P16PS00939_CR_IDIQ_edited_and_referenced_clauses.pdf

PDF 655 KB Posted

Attached to
Multidisciplinary CR IDIQ Federal contract opportunity
Solicitation number
P16PS00939
Issued by
Department of the Interior National Park Service

About this file

Clauses

View the file

Other files for this federal contract opportunity

Other files attached to Multidisciplinary CR IDIQ, newest first.
File Type Posted
Sol_P16PS00939.pdf PDF
FY2016_CR_IDIQ_SOW_4-20-16_Final.pdf PDF
Technical_Exhibit_1____Position_Qualifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation

P16PS00939

Document Title

Multiple Award Indefinite Delivery/Indefinite Quantity Multi-Disciplinary CR Services

INSTRUCTIONS FOR A/E IDIQ

52.252-02—Clauses Incorporated by Reference

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the

Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these addressees):

http://www.nps.gov/hfc/acquisition/pdf/av-production/shared/section-i.pdf http://farsite.hill.af.mil/farsite.html and https://acquisition.gov/far/

52.232-10 Payments under Fixed-Price Architect-Engineer Contracts April 2010

52.236-23 Responsibility of the Architect-Engineer Contractor April 1984

52.236-24 Work Oversight in Architect-Engineer Contracts April 1984

52.249-07 Termination (Fixed-Price Architect-Engineer) April 1984

Clause # Clause Title

INSTRUCTIONS

SECTION B -- Supplies or Services and Prices 1489.216-135 Fixed Prices - Indefinite Delivery/Indefinite Quantity Contract

1489.216-140 Minimum and Maximum Amounts

SECTION C -- Descriptions and Specifications 1489.210-110 Statement of Work/Specifications

DSC-18 Document Standards

DSC-19 Standard Services

SECTION E -- Inspection and Acceptance

52.246-04 Inspection of Services--Fixed-Price

52.246-06 Inspection--Time-and-Material and Labor-Hour

1489.246-100 Inspection and Acceptance

SECTION F -- Deliveries or Performance 52.242-17 Government Delay of Work

1489.212-155 Effective Period of Contract-Time and Materials, Labor-Hour, or

Indefinite Delivery/Indefinite Quantity Fixed Rate Services Contract

SECTION G -- Contract Administration Data 1452.201-70 Authorities And Delegations

1489.242.100 Contract Administration

DOI-AAAP-

0050 v 01

Contractor Performance Assessment Reporting System

DSC-11 Fee and Payment

DSC-13 Request for Task Order Proposals

DSC-14 Travel

DSC-16 Ordering Procedures

DOI Local

Clause

Electronic Invoicing and Payment Requirements - Internet Payment

Platform (IPP)

SECTION H -- Special Contract Requirements 1489.209-71 Organizational Conflicts of Interest

1489.236-05 Material and Workmanship (Deviation)

1489.236-72 Use of Premises

1489.236-80 Construction Contracts with Architect and Engineering Firms

1489.236-82 Permits

1489.237-71 Technical Direction

1489.237-72 Key Personnel

1489.237-73 Consultant Services and Consent

52.236-25 Requirements for Registration of Designers

DSC-37 Hold Harmless Clause

52.223-18 Encouraging Contractor Policies To Ban Text Messaging While

Driving

Document Title

SECTION I -- Contract Clauses

52.252-02—Clauses Incorporated by Reference

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the

Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these addressees):

http://www.nps.gov/hfc/acquisition/pdf/av-production/shared/section-i.pdf http://farsite.hill.af.mil/farsite.html and https://acquisition.gov/far/

Clause Title Date

1452.203-70 Restrictions on Endorsements - Department of Interior July 1996

1452.204-70 Release of Claims - Department of Interior July 1996

1452.215-70 Examination of Records by the Department of Interior April 1984

1452.236-70 Prohibition Against Use of Lead-Based Paint –DOI July 1996

52.202-01 Definitions November 2013

52.203-03 Gratuities April 1984

52.203-05 Covenant Against Contingent Fees May 2014

52.203-07 Anti-Kickback Procedures May 2014

52.203-08 Cancellation Rescission and Recovery of Funds for Illegal or Improper Activity May 2014

52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity May 2014

52.203-12 Limitation On Payments To Influence Certain Federal Transactions October 2010

52.204-04 Printed or Copied Double-Sided on Recycled Paper May 2011

52.204-07 System for Award Management July 2013

52.209-06 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment

August 2013

52.209-09 Updates of Publicly Available Information Regarding Responsibility Matters July 2013

