitation number
- P16PS02089
About this file
Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_P16PS02089.pdf | ||
| Davis_Bacon_Wage_Rates.txt | TXT text file | |
| Bid_Sheet.xls | XLS spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACADIA NATIONAL PARK
Hancock County, Maine
SCHOODIC PROPANE BOILERS
PROJECT MANUAL
ACAD 208488
NATIONAL PARK SERVICE
ACADIA NATIONAL PARK
JUN 2016 TOC-1
SCHOODIC PROPANE BOILERS
TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
01010 Summary of Work 01310 Project Meetings 01320 Schedules and Monthly Inspections 01330 Submittals 01360 Accident Prevention 01420 Reference Standards 01510 Temporary Services 01525 Construction Aids 01560 Temporary Controls 01600 Material and Equipment 01770 Project Closeout 01785 Operation and Maintenance Data
DIVISION 2 - SITE WORK
02224 Selective Demolition 02320 Utility Trenching and Backfilling 02502 Utility Line Marking
DIVISIONS 3 -14
NONE
DIVISION 15 - MECHANICAL
15010 General Mechanical Provisions 15050 Basic Materials and Methods 15075 Mechanical Identification 15080 Mechanical Insulation 15198 Small LP Gas Systems 15400 Plumbing Systems 15500 Hydronic Systems 15510 Boilers 15952 Testing, Adjusting and Balancing
DIVISION 16 - ELECTRICAL
16010 Electrical Provisions 16050 Basic Materials and Methods
JULY 2016 01010-1
SCHOODIC PROPANE BOILERS SUMMARY OF WORK
SECTION 01010
SUMMARY OF WORK
PART 1 - GENERAL
I. DESCRIPTION
The scope of this contract includes:
A. Removal of existing oil fired boilers and furnaces with appurtenances, unused electrical circuits, fuel lines, chimneys and flues. Repair and refinish penetrations of walls, ceilings and roofs left by the removals.
B. Furnish and install propane hot water boilers, consistent with the scope described in Section 15010.
C. Scope includes work in two buildings and installation of fuel lines and propane provider furnished fuel tanks. Drawings are furnished and attached.
D. The Contractor shall furnish all labor, materials, equipment, tools, transportation services and supplies required to complete the work in accordance with the specifications, drawings in solicitation and the accepted proposal.
E. All work will be performed under a single contract.
F. Site will be available for work upon award after notice to proceed, until completion and the project must be completed not to exceed December 1, 2016.
II. LOCATION: Schoodic, Education and Research Center Acadia National Park, Winter Harbor, Maine.
III. CONTRACTOR'S USE OF PREMISES
A. Construction Camp: Establishment of a camp within the Park will not be permitted.
B. Storage areas for materials and staging areas at the work site will be identified by the
Contracting Officer.
C. Preservation of natural features and protection of facilities: Confine all operations to work limits of the project. Prevent damage to natural surroundings and adjacent structures. Restore damaged areas, repairing or replacing damaged trees, plants, and facilities at no additional expense to the Government.
D. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials.
IV. SPECIAL CONSTRUCTION REQUIREMENTS
A. Contractor must maintain staff access to the buildings. Contractor must maintain utilities to the rest of the building except for brief outages coordinated in advance.
B. Contractor must maintain heat in building above 50 degrees during installs of less than 24 hours. For installs greater than 24 hours, the contractor must maintain heat at 68
JULY 2016 01010-2
SCHOODIC PROPANE BOILERS SUMMARY OF WORK
degrees Use approved temporary heat when necessary.
C. The government’s propane provider is Dead River Company. Coordinate with the fuel provider to assure a complete and functional fuel system installation.
V. FIELD VERIFICATION
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products or performing work at the site.
VI. CONSTRUCTION MATERIALS
A. All new materials shall be Contractor-furnished from outside the Park unless otherwise approved.
VII. PUBLICATIONS CITED
A. All publications, references, codes, or standards cited in this specification, regardless if dated or not, shall be the latest published edition. Those that are superseded shall be governed by the superseding document.
VIII. WORKMANSHIP
A. Unless directly specified otherwise all materials, fabrications and work shall be installed/applied/completed in accordance with manufacturer’s instructions/recommendations, state of Maine Regulations, and applicable International Codes. Notify Contracting Officer when impossible to comply.
PART 2 – PRODUCTS
Not used.
