17-T-0071_RFQ_Amendment.docx

DOCX document 35 KB Posted

Attached to
Window Pressure Vessel Federal contract opportunity
Solicitation number
N6893617T0071
Issued by
Department of the Navy Naval Air Systems Command Naval Air Warfare Center

About this file

17-T-0071 RFQ Amendment

View the file

Other files for this federal contract opportunity

Other files attached to Window Pressure Vessel, newest first.
File Type Posted
17-T-0071_RFQ_Amendment_2.docx DOCX document
17-T-0071_RFQ_Solicitation.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N68936-17-T-0071

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The following have been modified:

FOR YOUR INFORMATION:

The following addresses and points of contact are provided:

Name: Susan Wigfield Phone: (760) 939-4134 Email address: susan.wigfield@navy.mil

U.S. Postal Service Mailing Address:

COMMANDER
CODE 254620D (S. Wigfield – 760-939-4134)
NAVAIRWARCENWPNDIV
429 E. BOWEN RD. MAIL STOP 4015
CHINA LAKE, CA 93555-6108

Direct Delivery Address (UPS, FedEx, etc.):

COMMANDER
CODE 254620D (S. Wigfield)
NAVAIRWARCENWPNDIV
BLDG 982, MAIL STOP 4015
CHINA LAKE, CA 93555-6108

Below are questions regarding the window pressure vessel. The answers are below each question:

1). You want a total of four (4) thermocouples per optical bomb, do you want all four installed? It will require additional machining.

Only the wire feedthroughs are necessary (i.e. the fitting is present, but the actual thermocouples do not have to be installed). The thermocouples do not need to be installed.

2). I quoted RTD's, our's are designed to handle the higher pressures and used in our strand burner system. Would our RTD's be acceptable?

Yes, but we would like to know the specifications of the RTD to make sure they're compatible with our existing temperature controllers. Thermocouples are preferred.

3). If you want thermocouples which type?

K-type 4). The low pressure bomb you want two heads one with a window and one with the 1/2" dia. Hole?

The top portion where the top window is located should be removable. A second piece (or head as it's referred to above) should be able to quickly release pressure through a bursting disc or quick action valve.

5). The high pressure bomb do you still want the 5th window centered at the top of the radius of the head?

No 5th window is needed for the high pressure bomb 6). I yes do you want it also made of ZnSe also?

n/a

The use of metal to glass fused windows depends on a couple of criteria:

1. Window units must be replaceable without the use of specialized equipment

2. Windows must have the future option of being coated with anti-reflective coatings in the future.

3. The units should be able to be manufactured by multiple vendors for future replacements and modifications

1). Currently there is only one T/C port. Do you want an additional three T/C ports machined into the vessel?

One T/C will be sufficient if it can be removed to replace the temperature sensor barring damage during a test.

2). RTD's are 100 ohm.

That is fine.

3). Quick release valve or burst disc would be customer supplied.

That is fine.

Question: I want to verify that eliminating o-rings will not exclude our offer for these pressure vessels. The solicitation has line items for separate windows, window retainers, and o-rings. However, the windows we plan to include with the pressure vessel are a single fused piece and do not require any separate components for installation. I'd be happy to elaborate on any aspects of these windows or the assembled vessels. If the end user really wants 3-piece windows we can also provide that instead.

Answer: Eliminating o-rings will not necessarily exclude the offer from the possibility of being awarded, but it will depend on the vessel design, ability to use specialty coated windows as describe in the previous response.

(End of Summary of Changes) image1.wmf