52.215-02 Audit and Records—Negotiation October 2010

52.215-02 Alt I Audit and Records—Negotiation Alternate I October 2010

52.215-08 Order of Precedence--Uniform Contract Format October 1997

52.215-10 Price Reduction for Defective Cost or Pricing Data August 2011

52.215-11 Price Reduction for Defective Cost or Pricing Data—Modifications August 2011

52.215-12 Subcontractor Cost or Pricing Data October 2010

52.215-13 Subcontractor Cost or Pricing Data—Modifications October 2010

52.217-08 Option To Extend Services November 1999

52.217-09 Option To Extend The Term Of The Contract March 2000

52.219-08 Utilization of Small Business Concerns May 2014

52.219-09 Small Business Subcontracting Plan July 2013

52.219-16 Liquidated Damages-Subcontracting Plan January 1999

52.222-03 Convict Labor June 2003

52.222-21 Prohibition of Segregated Facilities February 1999

52.222-35 Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era and Other Eligible

Veterans

September 2010

52.222-36 Affirmative Action For Workers with Disabilities October 2010

52.222-37 Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era and Other

Eligible Veterans

September 2010

52.222-40 Notification of Employee Rights Under the National Labor relations Act December 2010

52.222-50 Combating Trafficking in Persons March 2015

52.223-02 Affirmative Procurement of Bio-based Products Under Service and Construction Contracts September 2013

52.223-06 Drug Free Workplace May 2001

52.225-13 Restrictions on Certain Foreign Purchases June 2008

52.227-01 Authorization and Consent December 2007

52.227-17 Rights In Data-Special Works December 2007

52.227-18 Rights in Data--Existing Works December 2007

52.228-05 Insurance - Work on a Government Installation January 1997

52.229-03 Federal, State, and Local Taxes February 2013

52.232-17 Interest May 2014

52.232-18 Availability Of Funds April 1984

52.232-23 Assignment Of Claims May 2014

52.232-26 Prompt Payment for Fixed-Price Architect-Engineer Contracts July 2013

52.232-33 Payment by Electronic Funds Transfer-System for Award Management July 2013

52.233-03 Protest After Award August 1996

52.233-04 Applicable Law for Breach of Contract Claim October 2004

Document Title

52.237-02 Protection Of Government Buildings Equipment And Vegetation April 1984

52.242-13 Bankruptcy July 1995

52.243-01 Alt III Changes--Fixed Price (Aug 1987) - Alternate III August 1987

52.244-04 Subcontractors and Outside Associates and Consultants (Architect-Engineer Services) August 1998

52.244-06 Subcontracts for Commercial Items May 2014

52.252-04 Alterations in Contract April 1984

52.252-06 Authorized Deviations In Clauses April 1984

DSC-40 Publicity January 1999

52.215-15 Pension Adjustments and Asset Reversions

52.215-17 Waiver of Facilities Capital Cost of Money

52.215-18 Reversion or Adjustment of Plans for Postretirement Benefits (PRB)

Other than Pensions

52.222-26 Equal Opportunity

52.223-03 Hazardous Material Identification and Material Safety Data

52.224-01 Privacy Act Notification

52.224-02 Privacy Act

52.227-02 Notice and Assistance Regarding Patent and Copy Infringement

52.227-16 Additional Data Requirements

52.230-03 Disclosure and Consistency of Cost Accounting Practices

52.230-06 Administration of Cost Accounting Standards

52.232-07 Payments under Time-and-Materials and Labor-Hour Contracts

52.233-01 Alt I Disputes (Jul 2002) - Alternate I

52.237-01 Site Visit

52.242-02 Production Progress Reports

52.242-14 Suspension of Work

52.243-03 Changes--Time-and-Material or Labor-Hours

52.245-02 Government Property Installation Operation Services

52.249-06 Alt IV Termination (Cost-Reimbursement) (May 2004) - Alternate IV

52.251-01 Government Supply Sources

52.253-01 Computer Generated Forms

1452.237-70 Information Collection -- DOI

1489.236-73 Archeological Findings

1489.236-79 Conduct of Operations

1489.236-81 Rights-of-Entry

1489.236-83 Notification of Visits to Parks

1489.236-84 Meetings

1489.236-85 Investigation of Field Conditions

1489.236-86 Electrical Power and Communications Arrangements

1489.236-87 Design for the Use of the Physically Handicapped

1489.236-88 Government Rights

52.203-13 Contractor Code of Business Ethics and Conduct

52.203-14 Display of Hotline Poster(s)

52.215-23 Limitations on Pass-Through Charges.

