05_Specifications_and_Statement_of_Work.pdf

PDF 10 MB Posted

Attached to
SEKI LP VC HVAC - CONSTRUCTION Federal contract opportunity
Solicitation number
P15PS00174
Issued by
Department of the Interior National Park Service

About this file

Specifications and Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to SEKI LP VC HVAC - CONSTRUCTION, newest first.
File Type Posted
Sol_P15PS00174_Amd_000003.pdf PDF
Davis_Bacon_Wage_Determination_Tulare_County_1.30.2015.pdf PDF
REVISED_-_Contract_Price_Schedule.xlsx XLSX spreadsheet
RFI s_and_Government_Response_1-30-14.pdf PDF
Sol_P15PS00174_Amd_000002.pdf PDF
07_General_References.pdf PDF
01_FedBizzOpps_Instructions.pdf PDF
02_Site_Visit_Agenda.pdf PDF
04_Site_Visit_Sign_In_Sheet.pdf PDF
05_Subcontractor_Reference.pdf PDF
Sol_P15PS00174_Amd_000001 1 .pdf PDF
03_Site_Visit_-_O A.pdf PDF
06_Past_Performance_Questionnaire.pdf PDF
04_Davis_Bacon_Wage_Determination_Tulare_County.pdf PDF
01_Bid_Bond_SF_24-98.pdf PDF
06_Drawings.pdf PDF
07_Bidder_Submittal_Instructions.pdf PDF
Contract_Price_Schedule.xlsx XLSX spreadsheet
03_Form_2-_Key_Personnel.pdf PDF
02_Form_1-_Experience_ _Past_Performance.pdf PDF
Sol_P15PS00174.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEQUOIA AND KINGS CANYON NATIONAL PARKS

CALIFORNIA

LODGEPOLE VISITOR CENTER

HVAC REHABILITATION

SEKI

PMIS #157075

CONSTRUCTION DOCUMENTS

SPECIFICATIONS

November 12, 2014

FFA Architecture + Interiors

520 SW Yamhill Street, Suite 900 Portland, Oregon 97204Tel. 503.327.0335

Fax. 503.222.1701

SEKI 157075 TABLE OF CONTENTS PAGE 1

TABLE OF CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS

011110 SUMMARY OF WORK

012700 DEFINITION OF CONTRACT LINE ITEMS

013100 PROJECT MANAGEMENT AND COORDINATION

013216 CONSTRUCTION SCHEDULE

013323 SUBMITTAL PROCEDURES

013513.22 ARCHEOLOGICAL PROTECTION

013523 SAFETY REQUIREMENTS

013591 HISTORIC PRESERVATION TREATMENT PROCEDURES

014000 QUALITY REQUIREMENTS

014200 REFERENCES

015000 TEMPORARY FACILITIES AND CONTROLS

015719.11 INDOOR AIR QUALITY MANAGEMENT

015719.12 NOISE AND ACOUSTICS MANAGEMENT

015723 TEMPORARY STORM WATER POLLUTION PREVENTION

016700 PRODUCT REQUIREMENTS

017329 CUTTING AND PATCHING

017340 EXECUTION

017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017700 CLOSEOUT PROCEDURES

017823 OPERATION AND MAINTENANCE DATA

017900 DEMONSTRATION AND TRAINING

DIVISION 02 – EXISTING CONDITIONS

024291 SELECTIVE DEMOLITION

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

061000 ROUGH CARPENTRY

062000 FINISH CARPENTRY

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

072100 THERMAL INSULATION

074623 WOOD SIDING

078400 FIRESTOPPING

079005 JOINT SEALERS

SEKI 157075 TABLE OF CONTENTS PAGE 2

DIVISION 08 – OPENINGS

081416 FLUSH WOOD DOORS

087100 DOOR HARDWARE

DIVISION 09 – FINISHES

092116 GYPSUM BOARD ASSEMBLIES

096500 RESILIENT FLOORING

099000 PAINTING AND COATING

DIVISION 22 – PLUMBING

226413 PROPANE GAS SYSTEM

DIVISION 23 – HEATING VENTILATING AND AIR CONDITIONING

230501 MECHANICAL GENERAL PROVISIONS

230519 METERS, GAUGES AND THERMOMETERS

230523 VALVES

230529 SUPPORTS, HANGERS, ANCHORS AND SLEEVES

230548 VIBRATION ISOLATION AND SEISMIC RESTRAINTS

230553 SYSTEMS IDENTIFICATION

230593 MECHANICAL SYSTEMS BALANCING

230700 INSULATION

230800 COMMISSIONING OF HVAC

230801 GENERAL MECHANICAL STARTING AND TESTING REQUIREMENTS

230811 MECHANICAL EQUIPMENT – EQUIPMENT STARTING AND TESTING

230900 HVAC CONTROLS

230993 AUTOMATIC CONTROL SEQUENCES

232101 HYDRONIC SYSTEMS SPECIALTIES

232113 PIPING AND ACCESSORIES

232123 PUMPS

233100 DUCTWORK

233313 DAMPERS

233400 FANS

233700 AIR OUTLETS AND INLETS

234000 AIR FILTERS AND CLEANERS

237313 FACTORY ASSEMBLED AIR HANDLING UNITS

238200 SPACE TERMINAL HEATING UNITS

238216 HYDRONIC COOLING AND HEATING COILS

238249 RADIANT THERMAL FLOOR

SEKI 157075 TABLE OF CONTENTS PAGE 3

DIVISION 26 – ELECTRICAL

260501 ELECTRICAL GENERAL PROVISIONS

260502 EQUIPMENT CONNECTIONS AND COORDINATION

260519 600V WIRE AND CABLE

260533 RACEWAYS AND BOXES

262416 PANELBOARDS

262726 WIRING DEVICES

262816 DISCONNECT SWITCHES AND INDIVIDUAL MOTOR CONTROLLERS

265100 INTERIOR LIGHTING

SEKI-157075 011100 - 1

SUMMARY OF WORK

SECTION 011100 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Work Restrictions.

9. Special Construction Requirements.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Lodgepole Visitors Center, accessed through the Ash Mountain Entrance on

Highway 198 in the southwest corner of the park northeast of Three Rivers Community.

B. The Work consists of the following:

Rehabilitation and replacement of critical components of the mission 66 Lodgepole Visitor Center and Park administrative facility located in the Lodgepole developed area of Sequoia National Park.

This project will address critical component replacement and needed rehabilitation of the facility’s heating and cooling mechanical systems (HVAC). Existing fin tube heating equipment located in the administrative offices will be replaced with hydronic panel style radiant heaters. Existing heating and ventilating equipment and ductwork supplying the exhibits area, lobby, and auditorium will be removed/altered to provide ventilation only with new dedicated outdoor air system (DOA) equipment. DOAS to operate only during occupied hours. These spaces will be heated with new hydronic radiant floor systems controlled by zone programmable thermostats. New underfloor insulation will be installed at all wood-framed floor locations. The comfort stations will be heated by ceiling-mounted hydronic panel style radiant heaters with external thermostats and new mechanical ventilation. All hydronic systems will be heated by the existing propane-fired condensing boiler. The existing propane vaporizer will be removed. Existing ceiling grilles and louvers will be retained along with new soffit and wall mounted louvers serving the DOAS exhaust. In conjunction with the HVAC modifications, the existing boiler room east wall and ceiling will receive a one-hour fire resistant assembly. All main electrical panels will be replaced including electrical feeders to subpanels. Bid options will consist of relocation of information technology equipment located in the Boiler Room to the Radio Room, installation of occupancy sensors for Administrative Zone lighting fixtures, and replacement of lamps/lenses in lighting fixtures at the Administrative Zone with new LED lamps/lenses.

C. Project will be constructed under a single prime contract.

SEKI-157075 011100 - 2

1.3 WORK PHASES

A. The Visitor Center Building Work shall be conducted in 4 phases in the following order, with each phase substantially complete before beginning the next phase:

1. Phase 1: Demolition and construction scope of work on Gridline H between Gridlines 1 and 2.5. Work of this phase shall be substantially complete and ready for occupancy prior to start of subsequent phase.

2. Phase 2: Demolition and construction scope of work on Gridline A between Gridlines 1 and 3. Work of this phase shall be substantially complete and ready for occupancy prior to start of subsequent phase.

3. Phase 3: Demolition and construction scope of work for portion of building not covered in Phase 1 or Phase 2.

4. Phase 4: Start up and commissioning of entire HVAC system.

1.4 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to areas indicated on Drawings.

B. Storage of Materials: Confine storage of materials to areas indicated on Drawings.

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to

Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Construction Camp: Park housing and /or RV hookups may be available to during construction.

Establishment of a camp within the park will not be permitted.

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for

SEKI-157075 011100 - 3

vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

1.5 PUBLIC USE OF SITE

A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.

Building and Road closures will be permitted, when required, upon specific approval of

Contracting Officer.

1.6 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer.

b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.

c. Maintain a minimum building temperature of 68 degrees Fahrenheit (20 degrees

Celsius) for the entirety of construction activities.

d. Maintain adequate ventilation in the entire building for the entirety of construction activities.

1.7 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of

6 a.m. to 6 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: Not allowed without written approval of Contracting Officer.

2. Exhibit, Lobby and Auditorium Zones Work Hours: Work in these areas is only authorized when it is closed, 5 p.m. to 7 a.m.

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

SEKI-157075 011100 - 4

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than three (3) days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.

1.8 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Sequencing Plan: Provide a detailed project sequencing plan in addition to the construction schedule required in Section 013216 Construction Schedule to be updated at weekly meetings with a minimum two week outlook. The project sequencing plan is to indicate the following:

1. Each Phase.

2. Start and completion dates.

3. Description of work each phase.

4. Any anticipated interruptions to power or data in the area of construction for each phase.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011100

SEKI-157075 012700 - 1

DEFINITION OF CONTRACT LINE ITEMS

SECTION 012700 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Line Item No.1: Base Bid: Mobilization/Demobilization

1. This item consists of furnishing all Labor and Materials for mobilization and demobilization.

2. Payment will be made at the contract lump sum price.

B. Line Item No.2: Base Bid: Administrative Zone Mechanical (Gridline H between Gridlines 1 and 2.5 and Gridline A between Gridlines 1 and 3.

1. This item consists of furnishing all Labor and Materials for installation of new wall mounted radiator heating system to include site work.

2. Payment will be made at the contract lump sum price.

C. Line Item No.3: Base Bid: Exhibits/Lobby/Auditorium/Comfort Station Zones Mechanical –

Heating (Gridline H between Gridlines 2.5 and 7 and Gridline A Gridlines 3 and 7)

1. This item consists of furnishing all Labor and Materials for installation of new heating system.

2. Payment will be made at the contract lump sum price.

D. Line Item No.4: Base Bid: Exhibits/Lobby/Auditorium Zones Mechanical – Ventilation

(Gridline H between Gridlines 2.5 and 6 and Gridline A Gridlines 3 and 6)

1. This item consists of furnishing all Labor and Materials for installation of new ventilation system.

2. Payment will be made at the contract lump sum price.

SEKI-157075 012700 - 2

E. Line Item No.5: Base Bid: Electrical Panel Replacement

1. This item consists of furnishing all Labor and Materials required to provide replacement of Electrical panels at the Lodgepole Visitors Center, including electrical feeders to all subpanels.

2. Payment will be made at the contract lump sum price.

F. Line Item No.6: Base Bid: Demolition

1. This item consists of furnishing all Labor and Materials for demolition of existing HVAC system.

2. Payment will be made at the contract lump sum price.

G. Line Item No.7: Bid Option A - IT Relocation

1. This item consists of furnishing all Labor and Materials required to provide relocation of information technology (IT) equipment from Boiler Room 107A to Radio Room 110.

Scope of work under this line item includes, but is not limited to; removal of all IT equipment not indicated to remain on the drawings, relocation of all IT equipment to

Radio Room 110 on a government furnished IT rack, installation of two (2) new Allen

Tel Products Inc. 48-port CAT 5E patch panels with wall mount in Boiler Room 107A and Radio Room 110, installation of a watertight lockable enclosure approved by CO in

Boiler Room 107A that will house two (2) 48-port CAT 5E patch panels, installation of one (1) 20 amp quadruplex receptacle in Radio Room 110 as shown on the drawings, extension of one (1) 25 pair telephone cable located in Mechanical 107 to Radio Room

110, furnish and installation of new louvered door for Radio Room 110, installation of necessary CAT 5E IT cable for connection between 48-port CAT 5E patch panels in

Boiler Room 107A and Radio Room 110 and new IT ground connection. All IT and telephone cable is to be routed in conduit. Prior to commencing work for this line item the contractor shall submit for approval an IT relocation plan. Coordinate relocation scope of work with CO.

2. Payment will be made at the contract lump sum price.

H. Line Item No.8: Bid Option B - Occupancy Sensors

1. This item consists of furnishing all Labor and Materials required to provide Occupancy

Sensors as specified in Section 262726 – Wiring Devices.

2. Payment will be made at the contract lump sum price.

I. Line Item No.9: Bid Option C - 4 ' LED Lamps and Prismatic Lens at Administrative Zone

1. This item consists of furnishing all Labor and Materials required to provide new LED

Lamps and prismatic lens in existing fixtures as indicated on the drawings and specified in Section 265100 “Lighting,” including new LED Drivers and electrical connections.

3. Payment will be made at the contract lump sum price.

SEKI-157075 012700 - 3

J. Line Item No.10: Bid Option D - 2' LED Lamps and Prismatic Lens at Administrative Zone

1. This item consists of furnishing all Labor and Materials required to provide new LED

Lamps and prismatic lens in existing fixtures as indicated on the drawings and specified in Section 265100 “Lighting,” including new LED Drivers and electrical connections.

END OF SECTION 012700

SEKI-157075 013100 - 1

PROJECT MANAGEMENT AND COORDINATION

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Construction Coordination.

2. Coordination Drawings.

3. Requests for Information (RFIs).

4. NPS/DSC Share-File System.

5. Project meetings.

6. Environmental Coordination.

B. Related Requirements:

1. Section 013216 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 017340 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 017700 “Closeout Procedures” for coordinating closeout of the Contract.

1.2 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

SEKI-157075 013100 - 2

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Pre-installation conferences.

7. Project closeout activities.

8. Commissioning activities.

1.3 SUBMITTALS

A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

8. Quality Control Plan.

1.4 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI.

1. CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

9. Requested date for response.

SEKI-157075 013100 - 3

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.5 NPS SHARE-FILE SYSTEM

A. Use the NPS File-Share System for transmitting all submittals digitally (exception to samples).

The NPS share-file System works similar to email, but can transmit large files. Subject line in each for each transmittal will include project name, transmittal number, and brief description of transmitted data such as: Submittal, RFI, RPP, etc. Submit a list of all employees who will need access to the NPS Share-file System to the Contracting Officer.

1.6 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Jobsite Safety.

4. Resolution of comments on required Division 01 documents.

5. Coordination of Subcontractors.

6. Labor law application.

7. Modifications.

8. Payments to Contractor.

9. Payroll reports.

SEKI-157075 013100 - 4

10. Contract time.

11. Contractor Performance Evaluation.

12. Display of Hotline posters.

13. Notice to proceed.

14. Correspondence procedures.

15. Acceptance/rejection of work.

16. Progress meetings.

17. Submittal procedures.

18. NPS Final Accessibility Inspection.

19. Environmental requirements.

20. As-constructed drawings/operation and maintenance (O&M) manuals.

21. Saturday, Sunday, holiday and night work.

22. Reference materials.

23. Value engineering.

B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.

All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections,

h. Construction Schedule update (provide updated CPM).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

SEKI-157075 013100 - 5

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Review of mockups.

i. Possible conflicts.

j. Compatibility requirements.

k. Time schedules.

l. Weather limitations.

m. Manufacturer's written instructions.

n. Warranty requirements.

o. Compatibility of materials.

p. Acceptability of substrates.

q. Temporary facilities and controls.

r. Space and access limitations.

s. Regulations of authorities having jurisdiction.

t. Testing and inspecting requirements.

u. Installation procedures.

v. Coordination with other work.

w. Required performance results.

x. Protection of adjacent work.

y. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

1.7 ENVIRONMENTAL COORDINATION

A. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements.

2. Regulatory Requirements.

3. Indoor Air Quality (IAQ) Management.

4. Noise & Acoustics Management.

5. Construction Waste Management.

SEKI-157075 013100 - 6

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 013100

SEKI-157075 013216 - 1

CONSTRUCTION SCHEDULE

SECTION 013216 – CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section consists of Construction Schedule requirements including but not limited to the following:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.

C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Float: The measure of leeway in starting and completing an activity.

1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.

SEKI-157075 013216 - 2

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.

G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.3 SUBMITTALS

A. Electronic Copies: All schedules and reports submitted shall be posted on the NPS Share-File System, provided in the native electronic file format. It is the intent of the Government to limit the number of printed reports to only those reports determined by the project team to be essential.

B. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.

C. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit (2) two paper copies of baseline schedule, large enough to show entire schedule for entire construction period.

D. CPM Reports: Concurrent with CPM schedule, submit (2) two paper copies of each of the following computer-generated reports. Format for each activity in reports shall contain activity number, activity description, resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of predecessor and successor tasks for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.

3. Total Float Report: List of all activities sorted in ascending order of total float.

E. Construction Schedule Updates: On or before the 7th day preceding the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data. Provide two paper copies.

F. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision submit (2) two paper copies of a Time Impact Analysis. Each Time Impact Analysis shall include a Fragmentary Network (Fragnet), incorporated into the currently accepted Construction Schedule, demonstrating how the Contractor proposes to incorporate a modification, change, delay, or Contractor request.

SEKI-157075 013216 - 3

1.4 QUALITY ASSURANCE

A. The Contractor shall meet with the Contracting Officer on the day of the preconstruction conference to go over the following:

1. Review software limitations, content and format for reports.

2. Verify availability of qualified personnel needed to develop and update schedule.

3. Discuss constraints, including phasing area separations interim milestones and partial

Government occupancy.

4. Review delivery dates for Government-furnished products.

5. Review schedule for work of separate Government contracts.

6. Review time required for review of submittals and re-submittals.

7. Review requirements for tests and inspections by independent testing and inspecting agencies.

8. Review time required for completion and startup procedures.

9. Review and finalize list of construction activities to be included in schedule.

10. Review baseline schedule comments, resolve issues and progress on incorporating them

11. Review procedures for updating schedule.

12. Discuss reporting requirements and establish a protocol for naming and transmitting electronic schedules.

B. Contractor's Schedule Representative: Before or at the preconstruction conference, designate an authorized representative to be responsible for the preparation and maintenance of the Construction Schedule. A resume outlining the qualifications of the Scheduler shall be submitted to the Contracting Officer for acceptance. The Scheduler shall have prepared and maintained at least 5 previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency in the use of scheduling software. The authorized representative will be responsible for preparing the Baseline Schedule, all required updates, revisions, Time Impact Analyses, and preparation of reports.

1.5 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.

B. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. In developing the Construction Baseline Schedule, ensure that the Subcontractor’s work at all tiers, as well as the prime Contractor’s work, is included and coordinated.

2. Secure time commitments for performing critical elements of the Work from parties involved.

3. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

SEKI-157075 013216 - 4

PART 2 - PRODUCTS

2.1 SCHEDULE OF VALUES

A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item. Schedule of values is to agree with the Contractor submitted contract price schedule.

B. Do not break down unit price items. Use only the contract price for unit price items.

C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.

D. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer before the first progress payment is processed.

2.2 CONSTRUCTION SCHEDULE REQUIREMENTS

A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, resource-loaded, time-scaled CPM network analysis diagram for the Work.

1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than (Thirty) 30 days after date established for the Notice of Award.

a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of Governments acceptance of the schedule.

2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.

B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the preliminary CPM network diagram, prepare a skeleton network to identify probable critical paths.

1. Activities: Indicate the estimated duration, sequence requirements, and relationship of each activity in relation to other activities.

2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.

SEKI-157075 013216 - 5

3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.

4. The Construction Baseline Schedule as developed shall show the sequence and interdependence of activities required for complete performance of the work. Ensure all work sequences are logical and the Construction Baseline Schedule shows a coordinated plan of the work.

5. Resource loading of each activity shall include all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown.

6. Consider seasonal weather conditions in planning and scheduling all work influenced by high and low ambient temperatures, wind, or precipitation to ensure completion of all work within the contract time.

7. Time Frame: Proposed duration assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity.

a. An early finish date may be shown but the late finish date must be the same date as the last day of the contract period. An early completion schedule must contain the following:

1) Insert an activity titled “Project Float” as a successor to the last activity in the early project completion schedule network.

2) Add a milestone titled “Contract End Date” as a successor to the activity “Project Float”.

3) Add duration to the activity “Project Float” as required so the milestone “Contract End Date” equals the last day of the Contract Period.

b. Contract completion date shall not be changed by submission of a schedule that shows an early completion date.

c. The Contractor shall limit use of lead or lag duration’s between schedule activities.

d. Project Calendars: Develop and incorporate the following calendars:

1) Administrative Calendar: Include a calendar that is based on a 7 day week to be used on any activities that are based on calendar days. Apply this calendar to administrative tasks or any other tasks that are not affected by non-working days (Federal Holidays, weather, etc.).

2) Project Calendar: Include a calendar that is based on the planned work week for the project. Include Federal Holidays, weekends, and any other non-work days indicated in the contract documents. Apply this calendar to activities which are not anticipated to be affected by weather.

3) Weather Calendar: Utilize the Project Calendar and show anticipated normal downtime related to weather as non-working time. Weather days shall be based on data for the local area from a reliable source like the National Oceanic and Atmospheric Administration (NOAA), National Park Service records, or source acceptable to the Contracting Officer. Apply this calendar to activities that are anticipated to be affected by weather.

e. Activity Duration: Define activities so no activity is longer than (15) fifteen days, except for non-construction activities including mobilization, shop drawings and submittals, fabrication and delivery of materials and equipment.

SEKI-157075 013216 - 6

f. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 calendar days, as separate activities in the schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.

1) Insulated Panels.

2) Aluminum Windows.

3) Heat Pumps.

g. Submittal Review Time: Include review and re-submittal times indicated.

Coordinate submittal review times in Construction Baseline Schedule.

h. Startup and Testing Time: Include not less than (3) three days for startup and testing and commissioning activities.

i. Substantial Completion: Allow time for Government administrative procedures necessary for certification of Substantial Completion. (For more information, refer to Division 01 Specification 01 77 00 Closeout Procedures.)

8. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.

a. Phasing: Arrange list of activities on schedule by phase.

b. Work under More Than One Contract: Include a separate activity for each contract.

c. Work Restrictions: Show the effect of the following items on the schedule:

1) Coordination with existing construction.

2) Limitations of continued occupancies.

3) Uninterruptible services.

4) Partial occupancy before Substantial Completion.

5) Use of premises restrictions.

6) Provisions for future construction.

7) Seasonal variations.

8) Environmental control.

d. Work Stages: Indicate important stages of construction for each major portion of the Work.

1) Subcontract awards.

2) Submittals.

3) Purchases.

4) Mockups.

5) Fabrication.

6) Sample testing.

7) Deliveries.

8) Installation.

9) Tests and inspections.

10) Adjusting.

11) Curing.

12) Building flush-out.

13) Building commissioning activities.

SEKI-157075 013216 - 7

9. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and the following interim milestones:

a. Down time for Electrical Power conversion from single to triple phase.

C. Joint Review, Revision, and Acceptance:

1. Within seven calendar days of receipt of the Contractor's proposed Construction Baseline Schedule, the Contracting Officer and Contractor shall meet for joint review, correction, or adjustment of the initial Construction Baseline Schedule. Any areas which, in the opinion of the Contracting Officer, conflict with timely completion of the project shall be subject to revision by the Contractor.

2. Within seven calendar days after the joint review between the Contractor and Contracting Officer, the Contractor shall revise and resubmit the Construction Baseline Schedule in accordance with agreements reached during the joint review.

3. In the event the Contractor fails to define any element of work, activity, or logic, and the Contracting Officer review does not detect this omission or error, such omission or error, when discovered by the Contractor or Contracting Officer, shall be corrected by the Contractor within seven calendar days and shall not affect the contract period.

4. Upon acceptance of the Construction Baseline Schedule by the Contracting Officer, save the schedule as a baseline and update on a monthly basis. The construction schedule update will be used to evaluate the Contractor's monthly applications for payment based upon information developed at the monthly Construction Schedule update meeting.

D. Recovery Schedule: When periodic schedule update indicates the Work is (14) fourteen or more calendar days behind the current accepted schedule, a separate recovery schedule indicating means by which Contractor intends to regain compliance with the schedule must also be submitted. Indicate changes to working hours, working days, crew sizes, and equipment required to achieve compliance, and date by which recovery will be accomplished.

E. Computer Software: Prepare schedules using a program that has been developed specifically to manage construction schedules.

1. Use Microsoft Project, operating system.

PART 3 - EXECUTION

3.1 CONSTRUCTION SCHEDULE UPDATES

A. Progress Meeting Updates: Provide updated schedule information before each weekly progress meeting.

1. Issue updated schedule concurrently with the report of each such meeting. Incorporate construction progress into the currently accepted schedule in a timely manner.

B. Monthly Schedule Updates:

SEKI-157075 013216 - 8

1. General: Update the Construction Schedule on a monthly basis to reflect actual construction progress and activities throughout the entire contract period and until project substantial completion. The status date of each schedule update shall be the 7th day preceding the progress payment request date.

2. Procedure: The Contractor shall meet with the Contracting Officer each month at a Construction Schedule update meeting to review actual progress made through the status date of the Construction Schedule update, including dates activities were started and/or completed and the percentage of work completed on each activity started and/or completed.

3. Reports: Concurrent with making revisions to schedule, prepare tabulated reports showing the following:

a. Identification of activities that have changed.

b. Changes in early and late start dates.

c. Changes in early and late finish dates.

d. Changes in activity durations in workdays.

e. Changes in the critical path.

f. Changes in total float or slack time.

g. Changes in the Contract Time.

4. Narrative: The report shall include a brief description of the actual progress made during the update period; actual and potential delaying activities; any impediments to progress;

issues related to inclement weather; progress toward established milestones and project float. The report shall include a brief description of the work anticipated to be performed in the next month. Any minor revisions to the schedule should be identified so they can be evaluated and accepted or rejected.

5. As the Work progresses, indicate Actual Completion percentage for each activity.

6. If the schedule update shows a late finish date after the contract completion date, at a minimum, include the following in the narrative with your submission:

a. Any known delays.

b. Actions that will be taken to get back on schedule.

c. Pending modifications.

d. Impediments or constraints affecting progress.

7. Progress Payments: The monthly updating of the currently accepted Construction Schedule shall be an integral part of the process upon which progress payments will be made under this contract. If the Contractor fails to provide schedule updates or revisions, then a portion of the monthly payment may be retained until such corrections have been made.

C. Distribution: Distribute copies of accepted schedule to Contracting Officer, Contracting Officers Representative, Construction Management Representative, Subcontractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.

1. Post copies in Project meeting rooms and temporary field offices.

2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.

SEKI-157075 013216 - 9

D. Construction Schedule Revisions:

1. Required Revisions: If, as a result of the monthly schedule update, it appears the currently accepted Construction Schedule no longer represents the actual prosecution and progress of the work, the Contracting Officer will request, and the Contractor shall submit, a revision to the Construction Schedule. The Contractor may also request reasonable revisions to the currently accepted Construction Schedule in the event the Contractor's planning for the work is revised. If the Contractor desires to make changes, the Contractor shall notify the Contracting Officer in writing, stating the reason for the proposed revision. Accepted revisions will be incorporated into the currently accepted Construction Schedule for the next monthly schedule update.

2. Procedure: If revision to the currently accepted Construction Schedule is contemplated, the Contractor or Contracting Officer shall so advise the other in writing at least seven calendar days prior to the next monthly schedule update meeting, describing the revision and reasons for the revision. Government-requested revisions will be presented in writing to the Contractor, who shall respond in writing within seven calendar days.

3. Reports: Concurrent with making revisions to schedule, prepare tabulated reports showing the following:

a. Identification of activities that have changed.

b. Changes in early and late start dates.

c. Changes in early and late finish dates.

d. Changes in activity durations in workdays.

e. Changes in the critical path.

f. Changes in total float or slack time.

3.2 TIME IMPACT ANALYSIS FOR CONTRACT MODIFICATIONS CHANGES DELAYS

AND CONTRACTOR REQUESTS:

1. Requirements: When contract modifications or changes are initiated, delays are experienced, or the Contractor desires to revise the currently accepted Construction Schedule, the Contractor shall submit to the Contracting Officer a written time impact analysis illustrating the influence of each modification, change, delay, or Contractor request on the contract time.

2. Time Extensions: Activity delays, which result in projecting a late completion date, shall not automatically mean that an extension of the contract time is warranted or due the Contractor. It is possible that a modification, change, or delay will not affect existing critical path activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of the available total float that may exist within an activity chain of the Schedule, thereby not causing any effect on the contract time. Time extensions will be granted in accordance with the terms of the contract.

3. Extension of the contract time will be granted only to the extent the equitable time adjustments to the activity or activities affected by the modification, change, or delay exceeds the total (positive or zero) float available on a particular…