AMEND 003 EXT.pdf
PDF 234 KB Posted
- Attached to
- CARPET REPLACEMENT Federal contract opportunity
- Solicitation number
- N6945021Q0025
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 20259757_Replace Flooring in Building 2527_Rev.pdf | ||
| Amend 0004.pdf | ||
| Receipt_2021-07-30_120221.pdf | ||
| Pic 1.pdf | ||
| Pic 2.pdf | ||
| N6945021Q0025 PPI Responses.pdf.”.pdf | ||
| Amend 003.pdf | ||
| P427 PRODUCT DATA.pdf | ||
| Amend 0002.pdf | ||
| Amend 0001.pdf | ||
| WAGE RATES.pdf | ||
| Attachment 3 - LAYDOWN SOP CHECKLIST.pdf | ||
| N6945021Q0025.pdf | ||
| 20259757_Replace Flooring in Building 2527.pdf | ||
| Attachment 2 - DIG PERMIT PROCESS.pdf | ||
| Encl 7 - PPI Log.xlsx | XLSX spreadsheet | |
| Attachment 5 - B2527 Flooring Drawings.pdf | ||
| Attachment 4 - NAVFAC eCMS Access (copy).pdf | ||
| Attachment 1 - Project location and Site Photos.pdf |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work - Construction - 3 - 24 and
Wilsonart no longer makes the flooring specified to be matched. It is unlikely that an identical match will be found. Should a similar 24" x 24" tile be considered for this project?
Does the customer have a manufacturer and color in mind?
See response above.
13 N/A Can the government provide a list of attendees for the site visit?
Yes
14 N/A Can an additional visit be scheduled to revalidate existing materials?
No
15 Scope of Work / BLDG 2527 / Construction /
Please specify what type of flooring the customer would prefer to have installed where the floor transistions from raised access flooring to concrete.
Vinyl strip per manufacturer recommendations.
16 Scope of Work / BLDG 2527 / General Notes / #1
Will the work be allowed to take place over the entire site at one time or will the contractor have to perform work in phases? If phasing is preferred, would it be acceptable to phase the work as follows:
Phase 1 – 1st and 2nd floor (East side of Bldg) Phase 2 – 1st and 2nd floor (West side of Bldg)
Sequencing shall be coordinated with the building end user at time of mobilization/construction.
Contractor preferred sequence will be considered, if it does not impact building operations.
17 BLDG 2527 / Attachment 5 / Flooring Drawings / Sheet AF102B
During the site visit, it was discussed that the Informal Gathering Area 1236 may be omitted from the Scope of Work. Please confirm if the contractor should include the cost for work in the area/room.
Include this work per the RFP documents.
18 Scope of Work / BLDG 2527 / General Notes / #2
Per the scope of work, the customer will provide escorts to accopmany the contractor during construction activiites. Please confirm if the contractor be allowed to have multiple escorts during construction so that work can take place in multiple areas? By doing so, this will allow workers to access the laydown areas, restrooms, etc. without stopping production each time a worker has to leave the work area.
Escorts (line of sight) will be required at all times and can be coordinated as proposed in the contractor plan.
19 BLDG 2527 / Attachment 3 / Laydown
Per Attachment 3, the customer has highlighted the laydown area to be utilitezed for this project. Will the customer allow the contractor to utilize the areas under Stairwell # 1 or Stairwell #2 for certain materials to acclimate on site or will the contractor be required to provide a climate controlled storage area onsite?
A climate controlled area for material relaxation can be provided in the facility.