52.216-18 Ordering

52.216-19 Order Limitations

52.216-22 Indefinite Quantity

52.219-28 Post-Award Small Business Program Representation

52.222-54 Employment Eligibility Verification

52.227-23 Rights to Proposal Data (Technical) Check if contractor filled in prior to award

52.232-19 Availability of Funds for the Next Fiscal Year

DS1452.228-70 Liability Insurance - Department of the Interior

DSC-39 Lobbying with Appropriated Money (18 USC 1913)

SECTION K -- Representations, Certifications and Other Statements of Offerors 1489.204-70 Contractor Establishment Code Number

1489.209-72 Organizational Conflict of Interest Certification

Document Title

1489.224-70 Social Security Numbers of Consultants and Certain Proprietors and

Privacy Act Statement

52.203-02 Certificate of Independent Price Determination

52.203-11 Certification and Disclosure Regarding Payments to Influence Certain

Federal Transactions

52.204-08 Annual Representations and Certifications

52.230-01 Cost Accounting Standards Notices and Certification

SECTION L -- Instructions, Conditions and Notices to Bidders 52.215-16 Facilities Capital Cost of Money

52.216-01 Type of Contract

DS52.233-02 Service of Protest (Para (a) modified by DSC)

Document Title

SECTION B -- SUPPLIES OR SERVICES AND PRICES

1489.216-135 Fixed Prices - Indefinite Delivery/Indefinite Quantity Contract November 2002

The fixed rates on the following Labor Rate pages shall apply for payment purposes for the duration of the contract. Fully loaded rates for base year and option years include overhead and profit. Option years include escalation.

Fixed price or time and material task orders will be issued against this contract for the services specified in each task order, based upon a combination of hourly rates and other established prices as stated in the schedule.

Required disciplines for projects include but are not limited to: Archaeology, History, National Register of Historic Places and

National Landmark Studies (NRNHL). Additional services: CADD drafting (use of AutoCAD and Bentley), word processing, power point, Adobe InDesign, Adobe Illustrator etc. may be required in the performance of specific task order requirements.

1489.216-140 MINIMUM AND MAXIMUM AMOUNTS APRIL 1984

During the period specified in Clause entitled "Effective Period of the Contract-Time and Materials, Labor Hour or Indefinite

Delivery/Indefinite Quantity Fixed Rate Contract" in Section F, including all options exercised by the Government, the minimum quantity of services ordered by the Government shall equal $200,000.00 worth of services. The total quantity of services ordered will not exceed $2,500,000.00 worth of services per order. The total quantity of services ordered in all orders shall not exceed

$2,500,000.00 worth of services during the base year, and shall not exceed an aggregate total amount of $2,500,000.00 during the life of the Contract.

Document Title

SECTION C -- DESCRIPTIONS AND SPECIFICATIONS

1489.210-110 STATEMENT OF WORK/SPECIFICATIONS NOVEMBER 2002

The professional services that may be provided under this contract are of an architect or engineering nature, as defined by State law, as applicable, which are required to be performed or approved by a person licensed, registered, or certified to provide such services.

Reference FAR Clause 52.236-25 Requirement for Registration of Designers (JUN 2003).

The types of services to be performed under this contract, include, identified in attached Section C, Statement of Work

A documented internal Quality Control program shall be applied to all services performed.

Task Orders may be placed by other Federal agencies, provided an Interagency Agreement or Memorandum of Understanding authorizing such use exists between the National Park Service and the Federal agency requesting the services. Use of this contract by other Federal agencies must be approved in advance by the Contracting Officer assigned responsibility for administration of this contract. The task orders issued by other Federal agencies must be in accordance with the requirements, terms, conditions, and within the scope and intent of this contract.

DSC-18 DOCUMENT STANDARDS MARCH 2002

A. Design shall be accomplished by licensed or registered design professionals in accordance with applicable codes, accepted standards and National Park Service Design Process Guidelines (Operations Manual, Part 2, Design Process).

B. Construction Drawings:

a. Complete construction drawings shall be prepared in AutoCAD. They shall be developed from the approved preliminary drawings and they shall embody adequate architectural, landscape architectural, civil, structural, mechanical, and electrical drawings showing details, dimensions, notational information and other data to ensure the construction contractor has a complete understanding of all elements of work. Professional registration stamps for the responsible disciplines shall be required on all final drawing sheets.

b. Drawings shall be prepared in accordance with the National Park Service publication "Preparation of Design and Construction

Drawings" NPS-10 Rel. 3, and the Denver Service Center Publication "CADD User's Guide". Note that the bidding documents will be issued as half sized prints, therefore strict adherence to these standards is critical.

c. Format: All drawings shall be prepared electronically using AutoCAD, and shall meet the standard and guidelines set forth in the

DSC CADD Standards document, the "CADD User's Guide."

d. All drawings shall be prepared using the standard NPS border sheet of 22 inch x 34--inch. The required NPS standard border sheets will be furnished in electronic format by the Contracting Officer without charge to the A/E. Title, drawing designation, and other identification of each drawing shall be approved by the Contracting Officer.

e. Directory structure and file naming, as identified in the CADD User's Guide, must be followed. All colors used in drawing files will comply with the DSC Pen/Color configuration, found in the CADD User's Guide.

f. Quality: All drawings shall be prepared in such manner as to facilitate 35 millimeter filming and reduced-size reproduction.