PART 3 – EXECUTION
END OF SECTION
JUN 2010 01310-1
SCHOODIC PROPANE BOILERS PROJECT MEETINGS
SECTION 01310
PROJECT MEETINGS
PART 1 GENERAL
1 .1 I. PRECONSTRUCTION CONFERENCE
A. Before start of construction, Contracting Officer will hold a meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Correspondence procedures
2. Designation of responsible personnel
3. Labor standards provisions
4. Payroll reports
5. Changes
6. Payments to Contractor
7. Subcontractors
8. National Park Service regulations
9. Accident prevention program (including name of responsible supervisor)
10. Accident reporting
11. Contractor’s Quality Control Program
12. Documents required under the contract
13. Park rules and regulations
14. Recycling Program
15. Saturday, Sunday, holiday and night work
16. Safety program (compliance with the "Accident Prevention" clause of the contract)
17. Cultural Survey and Natural Resource Compliance requirements for off-site, non-commercial borrow pits (compliance with "Cultural Resources Survey" clause of the contract)
18. Tentative construction schedule
19. Submittal of shop drawings, project data, samples, and approved equals
20. Project closeout requirements
JUN 2010 01310-2
SCHOODIC PROPANE BOILERS PROJECT MEETINGS
21. Relationship of Division 1 to other divisions
1 .2 II. PROGRESS MEETINGS
A. The Contracting Officer will schedule weekly meetings with the Contractor and subcontractors.
B. Subcontractors will not be allowed to work until they have attended a meeting.
C. Additional meetings will be held as needed or for new subcontractors.
D. The meeting agenda will include the following as a minimum:
1. Review of work progress
2. Field observations, problems, and decisions
3. Identification of problems which impede planned progress
4. Review of Contractor’s Quality Control Program and activities
5. Review of submittals schedule and status of submittals
6. Review of off-site fabrication and delivery schedules
7. Status of project record drawings (monthly)
8. Status of operation and maintenance data manuals (monthly)
9. Maintenance of progress schedule
10. Corrective measures to regain projected schedules
11. Planned progress during succeeding work period
12. Coordination of projected progress
13. Maintenance of quality and work standards
14. Effect of proposed changes on progress schedule and coordination
15. Other business relating to work
PART 2 – PRODUCTS
Not used.
PART 3- EXECUTION
JUN 2016 01320-1 of 1
SCHOODIC PROPANE BOILERS SCHEDULES AND MONTHLY INSPECTIONS
SECTION 01320
SCHEDULES
1 .1 DESCRIPTION
A. The work of this section consists of schedule requirements before and during construction.
1 .2 SCHEDULES
A. As soon as possible after Notice of Award and before beginning any work, submit Progress Schedule and Schedule of Values as a package. Contracting Officer will review the Progress Schedule and the Schedule of Values for format and content.
1. Progress Schedule: Submit three copies of the Progress Schedule in bar chart or computer program format. Show each quote item and area of work and break down work into the smallest element. No progress payments will be made until acceptable progress schedule is provided.
2. Schedule of Values:
a. The schedule of dollar values will be based on the Contract quote Schedule. Include bond costs, mobilization, general condition costs, overhead and profit, in the total dollar value of each item.
b. The total cost of all items shall equal the contract sum. The Schedule of Values will form the basis for progress payments as provided for in the terms of the contract.
PART 2 PRODUCTS NOT USED.
PART 3 EXECUTION NOT USED.
JUN 2016 01330-1
SCHOODIC PROPANE BOILERS SUBMITTALS
SECTION 01330
SUBMITTALS
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
1.2 DEFINITIONS
A. Action Submittals: Written, graphic information, and physical samples that require Government’s responsive action.
B. Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.
C. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols. An FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files.
D. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.
1.3 GENERAL SUBMITTAL PROCEDURES
A. General: Prepare and submit submittals required by individual specification sections. Types of submittals are indicated in individual specific sections.
1. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.
B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with Contract Documents.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
JUN 2016 01330-2
a. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
C. Submittal List: A submittal list has been attached to the end of this specification section. The intent is to provide an overall summary of submittal requirements and not a comprehensive list.
The requirements of the individual specification sections, terms and conditions of the Contract still apply regardless of what is shown on the submittal list.
D. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence when an e-mail notification is received by the Contracting Officer (or designee) indicating the submittal has been submitted and is ready for review. When the Contracting Officer has completed their review, an e-mail notification will be sent to the Contractor indicating the submittal has been processed. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.
1. Action Submittals
a. Initial Review: Allow 30 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.
b. Re-submittal Review: Allow 15 days for review of each re-submittal.
2. Informational submittals
a. Review: Allow 10 days for review of each submittal.
E. Approved Equals:
1. For each item proposed as an "approved equal," submit supporting data, including:
a. Drawings and samples as appropriate.
b. Comparison of the characteristics of the proposed item with that specified.
c. Changes required in other elements of the work because of the substitution.
d. Name, address, and telephone number of vendor.
e. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.
