Errata_One.pdf

PDF 72 KB Posted

Attached to
USNS HUNTER (TSV 3) Federal contract opportunity
Solicitation number
N40027-17-R-0025
Issued by
Department of the Navy Naval Sea Systems Command

About this file

Errata One

View the file

Other files for this federal contract opportunity

Other files attached to USNS HUNTER (TSV 3), newest first.
File Type Posted
N40027-17-B-0002,_Amd_0002.pdf PDF
Addendum_One.pdf PDF
IFB_N4002717B0002_USNS_HUNTER.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

THIS PERMANENT CHANGE UPDATES THE SPECIFICATION BID PACKAGE.

SHIP: CARRIER STRIKE GROUP 4 (CNRMC 9577)

SERM-002-17

ERRATA NUMBER:

SPECIFICATION NUMBER:

One

THE FOLLOWING ITEMS ARE REPLACED:

261-11-001

DATED: Page 1 of 1

SHIP: CARRIER STRIKE GROUP 4 (CNRMC 9577) ITEM NO: 261-11-001

COAR: 26 PCN: NS02-L99K

CSWT FILE NO: 261-002 CMP: NONE

REVISED: 16 Dec 2015 PLANNER: KRIMMER, DAVID

DUBOIS, DANIEL

SSP: SERM-002-17 1 of 2 ITEM NO: 261-11-001 ERRATA NO. One

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Fuel System Piping; replace

1.2 Location of Work:

1.2.1 Forward Machinery Space, Flat, Frames 10-16, Centerline

1.2.2 Passage Way, Flat, Frames 16-58, Centerline

1.3 Identification:

1.3.1 Quantity (50 100 LF), Piping and Associated Fittings, 3/4 Inch IPS, Fuel Supply For Bow Thruster Engine (Caterpillar 3406), From and Including Valve at Frame 57 Up To and Including Valve at Frame 10

(E1)

1.3.2 Quantity (50 100 LF), Piping and Associated Fittings, 3/8 3/4 Inch IPS, Fuel Return From Bow Thruster Engine (Caterpillar 3406), From and Including Valve at Frame 57 Up To and Including Valve at Frame 10, To Include Check Valve (Item VC-3/8" of 2.2) at Frame 13

(E1)

1.3.3 Quantity (2 EA), Flexible Hose, 3/8 3/4 Inch, Length: 12 Inches, Mfr.: Aeroquip, Mfr. Part No.: 1509-6 With 4722-6-65 Fitting on Each End, Item No.: HA-3/8" HA-3/4" of 2.2

(E1)

2. REFERENCES:

2.1 Standard Items

2.2 180 X 38 X 13, Supply Vessel, Sheet P-12

2.3 S6430-AE-TED-010, Technical Directive Piping Devices, Flexible Hose Assemblies

2.4 S9086-RK-STM-010/CH-505, Piping Systems

3. REQUIREMENTS:

3.1 Remove existing and install new piping listed in 1.3.1 and 1.3.2 and located in 1.2.1 and 1.2.2, using 2.2 for guidance, as designated by the

SUPERVISOR.

3.1.1 Template exact size, configuration, and location from

existing shipboard conditions.

3.1.2 Accomplish the requirements of 009-12 of 2.1, including Table One, Column A, Lines One through 10.

3.1.3 Accomplish the requirements of 009-71 of 2.1 for the new and disturbed fuel oil service piping using clean, dry air or nitrogen at

50 PSIG.

3.2 Remove existing and install new each flexible hose assembly listed in 1.3.3 and located in 1.2.1, in accordance with 2.3, using 2.2 for guidance.

3.2.1 Reuse existing flexible hose end fittings where found

acceptable after inspection in accordance with Section 6, Paragraph

SHIP: CARRIER STRIKE GROUP 4 (CNRMC 9577)

SSP: SERM-002-17 2 of 2 ITEM NO: 261-11-001 ERRATA NO. One

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

6.2 of 2.3.

(V)(G) "HYDROSTATIC TEST"

3.2.2 Accomplish the requirements of Section 8 of 2.2 for each flexible hose assembly. Allowable leakage or deformation: None.

3.2.2.1 Accomplish the requirements of Paragraphs 505-11.1.3.2 through 505-11.1.3.4.2 of 2.4.

3.2.3 Flush and treat each flexible hose assembly following testing in accordance with Chapter 8, Paragraphs 8.3 and 8.4.

3.2.4 Fabricate and install (One EA) CRES identification tag on each new flexible hose assembly in accordance with Chapter 8, Paragraph

8.5 of 2.3.

3.2.5 Install each new flexible hose assembly in accordance with Chapter 9 of 2.3.

3.3 Accomplish the requirements of 009-107 of 2.1 for fuel oil service system piping, from each Fuel Oil Day Tank up to Flexible Hose Connection for each Main Propulsion Diesel Engine and each Ships Service Diesel Generator, using 2.2 as guidance.

3.3.1 Accomplish the requirements of 009-09 of 2.1 for cleaning, flushing and acceptance criteria of fuel service piping.

3.3.2 Ensure General Cleaning shall be Level II.

(V)(G) "OPERATIONAL TEST"

3.4 Accomplish an operational and tightness test of new and disturbed piping systems, and inspect for leaks, proper operation, and unobstructed flow. Allowable leakage: None.

3.5 Accomplish the requirements of 009-32 of 2.1 for the new and disturbed surfaces.

4. NOTES:

4.1 None.

5. GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

5.3 KITTED MATERIAL:

1. None.