Detailing, lettering, spacing, line-weight, scale and other principles of technique shall be so executed as to ensure clarity and faithfulness in reduced-size reproduction, in the enlarged image as projected in 35 millimeter reading equipment, and in the

"blow-back" from the 35 millimeter film to a reduction identical in size to the original tracing. All letters and numerals shall be at least 1/8-inch in height, adequately spaced in single- stroke upper-case Gothic style, preferably vertical. All lines, strokes, letters and numerals shall be uniformly dense as practicable. Scale identification shall be by graphic illustration or by appropriate explanation to scale notation.

C. Specifications: All specifications prepared under this contract, including technical specifications, general requirements (provided by NPS contracting division), contract bid schedules and a table of contents, shall be prepared in accordance with the NPS "Guide for

Specifiers" which prescribes, in part, that technical specifications shall be written in accordance with the Manual of Practice written by the Construction Specifications Institute.

D. The Resource Conservation and Recovery Act (RCRA), Section 6002 and Executive Order 13101 require the purchase of

Environmental Protection Agency (EPA) designated products with a required minimum recovered material content as described in an agency's Affirmative Procurement Program (APP). This list of EPA-designated products is available at http://www.epa.gov/cpg. This requirement applies to all contracts that require EPA-designated products. When purchasing a product or products on this list without

Document Title the required minimum recovered material content, a written justification based on specific exemptions is required by FAR 23.405(c).

A/E firms and their consultants are required to be familiar with EPA's guidelines by developing specifications utilizing EPA's minimum recycled content standards. If products specified by the A/E under this task order do not meet EPA's guidelines, the A/E must prepare written justifications in accordance with FAR 23.405(c).

E. A/E firms are to use life-cycle cost analysis, wherever feasible and appropriate, to assist selecting in products and services.

Whenever possible, cost shall be calculated over the life of the item, not just the initial, up-front cost. When comparing alternative products, the initial cost of the acquisition as well as lifetime maintenance costs, operational costs, etc., must be considered in the analysis. A product having a higher initial cost may have lower operational cost or a higher resale value and will, therefore, prove to be a better value and more cost effective compared to the alternatives.

F. All designs shall comply with:

a. Applicable national and local building codes

b. OSHA requirements

c. National Electric Code

d. National Electrical Safety Code

e. Uniform Mechanical Code

f. National Fire Protection Association Standards

g. All other applicable codes and standards

G. Cost Estimates: Format of bid schedule and cost estimate shall be compatible. A Class "C" estimate is a conceptual cost estimate based on square foot cost of similar construction or unit cost. A Class "B" estimate is based on an approved preliminary design, and is comprised of partial lump sum and unit costs. A Class "A" estimate is based on a complete quantity take-off from completed construction drawings and specifications. When partial lump sum and allowable prices are used, the back-up information to explain these costs shall be furnished, such as labor, material and equipment cost.

H. Final specifications, technical reports, and special studies shall be in Microsoft Word format and prepared using standard word processing practices, with automatic page and paragraph numbering (using the "automatic" selection at each level) intact.

I. Cost estimates shall be prepared using either an estimating software program or in a spreadsheet format.

DSC-19 STANDARD SERVICES FEBRUARY 2001

A. Security: The safe and undamaged delivery to the Contracting Officer of all drawings, reports, estimate and related materials executed by or in behalf of the A/E is the responsibility of the A/E.

B. Other: The cost of transporting from the office of the A/E all correspondence, drawings, reports, samples and related matter shall be borne by the A/E without additional reimbursement by the Government. Local correspondence by priority mail or commercial courier service and original or reproducible drawings by insured, certified mail, return receipt requested.

C. Monthly Status Reports: Furnish monthly status reports of all work completed to date and schedule of work to be done, revised as necessary, in the form of a flow diagram or bar chart with sufficient supporting narrative. Monthly reports are to be submitted beginning at the end of the first month subsequent to the execution of the Contract.