2. A request for approval constitutes a representation that Contractor:
a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
b. Will provide the same warranties for the proposed item as for the item specified.
c. Has determined that the proposed item is compatible with interfacing items.
d. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
e. Waives all claims for additional expenses that may be incurred as a result of the substitution.
F. Electronic Submittals
JUN 2016 01330-3
1. Submit submittals as PDF electronic files via email if file size allows, or via a secure ftp web site specifically established for the project. The recipients for emailed submittals, and instructions for accessing the secure ftp site for submittals too large to email, will be provided to the Contractor by NPS at the preconstruction conference.
2. The NPS form CM-16 in unlocked (not scanned), electronically signed, PDF format shall accompany all submittals. NPS will provide the Contractor with an MS Word format copy of the form at the preconstruction conference.
G. Identification: Submittal number or other unique identifier, including revision identifier.
1. Submittal number shall use a sequential number (e.g., .001). Re-submittals shall include an alphabetic suffix after another decimal point (e.g., .001.A).
H. Re-submittals: Make re-submittals using the same process used with the initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in the title block on the CM-16 and clearly indicate the extent of revision.
3. Re-submit submittals until they are marked “Approved” or “Approved with notations”.
I. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities.
J. Use for Construction: Use only final submittals with mark indicating “Approved” or “Approved with notations”. Ensure all notations have been incorporated and, at a minimum, keep one copy of the final approved submittal on site for use during construction.
1.4 CONTRACTOR'S USE OF CAD FILES
A. General: At Contractor's written request, copies of CAD files will be provided to Contractor for Contractor's use in connection with Project, subject to the following conditions:
1. Files will be provided as is.
2. No format or other changes to files or changes to the objects in the drawing will be done by the Government.
3. The Contractor acknowledges that the CAD files are representational of the design intent for the Project and are not represented or warranted to be accurate.
4. Use of the CAD files is not a defense for failure to conform to the requirements of the
Contract Documents.
5. Reliance on dimensional or other information contained or inherent in electronic drawing is at the Contractor’s sole risk.
6. No transfer of electronic data to a third party shall be permitted.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
JUN 2016 01330-4
1. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections. If the contractor intends on supplying materials that differ from the salient characteristics specified in the individual sections, then a submittal will be required.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions: When Contract Documents require compliance with manufacturer's printed instructions, provide one complete set of instructions to Contracting Officer and keep another complete set of instructions at the project site until substantial completion.
d. Manufacturer's catalog cuts: Submit only pertinent pages; mark each page of standard printed data to identify specific products proposed for use.
e. Printed performance curves.
f. Operational range diagrams.
g. Compliance with specified referenced standards.
h. Testing by recognized testing agency.
4. Submit product data in PDF file format before or concurrent with samples.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data, unless submittal of CAD Drawings is otherwise permitted.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Shopwork manufacturing instructions.
e. Templates and patterns.
f. Schedules.
g. Notation of coordination requirements.
h. Notation of dimensions established by field measurement.
i. Relationship to adjoining construction clearly indicated.
j. Seal and signature of professional engineer if specified.
2. Submit shop drawings as a PDF electronic file.
D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
JUN 2016 01330-5
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
2. Email the CM-16 for processing and documentation of action on submitted samples.
3. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c. Sample source.
d. Submittal Number and title of appropriate Specification Section.
4. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.
5. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
a. Number of Samples: Submit four full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Contracting Officer will return submittal with options selected.
6. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.
a. Number of Samples: Submit four sets of Samples. Contracting Officer will retain three Sample sets; remainder will be returned. Retain Sample set as a Project Record Sample.
E. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.
F. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. List must include, at a minimum, Subcontractors shown in your original proposal.
2.2 INFORMATIONAL SUBMITTALS
A. General: Prepare and submit Informational Submittals required by individual Specification Sections.
1. Email informational submittals as PDF electronic files, or if too large to email post them on the project’s ftp site.
JUN 2016 01330-6
2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Informational submittals that do not comply with the requirements specified in the Contract Documents will be rejected and one copy will be returned.
B. Coordination Drawings: Comply with requirements specified in Division 01 Section "Project Management and Coordination."
C. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.
D. Installer Certificates: Prepare written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
E. Manufacturer Certificates: Prepare written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.
F. Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.
G. Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
H. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
I. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
J. Preconstruction Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
K. Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
L. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.
JUN 2016 01330-7
M. Design Data: Prepare written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations.
Include list of assumptions and other performance and design criteria and a summary of loads.
Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.
PART 3 - EXECUTION
3.1 CONTRACTOR'S REVIEW
A. Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions.
3.2 CONTRACTING OFFICER’S ACTION
A. General: Submittals will be disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect format of submittals is provided; the transmittal form is incorrectly filled out; submittals are not coordinated; or submittals do not show evidence of Contractor's approval.
1. Any work done or orders for materials or services placed before approval shall be at the Contractor's own risk.
B. Action Submittals: Contracting Officer will review each submittal, generate comments on corrections or modifications required, and indicate the appropriate action on the CM-16 Transmittal Form. The submittal will be marked in one of three ways as defined below:
1. APPROVED: Acceptable with no corrections.
2. APPROVED WITH NOTATIONS: Minor corrections or clarifications required. All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the work.
3. DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.
C. Informational Submittals: Contracting Officer will review each submittal and will either accept or reject it.
D. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.
JUN 2016 01330-8
PART 3- EXECUTION
PART 4 - MEASUREMENT AND PAYMENT
I. SUBMITTALS
A. All costs for the work of this section shall be included in the lump sum contract price.
JUN 2016 01360-1
SCHOODIC PROPANE BOILERS ACCIDENT PREVENTION
SECTION 01360
ACCIDENT PREVENTION
A. The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
II. SUBMITTALS
A. Accident Prevention Program: Before on-site work begins, submit for approval an accident prevention program. The Contracting Officer will review the proposed program for compliance with OSHA and project requirements. If the program requires any revisions or corrections, the Contractor shall resubmit the program within 10 days. No progress payments will be made until the program is approved. The program shall include:
1. Name of responsible supervisor to carry out the program.
2. Weekly and monthly safety meetings.
3. First aid procedures.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.
5. Training, both initial and continuing.
6. Planning for possible emergency situations, such as floods, fires, cave-ins, slides, explosions, power outages, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
7. Fire Protection: Section 01510.
B. Certificates: When requested, provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.
C. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.
D. Submit a report of safety meetings and of inspections.
E. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
III. QUALITY ASSURANCE
A. In case of conflicts between Federal, State, and local safety and health requirements, the
JUN 2016 01360-2
most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees:
1. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.
2. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment.
Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
IV. ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Notify Contracting Officer immediately in the event of a reportable accident. Within 3 days of a reportable accident, fill out and forward to the Contracting Officer the attached SMIS offline accident reporting worksheet.
B. All Other Accidents: The Contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
PART 2 PRODUCTS
I. FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the type of construction at the site.
II. PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of NIOSH and MSHA.
III. BARRIERS
A. Section 01525.
JUN 2016 01360-3
PART 3 EXECUTION
I. EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
II. EGRESS
A. Provide and maintain adequate egress at all times in accordance with the Life Safety Code (NFPA 101-94). No corridor, aisle, stairway, door, or exit shall be obstructed or used in a manner that interferes with egress.
III. PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
IV. SAFETY MEETINGS
A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the work site.
B. Conduct monthly safety meetings for all levels of supervision. Notify the Contracting Officer of meeting dates and times. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention program.
The Contracting Officer will attend the meeting and enter the results of the meetings into the daily log.
V. HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. A hard hat area will be designated by the Contracting Officer. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times.
VI. TRAINING
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
JUN 2016 01360-4
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
END OF
SECTION
JUN 2016 01360-5
JUN 2016 01420-1
SCHOODIC PROPANE BOILERS REFERENCE STANDARDS
SECTION 01420
REFERENCE STANDARDS
PART 1 - GENERAL
I. The following abbreviations, which may be used in the construction specifications, refer to the organizations and specifications of the organizations listed below:
AA Aluminum Association 900 19th Street, NW, Suite 300 Washington, D.C. 20006-2168
AABC Associated Air Balance Council 1518 K Street, NW, Suite 503 Washington, D.C. 20005
AAMA American Architectural Manufacturers Association 1827 Walden Office Square, Suite 104 Schaumberg, Illinois 60173-4268
AAN American Association of Nurserymen 1250 I Street, NW, Suite 500 Washington, DC 2005
AASHTO American Association of State Highway and Transportation Officials 444 North Capitol Street, NW, Suite 249 Washington, D.C. 20001
ABMA American Boiler Manufacturers Association 950 N. Glebe Road, Suite 160 Arlington, Virginia 22203-1824
ACI American Concrete Institute P.O. Box 9094 Farmington Hills, Michigan 48333-9094
ACPA American Concrete Pipe Association 222 West Las Colinas Boulevard, Suite 641 Irving, Texas 75039-5423
ADC Air Diffusion Council 11 South LaSalle Street, Suite 1400 Chicago, Illinois 60603
AFPA American Forest and Paper Association 1111 19th Street, NW, Suite 800 Washington, D.C. 20036
AGA American Gas Association 1515 Wilson Boulevard Arlington, Virginia 22209
AHA American Hardboard Association 1210 W. Northwest Highway Palatine, Illinois 60067-1897
JUN 2016 01420-2
AHAM Association of Home Appliance Manufacturers 20 N. Wacker Drive, Suite 1500 Chicago, Illinois 60606
AI Asphalt Institute Research Park Drive P.O. Box 14052 Lexington, Kentucky 40512-4052
AISC American Institute of Steel Construction 1 East Wacker Drive, Suite 3100 Chicago, Illinois 60601-2001
AISI American Iron and Steel Institute 1101 17th Street, NW Washington, D.C. 20036-4700
AITC American Institute of Timber Construction 7012 S. Revere Parkway, Suite 140 Englewood, Colorado 80112
ALSC American Lumber Standards Committee P.O. Box 210 Germantown, Maryland 20875
AMCA Air Movement and Control Association International, Inc.
