Attachment_1_-_SOW.pdf
PDF 2 MB Posted
- Attached to
- Construct Bouhadjra Health Post Federal contract opportunity
- Solicitation number
- N33191-14-R-0624
About this file
Attachment 1 - SOW
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_3_-_PPQ.pdf | ||
| N33191-14-R-0637_SOL.pdf | ||
| Attachment_5_-_APP_Template.pdf | ||
| Attachment_4_-_Submittal_Checklist.pdf | ||
| Attachment_2_-_Contract_Data_Sheet.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Prepared by: NAVFAC EURAFSWA HQ – CEBL Sonia Grillo
AFRICOM
Humanitarian Assistance Program
Bouhadjra Health Post Construction
Trarza, MAURITANIA
OHASIS MA-HA-2013-022987
FY14
March 2014
TECHNICAL REQUIREMENTS
Sean.Duffy Text Box Attachment 1 - Performance Technical Specifications (SOW)
Bouhadjra Health Post, MAURITANIA Attachment (1)
Table of Contents p. 2/81
TABLE OF CONTENTS
COVER PAGE
TABLE OF CONTENTS
LEGENDA: ACRONYMS AND DEFINITIONS
1 PROJECT DESCRIPTION
1.1 GENERAL 11
1.2 SCOPE OF PROJECT 11
1.3 SIGNAGE 12
1.4 STANDARD NOMENCLATURE 12
1.5 PROCEDURE 13
Concept Design Final design Construction Schedule Quality Control Plan Accident Prevention Plan [APP] Interim Submittal Requirements Completion Submittal Requirements
2 PROJECT OBJECTIVES
2.1 MISSION STATEMENT 15
2.2 FACILITY FUNCTION 15
2.3 PROJECT SPECIFIC PRIORITIES 15
2.4 APPROPRIATE DESIGN 15
2.5 WORKFLOW PROCESS - HOURS OF OPERATION 15
3 SITE ANALYSIS
3.1 EXISTING SITE CONDITIONS 16
3.2 SITE DEVELOPMENT REQUIREMENTS 17
Design Constraints Access, Circulation, and Site Development
4 BUILDING REQUIREMENTS
4.1 SPACE TABULATION 19
4.3 RAIN WATER COLLECTION SYSTEM 20
4.4 EXTERIOR CHARACTER 20
Table of Contents p. 3/81
4.5 MAIN BUILDING SPACE REQUIREMENTS 20
4.6 DRY VIP LATRINES 21
4.7 SETTLEMENT OF EXTERNAL AREAS 21
4.8 PROJECT SIGN 22
4.9 DEDICATION SIGN 22
5 ROOM MINIMUM REQUIREMENTS
5.1 FLOORS, WALLS AND CEILING 23
5.2 DOORS AND WINDOWS 23
5.3 PLUMBING AND FIXTURES 23
5.4 DRY VIP LATRINES 23
5.5 ELECTRICITY AND LIGHTING 24
5.6 GROUNDING SYSTEM 24
5.7 ELECTRICAL PANELBOARD 25
6 GENERAL WORK REQUIREMENTS
6.1 REFERENCE STANDARDS 26
6.2 WORK REQUIREMENTS 26
6.3 DESIGN GUIDANCE 26
6.4 PERFORMANCE TECHNICAL SPECIFICATIONS 26
6.5 SUBMISSIONS 27
Concept Design Final Design Construction Schedule Quality Control Plan Accident Prevention Plan
6.6 CONSTRUCTION GUIDANCE 29
6.7 CERTIFICATIONS, LICENSES, PERMITS, FEES, ETC. 29
6.8 COORDINATION 29
6.9 VEGETATION CONTROL 29
6.10 RESPONSIBILITY OF MATERIALS 30
6.11 SAFETY AND PROTECTION 30
6.12 SPILL CONTINGENCY PLAN 31
6.13 SPECIAL SITE CONDITIONS 31
6.14 CLEANING 31
7 ENGINEERING SYSTEMS REQUIREMENTS
Table of Contents p. 4/81
7.1 SECTION A10 FOUNDATIONS 32
A1010. Standard Foundations A1030. Slab On Grade
7.2 SECTION B10 SUPERSTRUCTURE 32
B1010. Floor Construction B1020. Roof Construction
7.3 SECTION B20 EXTERIOR ENCLOSURE 33
B2010. Exterior Walls
B201001. Balcony Walls, Guard Rails & Handrails B201002. Exterior Coatings
B2020. Exterior Windows B202001. Exterior Windows B202002. Exterior Glazing B201003. Exterior Louvers & Screens
B2030. Exterior Doors B203007. Gates
7.4 SECTION B30 ROOFING 34
B3010. Roof Coverings
B301001. Steep Slope Roofing Systems B301002. Low Slope Roofing Systems
7.5 SECTION C10 INTERIOR CONSTRUCTION 34
C1010. Partitions
C101001. Interior Guardrails C101002. Interior Screens C101003. Interior Windows C101004. Interior Glazing