D. The contractor shall respond to Government review comments by modifying the documents as appropriate and, in addition, by preparing typed memoranda which respond specifically to each question or comment. These memoranda shall be submitted to the

Government within two weeks of receiving the Government's written review comments.

E. Documentation of Project Discussions, Meetings, and Work Sessions: The A/E shall maintain a record of project discussions by preparing typed notes of all meetings, trips, work sessions, important phone conversations, and other communications regarding the project. Copies of these notes, along with other correspondence relating to the project shall be mailed to the Government no later than two weeks following the particular meeting, phone conversation, or project communication.

F. Approval Stages: All documents will be subject to approval by the Denver Service Center at draft and final stages. Required changes within the Scope of Work based on these reviews will be the responsibility of the contractor. Documents will be reviewed for:

Document Title accuracy, consistency, and completeness of mechanical editing quality and effectiveness of any reorganizing, rewriting, refining, formatting, or other substantive editing that is requested quality, accuracy, consistency, and completeness of camera- ready materials

Data and Materials to be provided by Government - the items outlined in herein and in each task order shall be provided by the

Government for the use of the A/E, as required for the express purpose of completing the services required in the Scope of Services for each task order. These items shall be returned to the Government upon completion of the work, before final payment is made, unless approved otherwise by the Contracting Officer.

1. Guide for Specifiers, prepared by the Denver Service Center.

2. Guide Specifications: Division 1: General Requirements.

3. NPS-10, Drawings Format and Drafting Practices Guideline for Design and Construction Drawings.

4. DSC CAD Standards Guide, January 2007

5. NPS Guide Specs on Disk

Document Title

SECTION E -- INSPECTION AND ACCEPTANCE

52.246-04 INSPECTION OF SERVICES--FIXED-PRICE AUGUST 1996

(a) Definition. “Services,” as used in this clause, includes services performed, workmanship, and material furnished or utilized in the performance of services.

(b) The Contractor shall provide and maintain an inspection system acceptable to the Government covering the services under this contract. Complete records of all inspection work performed by the Contractor shall be maintained and made available to the

Government during contract performance and for as long afterwards as the contract requires.

(c) The Government has the right to inspect and test all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The Government shall perform inspections and tests in a manner that will not unduly delay the work.

(d) If the Government performs inspections or tests on the premises of the Contractor or a subcontractor, the Contractor shall furnish, and shall require subcontractors to furnish, at no increase in contract price, all reasonable facilities and assistance for the safe and convenient performance of these duties.

(e) If any of the services do not conform with contract requirements, the Government may require the Contractor to perform the services again in conformity with contract requirements, at no increase in contract amount. When the defects in services cannot be corrected by re-performance, the Government may—

(1) Require the Contractor to take necessary action to ensure that future performance conforms to contract requirements; and

(2) Reduce the contract price to reflect the reduced value of the services performed.

(f) If the Contractor fails to promptly perform the services again or to take the necessary action to ensure future performance in conformity with contract requirements, the Government may—

(1) By contract or otherwise, perform the services and charge to the Contractor any cost incurred by the Government that is directly related to the performance of such service; or

(2) Terminate the contract for default.

52.246-06 INSPECTION--TIME-AND-MATERIAL AND LABOR-HOUR MAY 2001

(a) Definitions. As used in this clause—

“Contractor’s managerial personnel” means any of the Contractor’s directors, officers, managers, superintendents, or equivalent representatives who have supervision or direction of—

(1) All or substantially all of the Contractor’s business;

(2) All or substantially all of the Contractor’s operation at any one plant or separate location where the contract is being performed;

or

(3) A separate and complete major industrial operation connected with the performance of this contract.

“Materials” includes data when the contract does not include the Warranty of Data clause.

(b) The Contractor shall provide and maintain an inspection system acceptable to the Government covering the material, fabricating methods, work, and services under this contract. Complete records of all inspection work performed by the Contractor shall be maintained and made available to the Government during contract performance and for as long afterwards as the contract requires.

(c) The Government has the right to inspect and test all materials furnished and services performed under this contract, to the extent practicable at all places and times, including the period of performance, and in any event before acceptance. The Government may also inspect the plant or plants of the Contractor or any subcontractor engaged in contract performance. The Government shall perform inspections and tests in a manner that will not unduly delay the work.

(d) If the Government performs inspection or test on the premises of the Contractor or a subcontractor, the Contractor shall furnish and shall require subcontractors to furnish all reasonable facilities and assistance for the safe and convenient performance of these duties.

Document Title

(e) Unless otherwise specified in the contract, the Government shall accept or reject services and materials at the place of delivery as promptly as practicable after delivery, and they shall be presumed accepted 60 days after the date of delivery, unless accepted earlier.

(f) At any time during contract performance, but not later than 6 months (or such other time as may be specified in the contract) after acceptance of the services or materials last delivered under this contract, the Government may require the Contractor to replace or correct services or materials that at time of delivery failed to meet contract requirements. Except as otherwise specified in paragraph (h) of this clause, the cost of replacement or correction shall be determined under the Payments Under Time-and-Materials and Labor-Hour Contracts clause, but the “hourly rate” for labor hours incurred in the replacement or correction shall be reduced to exclude that portion of the rate attributable to profit. The Contractor shall not tender for acceptance materials and services required to be replaced or corrected without disclosing the former requirement for replacement or correction, and, when required, shall disclose the corrective action taken.

(g)(1) If the Contractor fails to proceed with reasonable promptness to perform required replacement or correction, and if the replacement or correction can be performed within the ceiling price (or the ceiling price as increased by the Government), the

Government may—

(i) By contract or otherwise, perform the replacement or correction, charge to the Contractor any increased cost, or deduct such increased cost from any amounts paid or due under this contract; or

(ii) Terminate this contract for default.

(2) Failure to agree to the amount of increased cost to be charged to the Contractor shall be a dispute.

(h) Notwithstanding paragraphs (f) and (g) of this clause, the Government may at any time require the Contractor to remedy by correction or replacement, without cost to the Government, any failure by the Contractor to comply with the requirements of this contract, if the failure is due to—

(1) Fraud, lack of good faith, or willful misconduct on the part of the Contractor’s managerial personnel; or

(2) The conduct of one or more of the Contractor’s employees selected or retained by the Contractor after any of the Contractor’s managerial personnel has reasonable grounds to believe that the employee is habitually careless or unqualified.

(i) This clause applies in the same manner and to the same extent to corrected or replacement materials or services as to materials and services originally delivered under this contract.

(j) The Contractor has no obligation or liability under this contract to correct or replace materials and services that at time of delivery do not meet contract requirements, except as provided in this clause or as may be otherwise specified in the contract.

(k) Unless otherwise specified in the contract, the Contractor’s obligation to correct or replace Government-furnished property shall be governed by the clause pertaining to Government property.

1489.246-100 INSPECTION AND ACCEPTANCE APRIL 1984

(a) The Contracting Officer or the duly authorized representative will perform inspection and acceptance of materials and services to be provided.

(b) For the purposes of this clause, the authorized representative of the Contracting Officer will be designated on a Task Order basis by the National Park Service, National Capital Region Office, Chief Archaeologist, Directorate of Resource, Stewardship, and

Science, Telephone No. 202-619-7080. Contracting Officer’s Representatives will be established under Appointment Letter issued by the Contracting Officer.

(c) The method and location for inspection and acceptance will be set in each individual task order.

Document Title

SECTION F -- DELIVERIES OR PERFORMANCE

52.242-17 GOVERNMENT DELAY OF WORK APRIL 1984

(a) If the performance of all or any part of the work of this contract is delayed or interrupted (1) by an act of the Contracting Officer in the administration of this contract that is not expressly or impliedly authorized by this contract, or (2) by a failure of the Contracting

Officer to act within the time specified in this contract, or within a reasonable time if not specified, an adjustment (excluding profit) shall be made for any increase in the cost of performance of this contract caused by the delay or interruption and the contract shall be modified in writing accordingly. Adjustment shall also be made in the delivery or performance dates and any other contractual term or condition affected by the delay or interruption. However, no adjustment shall be made under this clause for any delay or interruption to the extent that performance would have been delayed or interrupted by any other cause, including the fault or negligence of the

Contractor, or for which an adjustment is provided or excluded under any other term or condition of this contract.

(b) A claim under this clause shall not be allowed—

(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved; and

(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the delay or interruption, but not later than the day of final payment under the contract.

1489.212-155 EFFECTIVE PERIOD OF CONTRACT-TIME AND

MATERIALS, LABOR-HOUR, OR INDEFINITE

DELIVERY/INDEFINITE QUANTITY FIXED RATE SERVICES

CONTRACT

JANUARY 1999

(a) The effective period of this contract is from __________ through ___________.

(b) The Government has the option to extend the effective period of this Contract for 4 additional period(s). If more than 60 days remain in the Contract effective period, the Government, without prior written notification, may exercise this option by issuing a

Contract Modification. To unilaterally exercise this option within the last 60 days of the effective period, the Government must issue written notification of its intent to exercise the option prior to that last 60 day period. This preliminary notification does not commit the Government to exercising the option.

(c)) If the options are exercised, the "Minimum and Maximum Contract Amount" clause will be modified to reflect new and separate maximum amounts:

Period Minimum Amount Maximum Amount

Option Period I $200,000.00 $2,500,000.00

Option Period II $200,000.00 $2,500,000.00

Option Period III $200,000.00 $2,500,000.00

Option Period IV $200,000.00 $2,500,000.00

*The contractor is guaranteed a minimum of $200,000.00 during the life of the contract. The total quantity of services ordered in all orders shall not exceed $2,500,000.00 worth of services during the base year, and shall not exceed an aggregate total amount of

$2,500,000.00 during the life of the Contract.

(d) The "Effective Period of the Contract" clause will be modified as follows:

Start Date End Date

Option Period I _________ _________

Option Period II _________ _________

Option Period III _________ _________

Option Period IV _________ _________

Document Title

SECTION G -- CONTRACT ADMINISTRATION DATA

1452.201-70 AUTHORITIES AND DELEGATIONS SEPTEMBER 2011

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without prior authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the

Contractor's risk.

1489.242.100 CONTRACT ADMINISTRATION APRIL 1984

Contracting Officer's Technical Representative(s) for this contract will be established for each Task Order.

Contract Specialist(s) responsible for administering this contract:

Administrative Contracting Officer: John Warner National Park Service, National Capital Region, Office of Acquisition, Financial Assistance, and Property Management

1100 Ohio Drive, SW

Washington, DC 20242 Telephone No. (202) 619-6381 Fax No. (202) 485-9720

John_k_warner@nps.gov

DOI-AAAP-

0050 v 01

USING AND REPORTING OF CONTRACTOR

PERFORMANCE INFORMATION

DECEMBER 2015

Document Title

1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the

Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past

Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.

3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO).

Information in the report must be protected as source selection sensitive information not releasable to the public.

4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.

5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.

a. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.

b. Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.

c. All information provided should be reviewed for accuracy prior to submission.

d. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.

e. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.

f. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."

6. The following guidelines apply concerning your use of the past performance evaluation:

Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.

a. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

b. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.

7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your

60-day review period.

8. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

DSC-11 FEE AND PAYMENT APRIL 1984

For the furnishing of all services as specified in each individual Task Order, the A/E shall be paid the total price as specified in each

Task Order. Task orders may be issued on a firm-fixed price basis, on a total amount not-to-exceed basis or a combination of both.

Final task order amounts will be established on the basis of hourly rates and other rates as set forth in Section B.

Progress payments to the A/E shall be made on the basis of proper and acceptable invoices submitted monthly for the actual percentage of services completed by the A/E and shall be made in accordance with the provisions of Section I Contract Clauses except as follows:

Partial payments for Title I Services shall not exceed 90% of the total amount established under the task order. At the completion of the Title I Services and after acceptance by the Government of the Title I documents, the final payment will be authorized.

Partial payments for Title II Services shall not exceed 90% of the total amount established under the task order. At the completion of the Title II Services and after acceptance by the Government of all Title documents, the final payment may be authorized. The https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.cpars.gov/ https://www.cpars.csd.disa.mil/ https://www.cpars.csd.disa.mil/

Document Title

Government reserves the right to withhold the final payment until the construction work resulting from the design contract has been completed and accepted by the Government. REFERENCE FAR 52.232.10 PAYMENTS UNDER FIXED-PRICE

ARCHITECTENGINEER CONTRACTS.

Payments for not-to-exceed type services, when such services are authorized, shall be made to the A/E on the basis of monthly itemized invoices. Invoices shall include a description of the work performed and the cost for the month, broken down by discipline and labor hours. Invoices should also include receipts for actual direct expenses claimed, including travel expenses.

Note: Proper invoices shall be received within 60 days after the work is performed. Invoices for work performed over 60 days will not be paid.

After completion of the work and as a prerequisite to the final payment on each task order, the A/E shall furnish to the Contracting

Officer a Release of Claims arising out of each Task Order. Such claims as are asserted by the A/E and excepted from operation of the Release (see enclosed Form DI-137) shall be listed in spaces provided after the word "except" and shall be referenced to correspondence or other identifying data, together with monetary amount for each major claim item.

Original invoices are to be mailed directly to the National Park Service, National Capital Region Office of Acquisition Management, 1100 Ohio Drive, SW, Washington, DC 20242.

DSC-13 REQUEST FOR TASK ORDER PROPOSALS APRIL 1984

The Contractor's failure to respond to any task order proposal shall be considered a failure to meet a material contract requirement and may be grounds for default. The costs of preparing any task order proposal shall not be charged to and shall not be an allowable cost under this contract.

DSC-14 TRAVEL JANUARY 2003

All travel to be performed in connection with the services to be rendered under this Contract shall be included in the price for each individual Task Order and shall be at no additional expense to the Government.

However, if additional travel by the A/E becomes necessary and when authorized in writing by the Government, the A/E will be reimbursed for such travel as follows:

A. Commercial Carriers: Current Commercial Coach or Tourist Rate

B. Taxi: Actual Expense

C. Auto Expense:

1.Commercial : Actual Expense

2. Private: Per Federal Travel Regulations

D. Subsistence: Per Federal Travel Regulations

DSC-16 ORDERING PROCEDURES APRIL 1984

(a) Upon receipt of any order issued hereunder by the Contracting Officer (CO), the A/E, pursuant to such order, shall furnish to the

Government services of the type and at the prices set forth in the task order. Order may be issued at the discretion of the Government during the period set forth elsewhere in this contract.

(b) The total amount of each order shall establish a ceiling price (for Time & Material task orders) or a firm-fixed price (for Fixed

Price task orders) for the order, which the A/E shall not exceed without prior written authorization from the CO. Any changes to the ceiling or fixed price will be issued in writing, will set forth any additional obligation incurred by the Government, and will be signed by the Contracting Officer.

(c) Each task order shall be placed in accordance with the following procedures:

(1) The CO shall furnish the A/E with a written request for proposal. The request shall include:

a. a description of the specified work required,

b. the type of task order to be awarded,

c. the desired project delivery schedule,

d. the place and manner of inspection and acceptance, Document Title

e. the proposal due date, and

f. any other pertinent information.

(2) The A/E shall, within the time specified, provide the CO a copy of the task order proposal that address:

a. The technical/management approach that the A/E is proposing to accomplish the work effort, including any assumptions made by the A/E.

b. A detailed cost estimate showing direct and indirect costs. Include in the detailed estimate, the labor rates identified in Section

B of the contract as well as other costs to perform the services.

c. Any other pertinent terms, conditions, or assumptions.

(3) Upon receipt of the task order proposal, the CO and COR shall review the proposal to ensure acceptability to the Government, and enter into such discussions with the A/E as may be necessary to correct and/or revise the proposal costs and to reach agreement as to scope, schedule and price.

(4) Upon completion of this process, the CO will prepare a unilaterally issued task order which shall include:

a. Scope of Services, including references to applicable specifications,

b. the place and manner of inspection and acceptance,

c. any Government-furnished property,

d. an estimated cost of performance (for Time & Material task orders) or firm-fixed price (for Fixed Price task orders) which may not be exceeded without prior written authorizations,

e. the delivery date or period of performance,

f. accounting and appropriation data, and

g. any other pertinent information deemed necessary to the performance of the order.

Only upon receipt of such executed order, signed by the CO, shall the A/E commence work.

(d) The A/E shall notify the CO if any significant difficulties with regard to performance according to the terms of the order are anticipated or any time significant difficulties in performance arise. If, at any time during the performance of a Time & Material task order it appears that additional funds will be required to complete performance of the task order, the A/E shall promptly notify the CO in writing. Such notification shall include the costs expended, an estimate of costs required to complete the order, and an explanation of why the originally negotiated estimated costs were not adequate. The Government shall have the right to require the A/E to continue performance up to the originally estimated cost level and to suspend work thereafter, negotiate a new set of work priorities to be completed within the remaining funds, to modify the order, increasing the estimated cost to the level appropriate for completion of the work, or to modify the order to reduce the total to coincide with actual work accomplished.

DOI LOCAL

CLAUSE

ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS -

INTERNET PAYMENT PLATFORM (IPP)

APRIL 2013

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform

System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

FAR 52.232-07 Payments Under Time and Materials and Labor Hour Contracts

FAR 52.232-10 Payments Under Fixed-Price Architect-Engineer Contracts

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor

Government Business Point of Contact (as listed in SAM will receive enrollment instructions via email from the Federal Reserve

Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause)

Document Title

SECTION H -- SPECIAL CONTRACT REQUIREMENTS

1489.209-71 ORGANIZATIONAL CONFLICTS OF INTEREST APRIL 1984

(a) The Contractor warrants that, to the best of the Contractor's knowledge and belief, there are no relevant facts or circumstances which could give rise to an organizational conflict or interest, as defined in FAR Subpart 9.5, or that the Contractor has disclosed all such relevant information.

(b) The Contractor agrees that if an actual or potential organizational conflict of interest is discovered after award, the Contractor will make a full disclosure in writing to the Contracting Officer.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .