Statement_of_Work.pdf

PDF 102 KB Posted

Attached to
Lever Arm Tester Federal contract opportunity
Solicitation number
N6588818RC00567
Issued by
Department of the Navy Naval Supply Systems Command

View the file

Other files for this federal contract opportunity

Other files attached to Lever Arm Tester, newest first.
File Type Posted
SOW_Revised.pdf PDF
Evaluation_Factors.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Procurement, Installation, and Training of Universal Load Test Frames

N6588818RC00567

1.0 SCOPE

1.1 Fleet Readiness Center South West (FRCSW) operates a fully functioning industrial electro-plating facility for the purpose of restoring dimensional and protective coatings to high-strength steel aircraft components. Necessary as a Quality Control (QC) measure is to ensure these processes do not cause hydrogen embrittlement. One method is to process representative coupons on a recurring schedule then physically test these coupons to determine whether any part of the process induces residual hydrogen thus embrittling the steel.

1.2 The Materials Engineering Laboratory (4.3.4) and the industrial facility (6.0) does not have the capability to perform hydrogen embrittlement testing in accordance with the methods described in the ASTM-F519 standard.

This Statement of Work describes the equipment necessary to establish the capability for FRCSW to conform to industry & Commander Fleet Readiness Center (COMFRC) process QC standards supporting hydrogen embrittlement testing.

1.3 In addition to Hydrogen Embrittlement testing, properly configured equipment will be utilized for Creep, Creep-

Rupture, and Stress-Rupture tests for monolithic, metallic materials, composite materials, and adhesive structural bond joints.

1.4 The Government requires four Universal Load Test Frames, (Systems), installation services, all associated equipment for the installation, testing/validation of the Systems and training services for FRCSW personnel to support the requirements described above.

Location:

Fleet Readiness Center Southwest (FRCSW)

Building 469 North, Room 241

NAS North Island P.O. Box 357058

San Diego, CA 92135-7058

2.0 APPLICABLE DOCUMENTS

2.1 ASTM E4-10, Standard Practice for Force Verification of Testing Machines.

2.2 ASTM E8-08, Standard Test Methods for Tension Testing of Metallic Materials.

2.3 ASTM E74-06, Standard Practice for Calibration of Force-Measuring Instruments for Verifying the Force

Indication of Testing Machines.

2.4 ASTM E139-11, Standard Test Methods for Conducting Creep, Creep-Rupture, and Stress-Rupture Tests of

Metallic Materials

2.5 ASTM E292, Standard Test Methods for Conducting Time-for-Rupture Notch Tension Tests of Materials

2.6 ASTM-F519, Standard Test Method for Mechanical Hydrogen Embrittlement Evaluation of Plating/Coating

Processes and Service Environments

2.7 ASTM D2294-96, Standard Test Method for Creep Properties of Adhesives in Shear by Tension Loading

(Metal-to-Metal)

2.8 ASTM D2295-96, Standard Test Method for Strength Properties of Adhesives in Shear by Tension Loading at

Elevated Temperatures (Metal-to-Metal)

2.9 ISO/IEC 17025, General Requirements for the Competence of Testing and Calibration

Laboratories.

2.10 SECNAV Form 5512/1 - DoN Local Population ID Card/Base Access Pass Registration

2.11 FRCSW 5512/5 - FRCSW Visitor Access Request Form

3.0 REQUIREMENTS

3.1 The vendor shall provide four each, vertical load frames capable of static load application compliant with referenced specifications listed in paragraphs 2.1 through 2.3 and capable of testing described in specifications listed in paragraphs 2.4 and 2.5 and Sustained Load Testing (SLT) described in the specification referenced in paragraph

2.6.

Additional requirements for specific capabilities, facility requirements, physical size limitation, accessories, and peripheral equipment are provided in the following paragraphs.

3.1.1 Maximum load frame dimensions shall not exceed 42”W x 21”D x 92”H (floor standing) or 62”H (tabletop).

3.1.2 Load frames shall be capable of 50kN (12,000lbf) axial force.

3.1.3 Electrical power requirement shall be 115 -120 VAC, 40 Amp maximum.

3.1.4 Load Frames shall be capable of repeated, sustained (up to 400 hrs) test loads of 90% design capacity without compromising repeatability, dependability, and durability.

3.1.5 Noise emission shall be less than 75dB during operations of 30 minutes or less and less than 68dB during operations greater than 30 minutes.

3.1.6 Minimally one of the four load frames shall incorporate the following features;

a. Automated, incremental load application compliant with the Incremental Step Loading (ISL) described in the specification referenced in paragraph 2.6.

b. Mechanical, electrical, and electronic adapters for furnace installation, control, and monitoring to enable testing per specifications listed in paragraphs 2.7 and 2.8. Configuration shall also provide for monitoring of specimen temperature at 4 separate surface locations, minimum.

3.1.7 Accessories for load frame described in 3.1.6:

a. Controller to control, monitor, and record load application and environmental temperature.

b. Portable user interface for system operation.

c. Furnace w/ integral, frame-specific design, capable of sustaining temperatures exceeding 2000 degrees F to enable testing described in the specification listed in paragraph 2.8.

3.1.8 Adapters: One complete adapter set shall be provided with each load frame. Adapter design shall facilitate load frame interface with ASTM F519 Type 1a.1 specimens/coupons.

3.2 TESTING & PERFORMANCE VERIFICATION:

Upon delivery and installation the vendor must perform Field Service System Startup Assistance for each of the load frames. A Field Service Engineer (FSE) will schedule a visit to set up each of the four load frames, ancillary devices & controllers as necessary to:

(1) Fully enable operation of the test equipment in accordance with ASTM F519 by responsible personnel.

(2) Verify/establish system repeatability and accuracy as defined in specifications identified in section 2.0.

Verification and calibration shall be compliant with the requirements of specifications listed in section 2.0 and a calibration report provided.

(3) The certificate of calibration must be in effect for a minimum of one calendar year.

3.3 ON-SITE TRAINING OF GOVERNMENT PERSONNEL:

The Government requires the contractor to provide comprehensive, on-site, one time training of designated FRCSW personnel (one to three individuals) to operate the equipment described in para 3.1 in a proficient manner with emphasis on ASTM F519 test protocols.

3.4 TECHNICAL SUPPORT:

During the warranty period, the Government requires that the contractor’s FSE or factory technical support personnel provide telephone support to FRCSW operators with basic inquiries regarding System operation and assistance in remediating basic hardware/software malfunctions. Support shall be rendered within 24-hours of notification by the Government via telephone at (619)545-8655, Monday-Thursday, 0800-1400 PST.

If, the issue(s) cannot be remedied after all remote support options are exhausted the contractor’s FSE shall provide on-site support within 14 calendar days.

3.5 DELIVERY LOCATION Upon contract award, the Contractor shall deliver the items as described in paragraph 3.1 to the address below.

Delivery and Installation Address:

Fleet Readiness Center South West (FRCSW)

Building 469N, Materials Engineering Laboratory

San Diego, CA 92135

Mark For:

Primary Designated Government Representative (DGR):

Manual Goulart, (619)545-8655

Alternate DGR: Michael Yawn, (619)545-9844

3.6 INSPECTION/ACCEPTANCE:

3.6.1 The Government will inspect all System components, peripherals, and accessories after installation and witness the functional testing conducted by the contractor’s FSE on each System. The contractor is required to furnish all applicable Certificate of Calibration/Conformance (COC) documents upon successful testing and calibration/calibration verification.

3.6.2 Upon successful testing of all Systems, the Government will accept the Systems and process documentation to facilitate invoice processing.

NOTE: In the event that the materials and services delivered under this order by the contractor do not meet all specifications and technical criteria established by the contract; both the contractor and FRCSW DGR are to contact the Fleet Logistics Center San Diego (FLCSD) Contracting Officer immediately.

3.6.3 FRCSW personnel are not authorized to extend the delivery and or period of performance, change pricing, terms or conditions or to allow the contractor to “fix” a problem. Changes to the contract shall be made by mutual agreement between the Government and Contractor via a formally issued SF-30 contract modification. If an issue arises during performance of the contract, the issue shall be elevated to the Contracting Officer for disposition.

3.6.4 The Contractor shall provide the DGR with a detailed Field Summary Report (FSR) identifying the date and time of arrival, date and time of completion, the work performed, and recommended maintenance to ensure optimal

System performance.

3.6.5 The Contractor is required to provide a one year warranty on all equipment/systems. Parts replaced under warranty shall remain defect free for a period of one year from the date of installation. Warranty parts requiring repair or replacement shall be at no additional cost to the Government for one year following completion of 3.2 above, and must include material, labor, travel, shipping and handling.

3.6.6 A Certificate of Completion (COC) shall function as the Government’s inspection and acceptance (I/A) document. Upon completion of services:

3.6.6.1 The Contractor shall provide the DGR with a COC.

3.6.6.2 The DGR shall review, sign, and provide a signed copy of the COC to the Contractor prior to departing NAS North Island.

3.7 BASE ACCESS

3.7.1 The Contractor shall provide the DGR with the full name (first, middle, and last), date of birth, place of birth, citizenship, and full Social Security Number of each person requiring base access in order to facilitate the vetting process required for base access at least ten business (10) days in advance of the scheduled site visit. Personal information is for the purpose of completing Dept. of the Navy Local Population ID Card/Base Access Pass

Registration SECNAV Form 5512/1 and FRCSW 5512/5; Fleet Readiness Center South West Visitor Access

Request, and Navy Region SW NCACS and Non-Affiliated Personnel Vetting Request forms. Complete forms must be forward by DGR to FRCSW Base Security, Code 7.4 Base Security.

3.7.2 Upon arrival, all personnel will be required to check-in at the Visitor Control Center (Building 680), which is located near the Main Gate to Naval Base Coronado (NBC), Naval Air Station North Island, San Diego, CA.

Following receipt of clearance personnel are required to coordinate with the DGR and obtain visitor badges through the FRCSW Quarterdeck, located in the lobby of Building 94.

3.8 INVOICING and PAYMENT

3.8.1 Invoices for services rendered under this contract shall be submitted electronically through Wide Area

Workflow (WAWF).

3.8.2 The Contractor shall be responsible for uploading a copy of the signed COC and FSR into WAWF as an attachment upon invoicing. Failure to include the document may result in the delay of invoice and payment processing.

3.8.3 Partial payments for material delivered or services rendered are not authorized.

3.9 CONTACTS

3.9.1 Designated Government Representative (DGR): Manuel Goulart, (619)545-8655, manuel.goulart@navy.mil

3.9.2 Technical Point of Contact (TPOC): Michael Yawn, (619)545-9488, michael.yawn@navy.mil mailto:manuel.goulart@navy.mil mailto:michael.yawn@navy.mil