C1020. Interior Doors C102001. Standard Interior Doors C102002. Glazed Interior Doors
C1030. Specialties C103001. Toilet Compartments and Accessories C103003. Marker Boards C103004. Counters C103005. Cabinets C103006. Ornamental Metal Work
7.6 C30 INTERIOR FINISHES 35
C3010. Wall Finishes C3020. Floor Finishes C3030. Ceiling Finishes C3040. Interior Coatings And Special Finishes
7.7 SECTION D20 PLUMBING 35
D2010. Plumbing Fixtures
D201001. Water Closets D201002. Urinals D201003 Lavatories D201004. Sinks D201005. Finish Trim
D2020. Domestic Water Distribution D202001. Pipes and Fittings
Table of Contents p. 5/81
D202002. Domestic Water Equipment D202003. Insulation & Identification D202004. Specialties D202005. Other Domestic Water Supply
7.8 SECTION D50 ELECTRICAL 36
D5010. Electrical Service And Distribution
D501002. Service Entrance Equipment D501004. Switchboard D501005. Enclosed Circuit Breakers
D5020. Lighting And Branch Wiring D502001. Branch Wiring D502002. Lighting Equipment D502003. Finish Trim D502004. Potential Drop
D5040. Other Electrical Services D504001. General Construction Items (Electrical) D504002. Emergency Lighting and Power D504003. Grounding Systems D504004. Lightning Protection D504005. Electric Heating
7.9 SECTION G10 SITE PREPARATION 38
G1010. Site Clearing
G101001. Clearing G1030 Disposal
7.10 SECTION G20 SITE IMPROVEMENTS 38
G2040. Site Development
G204001. Freestanding Walls & Gates
7.11 SECTION G30 SITE CIVIL/MECHANICAL UTILITIES 38
G301003. Water Storage
8 PERFORMANCE TECHNICAL SPECIFICATIONS (PTS)
8.1. NARRATIVE 40
8.2. SECTION A10: FOUNDATIONS [6/07] 40
A10 General A1010 Standard Foundations
A101001 Wall Foundations A101002 Column Foundations And Pile Caps A101003 Foundation Drainage
A1020 Slab On Grade A102001 Concrete Slabs On Grade A102002 Slab On Grade Insulation
A1030 Elevated Floor Slabs A1040 Concrete
A104001 Concrete Materials A104002 Concrete Formwork A104002 Concrete Reinforcement A104003 Placing Concrete Reinforcement A104004 Concrete Mixing A104005 Concrete Conveying
Table of Contents p. 6/81
A104006 Concrete Depositing A104007 Concrete Curing A104008 Hot Weather Concrete A104009 Concrete Construction Joints A104010 Concrete Testing
8.3. SECTION B10: SUPERSTRUCTURE [06/07] 47
B10 General B1010 Construction Components B1020 Wood B1030 Unit Masonry B1050 Steel
8.4. SECTION B20: EXTERIOR ENCLOSURE [04/07] 51
B20 General B2010 Exterior Walls
B201001 Unit Masonry B201002 Guardrails ad Handrails B201003 Exterior Painting and Special Coatings
B2020 Exterior Windows B202001 Standard Window Systems B202002 Louvered Windows B202003 Screens B202004 Roll Shutters
B2030 Exterior Doors B203001 Standard Doors Systems B203002 Door Frames B203003 Exterior Door Hardware B203004 Exterior Door Hardware Finishes B203005 Other Exterior Specialty Doors
8.5. SECTION B30: ROOFING [04/07] 54
B30 General B3010 Steep Slope Roof Systems
B301001 Slate Roofing B301002 Roof Tiles B301003 Metal Roof Panels B301004 Concrete Roof Panels
B3020 Low Slope Roof Systems B302001 Built-Up Asphalt Roofing (Aggregate Surfaced)
B3030 Flashings & Trim B303001 Flashing And Sheet Metal B301002 Gutters and Downspouts B301003 Roof Openings and Supports B301004 Other Roofing
8.6. SECTION C10: INTERIOR CONSTRUCTION [06/07] 57
C10 General C1010 Partitions
C101001 Unit Masonry C101002 Handrails C101003 Interior Painting And Special Coatings
C1030 Interior Doors C103001 Standard Doors Systems