30 W. University Drive Arlington Heights, Illinois 60004-1893
ANSI American National Standards Institute 11 West 42nd Street, 13th Floor New York, New York 10036
APA American Plywood Association P.O. Box 11700 Tacoma, Washington 98411-0700
APWA American Public Works Association 106 West 11th Street, Suite 1800 Kansas City, Missouri 64105-1806
ARI Air-Conditioning and Refrigeration Institute 4301 Fairfax Drive, Suite 425 Arlington, Virginia 22203
ARM Asphalt Roofing Manufacturers Association Center Park, 4041 Powder Mill Road, Suite 404 Calverton, Maryland 20705
ASC Adhesive and Sealant Council 1627 K Street, NW, Suite 1000 Washington, D.C. 20006-1707
ASHRAE American Society of Heating, Refrigerating, and Air-Conditioning Engineers 1791 Tullie Circle, NE Atlanta, Georgia 30329-2305
JUN 2016 01420-3
ASLA American Society of Landscape Architects 4401 Connecticut Avenue, NW Fifth Floor Washington, D.C. 20008-2369
ASME American Society of Mechanical Engineers 345 East 47th Street New York, New York 10017
ASPE American Society of Plumbing Engineers 3617 Thousand Oaks Boulevard, Suite 210 Westlake, California 91362-3649
ASSE American Society of Sanitary Engineering P.O. Box 40362 Bay Village, Ohio 44140
ASTM American Society for Testing and Materials 100 Barr Harbor Drive West Conshohocken, Pennsylvania 19428-2959
AWI Architectural Woodwork Institute 1952 Isaac Newton Square Reston, Virginia 20190
AWPA American Wood-Preservers' Association 3246 Fall Creek Highway, Suite 1900 Granbury, Texas 76049-7979
AWPI American Wood Preservers Institute 1945 Old Gallows Road, Suite 550 Vienna, Virginia 22182
AWS American Welding Society, Inc.
550 NW LeJeune Road P.O. Box 351040 Miami, Florida 33126
AWWA American Water Works Association 6666 W. Quincy Avenue Denver, Colorado 80235
BHMA Builders Hardware Manufacturers Association, Inc.
355 Lexington Avenue, 17th Floor New York, New York 10017-6603
BIA Brick Institute of America 11490 Commerce Park Drive Reston, Virginia 22091-1525
BOCA Building Officials Code Administrators 4051 W. Flossmoor Road Country Club Hills, Illinois 60478-5795
CBM Certified Ballast Manufacturers 1422 Euclid Avenue, Suite 402 Cleveland, Ohio 44115-2851
JUN 2016 01420-4
CDA Copper Development Association, Inc.
260 Madison Avenue, 16th Floor New York, New York 10016-2401
CE Corps of Engineers (Chief of Engineers – Referral, U.S. Department of the Army) Washington, D.C. 20314
CID Commercial Item Description See General Provisions
CISPI Cast Iron Soil Pipe Institute 5959 Shallowford Road, Suite 419 Chattanooga, Tennessee 37421
CLFMI Chain Link Fence Manufacturers Institute 9891 Broken Land Parkway, Suite 300 Columbia, Maryland 21046
CRA California Redwood Association 405 Enfrente Drive, Suite 200 Novato, California 94949
CRI Carpet and Rug Institute Box 2048 Dalton, Georgia 30722-2048
CRSI Concrete Reinforcing Steel Institute 933 N. Plum Grove Road Schaumburg, Illinois 60173-4758
CS Commercial Standard of NBS (U.S. Department of Commerce) Government Printing Office Washington, D.C. 20402
CSSB Cedar Shingle and Shake Bureau 515 116th Avenue, NE, Suite 275 Bellevue, Washington 98004-5294
DHI Door and Hardware Institute 14170 Newbrook Drive Chantilly, Virginia 22021-2223
EPA Environmental Protection Agency 401 M Street, SW Washington, D.C. 20460
FHA Federal Housing Administration (U.S. Department of Housing and Urban Development) 451 7th Street, SW Washington, D.C. 20410
FHVA Fine Hardwood Veneer Association 260 S. First Street, Suite 2 Zionsville, Indiana 46077
FM Factory Mutual System 1151 Boston-Providence Turnpike P.O. Box 9102 Norwood, Massachusetts 02062-9102
JUN 2016 01420-5
FS Federal Specifications See General Provisions
GA Gypsum Association 810 First Street, NE, Suite 510 Washington, D.C. 20002
GANA Glass Association of North America 3310 SW Harrison Street Topeka, Kansas 66611-2279
HI Hydronics Institute 35 Russo Place P.O. Box 218 Berkeley Heights, New Jersey 07922
HMA Hardwood Manufacturers Association 400 Penn Center Boulevard, Suite 530 Pittsburgh, Pennsylvania 15235-5605
HPMA Hardwood Plywood Manufacturers Association P.O. Box 2789 Reston, Virginia 22090-2789
IA Irrigation Association 1911 N. Fort Myer Drive, Suite 1009 Arlington, Virginia 22209-1630
ICBO International Conference of Building Officials 5360 S. Workman Mill Road Whittier, California 90601
ICEA Insulated Cable Engineers Association, Inc.
P.O. Box 440 South Yarmouth, Massachusetts 02664
IEEE The Institute of Electrical and Electronics Engineers 345 E. 47th Street New York, New York 10017-2394
IES Illuminating Engineering Society of North America 120 Wall Street, 17th Floor New York, New York 10005-4001
IGCC Insulating Glass Certification Council 3393 Route 11, Industrial Park P.O. Box 2040 Cortland, New York 13045-0950
ILIA Indiana Limestone Institute of America, Inc.
Stone City Bank Building, Suite 400 Bedford, Indiana 47421
KCMA Kitchen Cabinet Manufacturers Association 1899 Preston White Drive Reston, Virginia 22091-4326
LIA Lead Industries Association, Inc.
295 Madison Avenue New York, New York 10017
JUN 2016 01420-6
MBMA Metal Building Manufacturer’s Association c/o Thomas Associates, Inc.
1300 Sumner Avenue Cleveland, Ohio 44115-2851
MFMA Maple Flooring Manufacturers Association 60 Revere Drive, Suite 500 Northbrook, Illinois 60062
MIA Marble Institute of America 30 Eden Alley, Suite 201 Columbus, Ohio 43215
MIMA Mineral Insulation Manufacturers Association 1420 King Street Alexandria, Virginia 22314
MLSFA Metal Lath/Steel Framing Association - A Division of NAAMM 8 South Michigan Avenue, Suite 1000 Chicago, Illinois 60603
MS Military Standardization Documents See General Provisions
MSHA Mine Safety and Health Administration 4015 Wilson Boulevard, Room 601 Arlington, Virginia 22203
MSS Manufacturers Standardization Society of the Valve and Fittings Industry 127 Park Street, NE Vienna, Virginia 22180-4602
NAAMM The National Association of Architectural Metal Manufacturers 8 South Michigan Avenue, Suite 1000 Chicago, Illinois 60603
NACE National Association of Corrosion Engineers 1440 South Creek Drive P.O. Box 218340 Houston, Texas 77218-8340
NAIMA North American Insulation Manufacturers Association 44 Canal Center Plaza, Suite 310 Alexandria, Virginia 22314
NAPA National Asphalt Pavement Association NAPA Building 5100 Forbes Boulevard Lanham, Maryland 20706-4413
NAPCA National Association of Pipe Coating Applicators 8th Floor, Commercial National Bank Building 333 Texas Street, Suite 800 Shreveport, Louisiana 71101-3673
NBS National Bureau of Standards (U.S. Department of Commerce)(See NIST)
JUN 2016 01420-7
NCMA National Concrete Masonry Association 2302 Horse Pen Road Herndon, Virginia 20171-3499
NEC National Electrical Code (by NFPA) NECA National Electrical Contractors Association
3 Bethesda Metro Center, Suite 1100 Bethesda, Maryland 20814
NELM Northeastern Lumber Manufacturers' Association 272 Tuttle Road P.O. Box 87A Cumberland Center, Maine 04021-0687
NEII National Elevator Industry, Inc.
185 Bridge Plaza North, Suite 310 Fort Lee, New Jersey 07024
NEMA National Electrical Manufacturers Association 2101 L Street, NW, Suite 300 Washington, D.C. 20037-1526
NFPA National Fire Protection Association 1 Batterymarch Park P.O. Box 9101 Quincy, Massachusetts 02269-9101
NHLA National Hardwood Lumber Association P.O. Box 34518 Memphis, Tennessee 38184-0518
NIST National Institute of Standards and Technology (US Department of Commerce) Administration Building, Room E128 Gaithersburg, Maryland 20899
Send requests for publications to:
Superintendent of Documents Government Printing Office Washington, D.C. 20402
NHPMA Northern Hardwood and Pine Manufacturers Association, Inc., c/o Northern Softwood Lumber Bureau Box 217 Dear River, Minnesota 56636
NIOSH National Institute for Occupational Safety and Health NIOSH Building 1, Room 3007 1600 Clifton Road, NE Atlanta, Georgia 30333
NOFMA National Oak Flooring Manufacturers Association P.O. Box 3009 Memphis, Tennessee 38173-0009
NPA National Particleboard Association 18928 Premiere Court Gaithersburg, Maryland 20879-1569
JUN 2016 01420-8
NRCA National Roofing Contractors Association O'Hare International Center 10255 W. Higgins Road, Suite 600 Rosemont, Illinois 60018-5607
NSF National Sanitary Foundation 3475 Plymouth Road P.O. Box 130140 Ann Arbor, Michigan 48113-0140
NTMA The National Terrazzo and Mosaic Association 3166 Des Plaines Avenue, Suite 121 Des Plaines, Illinois 60018
NWWDA National Wood Window and Door Association 1400 East Touhy Avenue, Suite G-54 Des Plaines, Illinois 60018
OSHA Occupational Safety and Health Administration U.S. Department of Labor 200 Constitution Avenue, NW Washington, D.C. 20210
PCA Portland Cement Association 5420 Old Orchard Road Skokie, Illinois 60077-1083
PCI Precast/Prestressed Concrete Institute 175 W. Jackson Boulevard Chicago, Illinois 60604
PDI Plumbing and Drainage Institute 45 Briston Drive, Suite 101 South Euston, Massachusetts 02375
PEI Porcelain Enamel Institute, Inc.
4004 Hillsboro Pike, Suite 224-B Nashville, Tennessee 37215
PI Perlite Institute, Inc.
88 New Dorp Plaza Staten Island, New York 10306
PS Product Standard of NBS (U.S. Department of Commerce) Government Printing Office Washington, D.C. 20402
RFCI Resilient Floor Covering Institute 966 Hungerford Drive, Suite 12-B Rockville, Maryland 20850-1714
RIS Redwood Inspection Service (Grading Rules) 405 Enfrente Drive, Suite 200 Novato, California 94949
RMMI Rocky Mountain Masonry Institute 1780 South Bellaire Street, No. 602 Denver, Colorado 80222
JUN 2016 01420-9
SCMA Southern Cypress Manufacturers Association 400 Penn Center Blvd., Suite 530 Pittsburgh, Pennsylvania 15235
SDI Steel Deck Institute P.O. Box 25 Fox River Grove, Illinois 60021
SDI Steel Door Institute 30200 Detroit Road Cleveland, Ohio 44145-1967
SFPA Southern Forest Products Association P.O. Box 52468 New Orleans, Louisiana 70152
SGCC Safety Glazing Certification Council ETL Testing Labs, Inc., Industrial Park 3933 U.S. Route 11 P.O. Box 2040 Cortland, New York 13045-0950
SIGMA Sealed Insulating Glass Manufacturers Association 401 N. Michigan Avenue Chicago, Illinois 60611-4267
SJI Steel Joist Institute 3127 10th Avenue, North Ext.
Myrtle Beach, South Carolina 29577-6760
SMACNA Sheet Metal and Air-Conditioning Contractors' National Association, Inc.
4201 Lafayette Center Drive P.O. Box 221230 Chantilly, Virginia 20151-1209
SPIB Southern Pine Inspection Bureau (Grading Rules) 4709 Scenic Highway Pensacola, Florida 32504-9094
SSPC Steel Structures Painting Council 40 24th Street, 6th Floor Pittsburgh, Pennsylvania 15222-4643
SWI Steel Window Institute c/o Thomas Associates, Inc.
1300 Sumner Avenue Cleveland, Ohio 44115-2851
TCA Tile Council of America 100 Clemson Research Boulevard Anderson, South Carolina 29625
TIMA Thermal Insulation Manufacturers Association (See NAIMA) TPI Truss Plate Institute
583 D'Onofrio Drive, Suite 200 Madison, Wisconsin 53719
UBC Uniform Building Code (by ICBO)
JUN 2016 01420-10
UL Underwriters Laboratories, Inc.
333 Pfingsten Road Northbrook, Illinois 60062
USDA U.S. Department of Agriculture Independence Avenue, between 12th and 14th Streets, SW Washington, D.C. 20250
WCLB West Coast Lumber Inspection Bureau (Grading Rules) P.O. Box 23145 Portland, Oregon 97281-3145
WIC Woodwork Institute of California P.O. Box 980247 West Sacramento, California 95798-0247
WMMPA Wood Moulding and Millwork Producers Association P.O. Box 25278 Portland, Oregon 97225-0278
WRI Wire Reinforcement Institute, Inc.
203 Loudoun Street, SW Leesburg, Virginia 20175-2718
WSFI Wood and Synthetic Flooring Institute (See MFMA) WWPA Western Wood Products Association (Grading Rules)
Yeon Building 522 SW 5th Avenue Portland, Oregon 97204-2122
WWPA Woven Wire Products Association 2515 Nordica Avenue Chicago, Illinois 60635
PART 3 – EXECUTION
JUN 2016 01510-1
SCHOODIC PROPANE BOILERS TEMPORARY SERVICES
SECTION 01510
TEMPORARY SERVICES
A. The work of this section consists of providing temporary services required for Contractor's performance of the work of this contract.
B. RELATED REQUIREMENTS
1. Section 01560 - Temporary Controls.
I. GENERAL
A. Temporary materials may be new or used, but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.
II. FIRE PROTECTION EQUIPMENT
A. Extinguisher shall have a minimum UL rating of 2-A:10-B:C.
I. ELECTRICITY AND LIGHTING
A. There is electrical service available at the project site.
B. Temporary Electrical: Temporary electrical work shall meet requirements of NFPA 70
(NEC), Article 305.
II. HEATING AND VENTILATING
A. Provide and maintain adequate temporary heat in work areas without heat, as required for safety and construction requirements, during the progress of the work. Provide ample clearance around stoves and heaters and all chimney and vent connections to prevent ignition of combustible material.
JUN 2016 01510-2
III. TELEPHONE
A. No telephone service is available on site for Contractor's use.
IV. WATER
A. Furnish cool, potable water for construction personnel in locations convenient to work stations.
V. SANITARY FACILITIES
A. Facilities in buildings may be used.
VI. FIRE PREVENTION AND PROTECTION
A. Responsible person: A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.
B. Hazard Control: Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
C. Spark Arresters:
1. Written determinations of periods and areas of potential fire hazard will be issued by
Contracting Officer.
2. Equip all gasoline or diesel powered equipment used during periods of potential fire hazards or in potential forest and grass fire locations with spark arresters approved by the U.
S. Forest Service.
D. Service and Refueling Areas: Fuel all vehicles and mobile equipment off site. Fuel cans stored on site will be in secondary containment tubs.
E. Smoking: Smoking within buildings or temporary storage sheds is prohibited.
F. Welding: Cutting by torch or welding shall be performed only when adequate fire protection is provided.
VII. FIRE PROTECTION EQUIPMENT REQUIRED
A. Buildings:
1. Furnish a minimum of one extinguisher for each 1,500 square feet of area or major fraction thereof.
2. Travel distance from any work station to the nearest extinguisher shall not exceed 75 feet.
B. Vehicles and Equipment:
1. Provide one extinguisher on each vehicle or piece of equipment.
JUN 2016 01510-3
JUN 2016 01560-1 of 2
SCHOODIC PROPANE BOILERS TEMPORARY CONTROLS
SECTION 01560
TEMPORARY CONTROLS
A. The work of this section consists of providing temporary controls for the maintenance of Park cleanliness and the prevention of contamination of Park lands by construction operations.
PART 2 PRODUCTS Not Used
I. HOUSEKEEPING
A. Keep project neat, orderly, and in a safe condition at all times.
B. Provide enough containers for collecting construction debris.
C. Wet down dry materials and rubbish to prevent blowing dust.
D. Keep volatile wastes in covered fire and explosion proof containers.
E. Use or dispose of excavated material as soon as possible after excavation.
II. DISPOSAL
A. Unless otherwise specified, all removed material becomes the property of the Contractor and shall be disposed of outside the park.
B. Immediately remove hazardous rubbish from project site. Place other construction debris in refuse containers at least daily. Dispose of refuse at least weekly, in a legal manner, at public or private dumping areas outside the park. Do not burn or bury refuse inside the park.
III. AIR POLLUTION CONTROL
A. Take all necessary reasonable measures to minimize air pollution by any material or equipment used during construction.
IV. EQUIPMENT FUELING AND SERVICING
A. All construction equipment that frequently travels the Park roads (such as trucks) and other equipment that can reasonably travel from the work area, shall be fueled and serviced…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .