2015_Roof_Bid_Schedule_7-1-15.docx

DOCX document 31 KB Posted

Attached to
z--Roofing Project Cuyahoga Valley NP Federal contract opportunity
Solicitation number
P15PS00615
Issued by
Department of the Interior National Park Service

About this file

Revised Price Schedule

View the file

Other files for this federal contract opportunity

Other files attached to z--Roofing Project Cuyahoga Valley NP, newest first.
File Type Posted
Sol_P15PS00615_Amd_000001.pdf PDF
CUVA_Roofing_SOW_FY15_7-1-15.doc DOC document
CUVA_Roof_Q A.docx DOCX document
2015_Roof_Bid_Schedule_6-1-15_final.docx DOCX document
OH121.txt TXT text file
CUVA_Roofing_SOW_FY15_final.doc DOC document
FORM_Past_Performance_Questionnaire.pdf PDF
Sol_P15PS00615.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUYAHOGA VALLEY NATIONAL PARKJuly 1 2015
2015 Cuyahoga Valley NP Roofing ProjectPage 1 of 2

Revised BID SCHEDULE

Submit bid for all items. In case of error in the extension of prices, unit price governs. In case of error in summation, the total of the corrected amounts governs. Quantities for unit price bid items are estimated,

Item
Description
Unit
Unit

Cost Total

1.
Boston Store Wood shingles

1548 Boston Mills rd. Peninsula, OH 44264 2280Square Feet

1a.
20% Replacement = 540 Sq. Ft

456Square Feet

2.
Richardson house 3-tab fiberglass w/ ½ round gutters

4171 Riverview rd. Peninsula, OH 44264

1900Square Feet

2a.
20% Replacement = 380 Sq. Ft

380Square Feet

3.
Richardson garage 3-tab fiberglass w/ ½ round gutters

4171 Riverview rd. Peninsula, OH 44264 800Square Feet

3a.
20% Replacement = 160Sq. Ft

160Square Feet

4.
Hunt Barn 3-tab fiberglass w/ ½ round gutters

2054 Bolanz rd., Peninsula, OH 44264 950Square Feet

4a.
20% Replacement = 190Sq. Ft

190Square Feet

5.
Hunt comfort station 3-tab fiberglass w/ ½ round gutters

2054 Bolanz Rd. Peninsula, OH 44264 550 Square Feet

5a.
20% Replacement = 110 Sq. Ft

110 Square Feet

6.
Kepner house 3-tab fiberglass w/ ½ round gutters

4722 Riverview rd., Peninsula 44264 2342Square Feet

6a.
20% Replacement = 468 Sq. Ft

468 Square Feet

7.
Muar house 3-tab fiberglass w/ ½ round gutters

4642 Riverview rd. Peninsula 44264 1700 Square Feet

7a.
20% Replacement = 340 Sq. Ft

340 Square Feet

8.
Hardy house 3-tab fiberglass w/ ½ round gutters

2167 Everett rd. Peninsula 44264 1800Square Feet

8a.
20% Replacement = 360 Sq. Ft

360Square Feet

Sub Total of Items 1 – 8a.

Overhead ____________ %

Profit _____________%

Bonds ____________%

TOTAL of lines 1 -8a, Overhead, Profit and Bonds:

OPTION 1

Unit
Unit cost
Total
9.
Pine Hollow Comfort Station Wood shake w/ aluminum K gutters

5465 Quick Road, Peninsula 44264 1944 Square Feet

9a.
20% Replacement = 388Sq Ft

388 Square Feet

OPTION 2

10.
Everett school house wood shake, no gutters

2279 Everett Road, Peninsula, OH 44264 700 Square Feet

10a.
20% Replacement = 140 Sq. Ft
140 Square Feet

OPTION 3

11.
Stewart Shed 3-tab fiberglass w/ ½ round gutters 4690 Riverview rd. Peninsula, OH 44264
421Square Feet
11a.
20% Replacement = 84 Sq. Ft

84 Square Feet

OPTION 4

12.
Sager Shed 3-tab fiberglass w/ ½ round gutters

4690 Riverview Road, Peninsula, OH 44264 315 Square Feet

12a.
20% Replacement = 63 Sq. Ft

63 Square Feet

OPTION 5

13.
Jurovat House 3-tab fiberglass w/ ½ round gutters

696 Streetsboro, Peninsula, OH 44264 3117 Square Feet

13a.
20% Replacement = 623Sq. Ft

623 Square Feet

OPTION 6

14.
Gleason barn Corrugated steel , no gutters

7243 Canal rd. Valley View , Ohio 44125 8200 Square Feet

14a.
20% Replacement = 1640 Sq. Ft
1640 Square Feet

OPTION 7

15.
CMA GAF 60 mil TPO white membrane or equivalent , no gutters

9329 Riverview rd. Brecksville, Ohio 3000 Square Feet

15a.
20% Replacement = 600 Sq. Ft

600 Square Feet

Sub Total of Items 9 – 15a

Overhead ____________ %

Profit _____________%

Bonds ____________%

TOTAL of Additional lines 9 – 15a, Overhead, Profit and Bonds:

TOTAL of line items 1 through 15a, Overhead, Profit and Bonds:

File details come from the government source that posted it. Updated .