Table of Contents p. 7/81
C103002 Door Frames C103003 Interior Door Hardware C103004 Interior Door Hardware Finishes C103005 Other Interior Specialty Doors
C1040 Specialties C104004 Counters C103005 Cabinets C104006 Casework
8.7. SECTION C30: INTERIOR FINISHES [04/07] 59
C30 General C3010 Wall Finishes
C301001 Plaster Wall Finishes C301002 Tile Wall Finishes
C3020 Floor Finishes C302001 Ceramic Tile Floor Systems C302002 Ceramic Glazed Tile Floor C302003 Ceramic Mosaic Unglazed Floor Tiles C302004 Porcelain Floor Tile C302005 Quarry Floor Tile C302006 Terrazzo Floor Finishes C302007 Masonry And Stone Flooring C302008 Wall Base Finishes C302008 Stair Finishes C302009 Hardeners And Sealers
C3030 Ceiling Finishes C303001 Acoustical Ceiling Tiles And Panels C303002 Plaster Ceiling Finishes
C3040 Interior Painting And Special Finishes C304001 Painting Systems Per Substrate C304002 Concrete Finishes C304003 Concrete Masonry Finishes C304004 Plaster Finishes C304005 Metal Finishes C304006 Interior Wood Finishes
8.8. SECTION D20: PLUMBING [08/06] 65
D20 General D2010 Plumbing Fixtures
D201001 Water Closets D201002 Urinals D201003 Lavatories D201004 Sinks D201005 Showers/Tubs
D2020 Domestic Water Distribution D202001 Pipes & Fittings D202002 Valves & Hydrants D202003 Domestic Water Equipment D202004 Insulation & Identification
D2030 Sanitary Waste D203001 Waste Pipe & Fittings D203002 Vent Pipe & Fittings D203003 Floor Drains
Table of Contents p. 8/81
8.9. SECTION D30: HVAC [06/07] 68
D30 General D3010 Heat Generating Systems
D301001 Boilers D301002 Heating Hot Water Distribution Systems D301003 Terminal Units D302001 Requirements D302002 Hot Water Heating Equipment Startup and Operational Tests
D3040 Performance Verification And Testing
8.10.SECTION D50: ELECTRICAL [08/06] 69
D5010 General
D501001 Quality Assurance D501002 Submittals
D5020 Electrical Service And Distribution D502001 Main Transformers D502002 Service Entrance Equipment D502003 Interior Distribution Transformers D502004 Switchboard D502005 Enclosed Circuit Breakers D502006 Motor Control Centers D502007 Other Service And Distribution
D5030 Lighting And Branch Wiring D503001 Branch Wiring D503002 Lighting Equipment D503003 Ballasts
D5050 Other Electrical Services D505002 Emergency Lighting And Power
8.11.SECTION G10: SITE PREPARATION 73
G10 General G1010 Site Clearing G1020 Site Demolition & Relocations
G102001 Building Mass Demolition G102002 Hazardous Components Abatement G102003 Aboveground Site Demolition G102004 Underground Site Demolition G102005 Fencing Relocation G102008 Site Cleanup
G1030 Site Earthwork G103001 Grading G103002 Common Excavation G103003 Rock Excavation G103004 Fill & Borrow G103005 Compaction G103006 Soil Stabilization G103007 Slope Stabilization G103008 Shoring G103009 Temporary Dewatering G103010 Temporary Erosion & Sediment Control G103011 Other Site Earthwork
G1040 Hazardous Waste Remediation
8.12.SECTION G20: SITE IMPROVEMENTS [08/06] 78
Table of Contents p. 9/81
G20 General G2010 Roadways G201001 Paved Surfaces G201002 Resurfacing
G2020 Pedestrian Paving G2030 Other Site Development G204001 Fencing & Gates G204002 Retaining Walls
Legenda p. 10/81
LEGENDA: ACRONYMS AND DEFINITIONS
As used throughout this solicitation/contract:
Contracting Officer [KO] is the Government’s representative in charge for executing the contract and responsible for any amendment.
Contractor is for the Offeror that has been awarded the contract COR stands for the Contracting Officer Representative, who is a qualified Government employee appointed by the KO to assist in the technical monitoring or administration of a contract D/B contract stands for Design and Build contract, which means that the contractor shall first provide a complete and executable design matching the specifications of the TR, then implement the construction in accordance to such a design.
DOD stands for U.S. Department of Defense ESR stands for Engineering System Requirements Government stands for the Government of the United States of America (U.S.A.);
HVAC stands for Heating, Ventilating and Air Conditioning NAVFAC EURAFSWA stands for Naval Facilities Engineering Command Europe, Africa and South West Asia; it is the Government’s executive agent for construction.
NTPC stands for Notice To Proceed with the Construction NTR stands for Navy Technical Representative, who is in charge to monitor the performance of work under the contract and is an accountable official for purposes of certifying payments Offeror is any constructor that submits a bid Project Manager [PM] is the Government’s technical representative in charge for managing the project (scope, cost, and schedule) from design authorization to closeout PTS stands for Performance Technical Specifications RFP stands for Request for Proposal RFQ stands for Request for Quote SF stands for Government’s standard form; this acronym is followed by a number identifying what contract action the form is intended for SOW stands for Statement Of Work: it is the detailed description of the work activities, deliverables and timeline the contractor will execute against in performance of specified work TEB stands for the Government Technical Evaluation Board in charge to receive, accept and evaluate the technical offers TR stands for Technical Requirements which are integrant part of the SOW and provide all the specifications for the design and the implementation of the project.
VIP stands for Ventilated Improved Pit which is the type of latrine to be implemented at the site as described in this SOW.
1. Project Description p. 11/81
1 PROJECT DESCRIPTION
1.1 GENERAL
Design and Build a Health Post in accordance to the Ministry of Health [MoH] standards, and to the requirements, sketches, and tables included hereby.
1.2 SCOPE OF PROJECT
The work shall consist of the following (dimensions are approximate):
a. Build a 130 m2 Health Post (rudimentary building) to include:
1 delivery room 1 pre-delivery consultation room 1 treatment room 1 general consultation room 1 pharmacy 1 office 1 technical storage room 1 changing/wardrobe room 1 veranda along the main entrance side 1 solar power system (to be designed and installed by a qualified firm)
b. Build a dry Ventilated Improved Pit [VIP] latrine facility to include:
4 stalls (2 for each gender) 1 screen wall 2 sinks
c. Build a water system to include:
1 underground 4,000 liter reservoir to be fed by truck 1 super-elevated 500 liter tank to be fed by pump 1 electric pump to be fed by the solar power 1 water distribution system
d. Build a rainwater drainage/collection system to include:
gutters 3,000 liter water tank 1 tap 1 masonry supporting base
e. Build a 8m x 6m sheltered waiting area to be located on one side of the main building.
f. Build a 1.45 m x 1.45 m incinerator in accordance to MoH standards.
g. Build a 40 m x 25 m fence wall to enclose the whole health post complex.
The new work shall result into complete, safe and usable health post complex, whose layout and interior spaces shall reflect the building requirements provided in the Part 4. Design and construction details are provided in the Part 5, and specified in Parts 6, 7, and 8.
All buildings shall have concrete superstructure and masonry infill construction with basic finishes.
1. Project Description p. 12/81
All buildings shall have a storm water drainage system to prevent erosion.
The work shall include - but not be limited to - the following: Demolition of existing structures, Foundations, Structures, Superstructures, Interior Construction, Roof System, Electrical System, Plumbing System, Exterior Area Settlement, Site Improvements and Other Work as required.
The work shall include a complete design and drawing package as described below. Design to meet all requirements of the RFP package. Drawings to be as described below and as required to communicate the design to the US Government, final users, contractor’s staff and sub-contractors.
Material selection, specifications and installation to be as described the in the Engineering Systems Requirements (ESR), and in the Performance Technical Specification (PTS), included below as the last two parts.
The ESR and the PTS of this document provide a guideline for the design package. If an item in the project design is included in the ESR/PTS, the requirements of the ESR/PTS and applicable local codes shall govern. If an item in the project design is NOT included in the ESR/PTS, the requirements of applicable local codes shall govern.
The design shall be developed by qualified design professionals, either consistently employed in the contractor’s company or working for a design firm hired by the contractor for the purpose of this project.
1.3 SIGNAGE
Project Sign The Contractor shall provide a painted project sign to be located at the worksite as soon as the construction starts. The paint shall be water resistant and display the project name, the Mauritanian and American flags, and the wording explaining the cooperation between the two Governments.
The Contractor shall submit a proof of the sign for acceptance prior to construction.
See detailed requirements at par. 4.8.
Dedication Sign The Contractor shall provide a project dedication sign (approximately 800 mm x 1200 mm) at the project site at least 2 weeks prior to project completion.
The project name shall appear at the top center, followed by the sentence “An everlasting example of friendship between the people of Mauritania and the United States” above the flags, and the sentence “Completed by the people of Mauritania and the United States of America on DD MONTH, YYYY” at the bottom.
The sign shall be constructed of sheet metal with a water resistant coating and affixed directly to the building at a location approved by the facility administrator and the COR.
The Contractor shall submit a proof of the sign for acceptance prior to manufacturing the sign.
See detailed requirements at par. 4.9
1.4 STANDARD NOMENCLATURE
This is an American document, and this note is to define the way in which numbers are presented herein:
1,000 = one thousand 3,500 = three-thousand five-hundred
1.08 = one and eight hundredths
0.1 = one-tenth
1. Project Description p. 13/81
1.5 PROCEDURE
The construction phase shall start only once that the official Notice to Proceed with Construction (NTPC) is issued by the NAVFAC EURAFSWA Project Manager/Contracting Officer.
The NTPC will not be issued until all required submittals are received and reviewed by the US Government and shown to meet the specifications of these Technical Requirements and the Solicitation package.
PRE-CONSTRUCTION SUBMITTALS CONSIST OF:
Concept Design Final Design Construction Schedule Quality Control Plan Accident Prevention Plan
CONCEPT DESIGN
The concept design shall be submitted within 50 calendar days of receipt of the award. The concept design is intended to assure all lay-out requirements are clearly met before the full design is developed. It shall identify site preparation, including items to be removed and to be kept. It shall provide the basic architectural design, including:
Current Site Layout plan with dimensions and distances Final Site Layout plan with dimensions and distances Final Plans, Elevations and Sections of each building.
The Government shall review the concept design submission for compliance with these Technical Requirements and the Solicitation package and provide written comments to the contractor.
See paragraph 6.5 for detailed explanation about the concept design.
FINAL DESIGN
The contractor shall have 100 calendar days to complete the design, incorporating all concept design review comments provided by the US Government. Elapsed timelines may be considered depending on which option is awarded, if any.
In the event the contractor does not concur with the US Government comments, the contractor shall notify the contracting officer in writing of the reasons for the non-concurrence.
The final design shall meet all the requirements identified in these Technical Requirements and the Solicitation package and shall include:
Site Improvement Drawings Architectural Drawings Structural Drawings Plumbing Drawings Electrical Drawings All Calculations and Details required to validate the design.
See paragraph 6.3, 6.4, and 6.5 for detailed explanation about the final design.
CONSTRUCTION SCHEDULE
The contractor shall have 270 calendar days to complete the construction work.
Within the timeframe allowed for the final design submission, the contractor shall prepare and submit a schedule of construction where the different work segments are identified and associated to the timeframe set for completion. The construction schedule shall state which work segments completion determines the achievement of the construction steps associated to the progressive invoicing (typically 10% (design completion), 40%, and 70% construction progress).
