About this file

Attachment 1 Statement of Work needed

View the file

Other files for this federal contract opportunity

Other files attached to Barge Engineering & Design, newest first.
File Type Posted
16-T-0174_Q_ _A's_4-28-16.docx DOCX document
16-T-0174_Q_ _A's.docx DOCX document
YC_1501_SOW_Revised_21_April_16.docx DOCX document
Barge_Engineering_ _Design_RFQ.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ N39040-16-T-0174

PROVIDE ENGINEERING AND DESIGN SERVICES (IN ACCORDANCE WITH THE BELOW STATEMENT OF WORK) TO PORTSMOUTH NAVAL SHIPYARD FOR THE DEVELOPMENT OF AN OVERHAUL PACKAGE FOR BARGE YC 1501. THE VESSEL IS LOCATED AT PORTSMOUTH NAVAL SHIPYARD, KITTERY, ME.

STATEMENT OF WORK

THE FOLLOWING IS A LIST OF TASKS THAT REQUIRE WORK ITEMS:

1. TOWING SERVICES

2. MAIN DECK/PRESERVE

3. HAZARDOUS WASTE

4. TEMPORARY SERVICES

5. DRYDOCK/FLEET/UNDOCK

6. CLEANING AND PUMPING

7. PRESERVE UNDERWATER HULL, FREEBOARD

8. UNDERWATER HULL, INSPECT/REPAIR

9. VOID, CLEAN, REPAIR, AND PRESERVE

10. PROVIDE HULL ZINC ANODE, REPLACE

11. MANHOLE COVERS, CLEAN AND PRESERVE

12. BULWARK, PRESERVE

13. EXISTING ELECTRICAL SYSTEM COMPONENTS, REMOVE

BASIC SCOPE OF SERVICES:

TASK 1: SHIPCHECK

CONDUCT A SHIPCHECK OF THE VESSEL AND GATHER INFORMATION FOR THE DEVELOPMENT OF THE OVERHAUL PACKAGE. THE INFORMATION GATHERED SHALL INCLUDE THE FOLLOWING:

1. PERFORM A VISUAL INSPECTION OF THE CRAFT WITH THE SUPERVISOR AND OR CRAFT REPRESENTATIVE. CHECK THE ENTIRE ACCESSIBLE HULL, DECK FITTINGS, DECK PLATING, RAILS, STANCHIONS AND LIFE LINES, FENDERS, DECK COATINGS INCLUDING EXISTING PRESERVATION SYSTEMS, LOOSE COATINGS, AND CONDITION OF DECK PLATING, CHOCKS, BITTS, CLEATS, FOUNDATIONS, BULWARK AND DECK PLATING. NOTE AREAS OFCORROSION, EROSION, EVIDENCE OF STRUCTURAL DEFECTS AND DAMAGE. OBTAIN “AS BUILT” AND OTHER REFERENCE DRAWINGS OR DOCUMENTS TO BE USED DURING PACKAGE DEVELOPMENT.

2. CONDUCT A MEETING WITH THE SUPERVISOR OR CRAFT REPRESENTATIVE TO COLLECT DATA AND OBTAIN INFORMATION FOR THE DEVELOPMENT OF TOWING, DRY DOCK, CLEANING AND BLASTING OF HULL, UT INSPECTION, TEMPORARY SERVICES, CLEANING AND PUMPING, CLEAN, PAINT AND PRESERVE AND ZINC REPLACEMENT WORK ITEMS. DISCUSS WITH CRAFT REPRESENTATIVE AMOUNTS OF FRONT LOADS FOR PLATING AND STIFFENER REPLACEMENTS TO PUT IN WORK ITEMS BASED ON HISTORICAL KNOWLEDGE. DETERMINE IF 3, 7 OR 12 YEAR SERVICE LIFE PAINT SYSTEM IS WHAT IS APPROPRIATE FOR UNDERWATER HULL.

TASK 2: DELIVERABLES

1. SHIPCHECK REPORT

2. WORK ITEMS, INCLUDES COST ESTIMATE

3. 2-KILO PACKAGE

4. GUIDANCE SHIPCHECK SKETCHES FOR WORK ITEMS