N4008520R33330004 Amendment 3 35kV.pdf
PDF 124 KB Posted
- Attached to
- Replacement of 34. 5kV feeder underground electrical distribution system Federal contract opportunity
- Solicitation number
- N4008520R2104
About this file
This solicitation requests design-build services for the replacement of an underground 34.5kV electrical distribution system at Naval Station Great Lakes in Illinois. The scope of work includes designing and constructing a new 12.47kV underground electrical distribution system to feed Buildings 322, 325, 328, 329, 510 and 520. It will require installing feeder cable and connecting new pad-mounted transformers while demolishing existing 35kV building feeds to the maximum extent possible. All work must be completed within 365 calendar days of award. The solicitation was issued by the Naval Facilities Engineering Command under NAICS code 237130 with a size standard of $39.5M.
View the file
Other files for this federal contract opportunity
Show all 27
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to answ er additonal questions #58 thru #61, to the Pre-Proposal Inquiry (PPI's). No changes or alterations have been made to questions #1 thru #57.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 09-Jul-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008520R3333
X 9B. DATED (SEE ITEM 11)
21-May-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09-Jul-2020
CODE
NAVFAC MID ATLANTIC
PWD GREAT LAKES - FEAD
310 SEABEE WAY
GREAT LAKES IL 60088-2814
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008520R3333
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
The following have been modified:
PRE-PROPOSAL INQUIRY (PPI'S)
SOLICITATION # N4008520R2104
Replace 35kV North Branch Service, Naval Station Great Lakes, IL
Pre-Proposal Inquires (PPIs) FORM
Questio n No.
RFP Reference (Sect/Para/Page
QUESTION GOVERNMENT RESPONSE
1 RFP Section Factor 3 - Past Performance, Para. (a), We strive to reduce the onus on our Government clients who need to complete the same PPQs repeatedly for proposals. Also, contracting representatives are reluctant to (or even discouraged from) completing PPQ forms if formal performance CPARS evaluations have been completed. Will the Government please consider allowing offerors to submit completed CPARS evaluations or previously completed/signed PPQs in lieu of new PPQ forms?
Please refer to page 71 of the RFP. CPARS are preferred, previously completed PPQ's within the last 12 month will be accepted in lue of new PPQ forms.
2 RFP Section Factor 3 - Past Performance, Para. (a), Per FAR 52.229-3 Federal, State, and Local Taxes, please confirm offerors are to include all applicable Federal, State, and local taxes in their bid price.
Tax exempt letter can be provided post award, Contractor to verify applicability with vendors.
3 RFP Section Factor 5 - Technical Solution, Para.
(a), Page 15
Can the Government please confirm that the three (3) conceptual drawings are excluded from the 6-page (3 page double-sided, 6 page single-sided) limit for Factor 5 - Technical Solution?
Conceptual drawings are excluded from the page limitation of the narrative
4 RFP Section
10. Evaluation, para. (a), Please confirm that the form referred to in the RFP as "Proposal Cover Sheet (Attachment D)" is the same form as RFP filename "Proposal Cover Sheet ACQR 5753952".
Yes, It is the same.
5 RFP Section
10. Evaluation, para. (a), Please confirm that the form referred to in the RFP as "Line Item Pricing Worksheet (Attachment E)" is the same form as RFP filename "Line Item Pricing Sheet".
Yes, It is the same.
6 RFP
Amendment
Amendment 0001 was issued Friday, June 5th, 2020.
The contents of Amendment 0001 were similar to the RFP filename "N4008520R3333 Solicitation 35kv", with exception to the addition of the 8(a) set-aside language on the 1st page of SF 1442. Will the Government please specify any other changes in Amendment 0001, and if the Government intends on issuing an SF30 for offerors to appropriately awknowledge this amendment?
Offerors do not need to provided acknowledgement with their proposal, as it only added a sentence to clarify 8(a) set-aside.
7 RFP
Amendment
If the Government does not intend on issuing an SF30 for Amendment 0001, which SF 1442 should offerors use in the proposal, the SF 1442 from the original solicitation issued May 27th, 2020, or the SF 1442 from the Amendment 0001 solicitation issued June 5th, 2020?
Either SF 1442 will be accepted. Both do not need to be submitted.
8 RFP Proposal Cover Sheet and SF 1442, Box 13(D)
RFP filename "Proposal Cover Sheet ACQR 5753952" states that offerors proposal must be valid for 120 days from submission. In contrast, Box 13(D) of the SF 1442 notes a minimum acceptance period of 90 calendar days after the date offers are due. Will the Government please clarify if the minimum acceptance period is 90 or 120 calendar days from the date offers are due?
Acceptance period of 90 days after date offers are due is applicable, as stated on the SF 1442
9 RFP Section Factor 2 - Experience, para. (1) & (2), Page 7 & 8
Please confirm that the mandatory form required for Factor 2 - Experience, referred to in the RFP instructions as "Attachment A – Experience Data Sheet", is the same form as RFP filename "Experience Form".
Yes, It is the same.
10 RFP Section Factor 3 - Past Performance, para. 2, Page
Please confirm that the form referred to in the RFP as "Past Performance Questionnaire (Attachment D)" is the same form as RFP filename "Past Performance Questionnaire".
Yes, It is the same.
11 RFP Section Factor 2 - Experience, The RFP states, "Provide applicable documentation on projects that were validated and/or certified through U.S. Green Building Council (USGBC) or the equivalent organization or process." Will the government allow offerors to include Appendices in order to provide additional documentation such as USGBC certification/validation documents?
Offerors can include Appendices to provide additional documentation such at USGBC certification/validation
12 RFP Section Factor 4 - Safety, para
(a) Note, page
The RFP states, "For a partnership or joint venture, the submittal requirements are required for each contractor who is part of the partnership or joint venture; however, only one safety narrative is required." Will the Government please confirm the understanding that designers, subcontractors and/or company affiliates are not considered a "partnership" under this factor, and thus are not required to provide EMR/DART/TRC rates?
Please refer to the note on page 73 of the RFP. All types of subcontractors are required to provide
EMR/DART/TRC rates.
13 RFP Section
9. Bonding, Can the Government please provide the address for offerors to use to deliver the big gaurantee?
Bid Guarantee should be submitted with the Proposal
14 RFP Section Factor 2 - Experience, para. (1) and (2), Page 7 and 8
In previous NAVFAC solicitations, NAVFAC has allowed projects that exceeds the size value to be submitted and considered as relevant, resulting in the best overall value to the Government and taxpayer. Please confirm that projects over $4M will be accepted?
Yes, Projects over $4M will be accepted.
15 SOW Section
1.0 Project
Description, para Utility Outages, page
The SOW states, "Extended outages may require temporary power.". What specific time parameters constitute an extended outage? If an extended outage requires temporary power, which building systems will require power?
I would consider an extended outage as an outage length that would impact other building systems and cause damage to the facility (i.e. no heat in winter, causing pipes to freeze) or an outage length that is unable to be scheduled around the normal building mission/occupancy.
16 SOW Section 33 71 02, para. 3.5.4 Jacking and Drilling Under Roads and Structures, Is directional boring acceptable? Will the use of HDPE duct for the raceway through the bored pathway be acceptable without the use of a steel casing?
No, conduits shall be installed in trench and concrete encased.
17 SOW Section 33 71 02, para. 3.5.4 Jacking and Drilling Under Roads and Structures, The SOW states, "Conduits to be installed under existing paved areas which are not to be disturbed, and under roads and railroad tracks, must be zinc coated, rigid steel, jacked into place." Will the Government please provide clarity as to which areas are considered "not to be disturbed" as it pertains to the scope of this project?
Areas not to be disturbed as it pertains to this project are roads and railways not owned by Navy or environmentally controlled areas. This should not be applicable to this project.
18 SOW Section 33 71 02, para. 3.14.1.1 b(2), Medium voltage cables, electrical tests, Contractor suggests that existing medium voltage cabling be hi-pot tested prior to splicing said cabling to new cabling. This will avoid splicing to a cable that may be on the verge of failure. Please confirm that if this situation arises a maintenance hi-pot test should be applied to the existing system cabling prior to splicing.
Splices are not allowed on the 12.47kV system. All 12.47kV cable junctions shall be made above grade in pad mounted sectionalizer pedestals. A maintenance hi‐pot test is not required prior to splicing to existing cable but is required after splicing to existing cable.
19 SOW Section 26 12 19.10, para. 3.5, Foundation for Equipment and Assemblies, Please confirm it is permissable to utilize existing concrete transformer pads as long as dimensions are appropriate for new transformer.
As long as existing concrete pads meet the size and structural requirements for new transformers, and are not showing signs of failure, they can be reused.
20 Part 4 Minimum materials, engineering, and construction requirements, G20 Site Improvements, In the interest of causing less disruption to Navy functions and to preserve existing hardscape, is it acceptable to utilize portions of existing medium voltage duct bank for new system cabling?
Existing medium voltage duct bank can be utilized for new system cabling. Emphasize that 12.47kV circuits are not allowed in manholes.
21 SOW Part 4 Minimum materials, engineering, and construction requirements, para. G40
1.3.6 Factory
testing, Page
"The government reserves the right to witness all factory testing." Please confirm travel costs for Government representatives for factory testing will be borne by the Government.
Correct, if Government chooses to witness factory testing, Government will pay for travel cost of Government employees.
22 SOW Part 3 Statement of Work, para.
Analysis and programming, Please confirm this analysis is for the entire mainside
34.5 kV and 12.47 kV systems as opposed to only the systems to be physically altered through this scope of work.
Correct, per the RFP analysis shall include all 34.5kV and 12.47kV circuits on mainside, whether altered under this contract or not.
23 SOW Section 33 71 02, para. 3.5.9.1, Connections to Existing Concrete Pads, Page
If applicable, please provide construction as-built drawings from the installation of applicable existing switches and transformers.
The existence of construction as‐built drawings for existing switches and transformers is unknown, assume they do not exist.
24 SOW Section 33 71 02, para.
3.14.1.2(b), Low voltage cable, 600 volts, Electrical tests, page
Will the Government please confirm if insulation resistance testing is required on existing secondary cables prior to connecting existing secondary cables to new transformers?
Yes insulation resistance testing is required for existing secondary cables prior to connection to new transformers.
25 SOW, Part 4, page 14, para G401006
Paragraph states splices are required. However, Part 3, SOW/Project Program, page 2, Demolition states:
Provide 34.5kv splices in manholes 1027, 1028, and 1034 to bypass unneeded cable for removal of building taps. Which is correct?
Splices are not allowed on the 12.47kV system. All 12.47kV cable junctions shall be made above grade in pad mounted sectionalizer pedestals. Part 3, Demolition requires 34.5kV splices to the existing cable to bypass building taps.
26 Solicitation,Off er, and Award Block 11.
Request 90 days be added to the performance period. With the two 21 day design approval periods (50% and 100% reviews) pluse required design time 365 days is not enough time to design, procure long lead items, then construct.
90 Days will be added.
27 SOW, Part 3, Page 2, Demolition
Paragraph states that existing 34.5kv cables in manholes 1027, 1028, and 1034 are to be spliced together after the switches are removed. Is the intent for the resulting M30-M40 tie to be an alternate subtransmission loop path? If so, the existing relays at M30 and M40 for that cable loop need to be replaced with line differential relays. This also involves SCADA work. Is the replacement of the existing overcurrent relays with line differential relays required?
Correct the intent is for the resulting M30‐M40 tie to be an emergency 34.5kV subtranmission loop. No the replacement of the overcurrent relays and associated
SCADA work is not part of this project.
28 SOW, Part 4, G20 Site
Improvements.
Our experience at Great Lakes is that all backfill in paved areas needs to be flowable fill. Is that still a requirement?
Regardless of fill type used it must be able to meet compaction requirements. Type of Fill also varies depending on means and methods employed.
29 SOW Part 3 SOW, Chapter 1.0, para Analysis and Programming, SOW page 24
Please clarify the requirement listed in RFP Part 3, 1.0, paragraph “Analysis and Programming” to provide a complete coordination analysis, short circuit analysis and load flow analysis of the 34.5 KV and 12.47 KV electrical distribution systems on Naval Station Great Lakes mainside." Is this analysis limited to the buildings included under the scope of the RFP? Or does this RFP include performing the short circuit analysis and load flow analysis for the complete existing 34.5 KV and
12.47 KV electrical distribution systems for the entire
mainside of Naval Station Great Lakes?
Per the RFP analysis shall include all 34.5kV and 12.47kV circuits on mainside, whether altered under this contract or not.
30 SOW Part 3 Statement of Work, para1.0 Building load analysis , page 23/185
Please confirm in case of building load analysis found unbalance of phase distribution, contractor need to revise and change/alter circuits feeding via panel through this scope of work. Does the contractor need to provide record drawings for these changes?
The intent of this contract is not to correct unbalanced building loads, but to appropriately size the new transformers to the actual building load.
31 General, scope Can the Government provide as builts for the buildings that the power feed serves along with any available as built drawings, utility maps, or existing conditions data for the surrounding area in which the feeder will be installed?
The availability of building as builts is unknown. Refer to RFP Part 6, Attachment G for utility maps and existing conditions.
32 General, RFP Based on the current COVID pandemic conditions and subsequent limitations on businesses for collaboration and coworking, will the Government extend the proposal due date by 3 weeks? This will allow offerors additional time to collaborate with teaming partners considering that most teams are working remotely which decreases efficiency on a collaborative proposal effort such as this.
Proposal Due has been extended until July 21st, 2020, no later than 4pm (CST)
33 Part 3 Statement of work, 1.0 Project Description, page 1 - Transformer Replacement
Please provide historical metering data for transformers serving buildings 322, 325, 328, 329, 510, 520 and
12.47 kV feeder circuits M41, M42, M31 and M32 if available.
See Excel files provided for facility metering data. No data is available for feeder circuits. 8 Files at Beta.Sam are labeled as B322, B325, B328, B329‐1, B329‐2, B510, B520‐1 and B520‐2
34 Part 3 Statement of work, 1.0 Project Description, page 1 - 12.47 kV Feeders
Please confirm that Substaton M40 and Substation M30 spare 12.47 kV feeder cubicles and overcurrent relays are fully functional and ready for service except for possible relay setting changes.
Correct M40 and M30 spare 12.47kV cubicles, breakers and relays are fully functional.
35 Part 3 Statement of work, 1.0 Project Description, page 1 - 12.47 kV Feeders
Please confirm that Substation M40 and Substation M30 spare 12.47 kV feeder cubicles have spare breakers which are fully functional and can be ustilized for new 12.47 kV feeders as needed for this project scope.
Correct M40 and M30 spare 12.47kV cubicles, breakers and relays are fully functional.
36 Are any existing environmental impact survey’s available for the areas where work is to be performed?
No
37 Please confirm that transformers have been drained of all fluids.
The transformer have not been drained.
38 Are there any existing tests or survey’s of the existing equipment for PCB oil, Asbestos, Lead or any other environmental hazards?
No
39 What are the lead time requirements for electrical shutdowns requests?
UEM requires 14 days notice for outage requests.
40 Are there specific Dates, Days of the week or times of day that must be avoided for electrical shutdowns for any location?
Unknown, outages will be coordinated with each group of facility occupants when requested.
41 Is there a maximum duration of electrical shut downs in any of the affected locations.
Shut downs must be scheduled with affected facilities as to not impact mission. If outages can not be scheduled without impacting mission, temporary utilities will need to be provided.
42 Are there any emergency generators that will remain in place and operational with the potential to backfeed while our work is being performed?
No
43 Are there any specific noise attenuation requirements for temporary generators in any of these locations or near any specific buildings.
Sound deflectors or other muffeling techniques may need to be employed depending on application and proximtity to occupied buildings.
44 Are there height restrictions for any areas being serviced. 17'6" (Access Gate Canopies).
45 Are there any weight restrictions for access roads All access to hospital Side(South of Sampson ST Bridge) must be coordinated with KO through Gate 3 for all
Heavy Trucks. Main Side.
46 Is Easypower modeling software acceptable? Great Lakes is attempting to standardize our electrical studies in SKM so that we will have a library of files to provide to future contractors as a starting point.
47 Is there an existing model that will be provided to contractors.
No
48 Can performance period be extended due to extensive design period?
90 Days will be added.
49 Can directional boring be used in lieu of duct banks. No, conduits shall be installed in trench and concrete encased.
50 Please confirm per section per G1010 & G1020 that there is not location on site for any demolished material & debris generated by this project.
Correct all debris shall be disposed of properly off‐site.
51 Please confirm per section per G1010 & G1020 that there is not a location on site for any excavated soil on site. If this needs to be removed, is there any requirements when this material leaves the project site.
There are no designated area on site to receive excess soil. Any soil that leaves Naval Station Great Lakes must be tested prior to removal from the site to determine it is not contaminated. Additionally soils must be managed in accordance with the approved NAVSTA Great Lake Soil Management Plan (see attached)
52 Are there any utility locating service providers on base. See RFP Part 2, 01 14 00.05 20 section 1.1
53 Are there any restricted areas that require an escort for badged contractors to perform work.
As seen during the walkthrough, electrical equipment is located in locked enclosures.
54 Are there any environmental permits that are required for the contractor to procure.
In accordance with the general terms and condition, the contractor is responsible for determinating and obtaining all regulatory permittng required (if any) for the project, however the Navy is unaware of any Illinois Environmental Protection Agency or United States Environmenatl Protetion Agency permits required to perform the scope of services as envisioned by the government.
55 Please confirm the list of demo materials to be removed from electrical equipment storage yard along Ziegemeier St.
is complete and any items in this lay down yard are to be left in place.
The list provided is complete
56 Does the government want any recycled material No ‐ all equipment and materials furnished under this contract shall be new
57 Can the bid date be extended due to the complexity of the project scope?
Proposal Due has been extended until July 21st, 2020, no later than 4pm (CST)
58 Are Item no. 0001 and 9000 meant to match/be the same number?
Similar, however, CLIN 9000 is an informational item only, referencing a pricing detail sheet summarized into the total of CLIN 0001. CLIN 0001 is a priced line item and represents the award amount for the project.
59 Which item no. is used in contract award? CLIN 0001 total represents the award amount for the contract
60 Are the prices in the line item extension sheet intended to be used solely in bid evaluation, or is it intended that these will be used in contract additions and deducts?
Contract modifications are negotiated at the time period in which it arise. The initial proposal may serve as a basis for fair and reasonable determination.
61 Can you confirm that we establish the quantities in the line item extension sheet based on our design
Yes, this is a design‐build project in which the contractor is responsible for the design to include quantities.
(End of Summary of Changes)