See paragraph 6.5 for more details about the construction schedule.
QUALITY CONTROL PLAN
Within the timeframe allowed for the final design submission, the Contractor will prepare and submit a Quality Control Plan describing personnel, procedures, tests and installation techniques that he plans to perform to ensure the quality required by this document and his design is obtained.
1. Project Description p. 14/81
ACCIDENT PREVENTION PLAN [APP]
Within the timeframe allowed for the final design submission, the Contractor will prepare and submit an APP describing procedures he plans to perform to ensure the safety of personnel and equipment on the job site. At a minimum, the safety plan must address types of personnel protective equipment to be used by personnel, types and frequencies of safety inspections, hazard analysis plan [AHA] to prevent safety incidents, and training utilized to familiarize employees with safety policies and practices.
See paragraph 6.5 for more details about the APP.
INTERIM SUBMITTAL REQUIREMENTS
During construction, the Contractor is required to submit:
Bi-weekly work progress report with photos Monthly work man-hours report Test results as required per the contract At least 10 days prior to installation of all electrical components, plumbing fixtures, windows and doors and associated hardware, a sample (or catalog photo) must be shown to the KO or COR for acceptance.
Possible construction schedule changes (to be motivated) Possible design changes (to be motivated) Invoices in accordance to work progress
COMPLETION SUBMITTAL REQUIREMENTS
Upon completion of project and prior to final payment, the Contract is required to submit:
Final as-built drawings Operations and maintenance plan A telephone contact number available for the duration of the warranty period.
~~~ End of Part 1 ~~~
2. Project Objectives p. 15/81
2 PROJECT OBJECTIVES
2.1 MISSION STATEMENT
DoD humanitarian assistance activities were first authorized by US Congress in 1986. In FY 1996, DoD was permitted to fund a wider variety of HA activities, including using contracts and deployment of U.S. Government personnel to conduct specific humanitarian projects.
Typical projects include the refurbishment of medical facilities, construction of health post buildings, digging of wells, construction of schools, improvement of sanitary facilities, and training of host country personnel in internally displaced persons/refugee repatriation operations and in disaster relief and emergency response planning.
The DoD, in an attempt to assist in development and implementation of the Humanitarian Assistance Program, is funding and coordinating the project which is the subject matter of this contract.
NAVFAC EURAFSWA has been designated as the Construction Agent for this project.
2.2 FACILITY FUNCTION
The health post complex will be situated in a remote area lacking any sanitary infrastructure, so the facility will also be used by the surrounding villages.
The clinic will provide assistance to women for delivery, and help handle quick accidents related to the population agricultural activities.
The operation of this health post will improve the health conditions in the area, and reduce the infant mortality rate.
2.3 PROJECT SPECIFIC PRIORITIES
Sustainable Design Integrate sustainable principles into the design, development and construction of the project.
Reduce the total cost of ownership of the facility using a whole building, life-cycle approach.
Provide integrated sustainable design strategies and features to minimize the energy consumption of the facilities; conserve resources; minimize adverse effects to the environment; and improve occupant productivity, health, and comfort.
Energy Conservation Integrate energy conservation principles into the design, development and construction of the project. Reduce the total cost and consumption of energy in the facility using a whole building approach.
2.4 APPROPRIATE DESIGN
The design is to maintain an indigenous character. As much as possible, materials are to be available locally to promote the local economy and to take advantage of the skills and experience of local trades-persons. Construction methods are to be in-line with those used locally to take advantage of the skills and experience of local trades-persons.
2.5 WORKFLOW PROCESS - HOURS OF OPERATION
The work of this contract is to be done during the hours the facility is normally open to the public. If needs arise to work other than normal hours, obtain approval from, and coordinate with the facility owner.
~~~ End of Part 2 ~~~
3. Site Analysis p. 16/81
3 SITE ANALYSIS
3.1 EXISTING SITE CONDITIONS
The land intended for the construction is an empty sandy area in the isolated village of Bouhadjra, located at GPS coordinates 16o 29' 94" 04 and 16o 40' 22" 28, in the vicinity of a school.
The village is within the area of the Diawling National Park in the municipality of N'diago, Moughataa de Keur, and it is reachable only by a dirty road.
The above picture shows the current status of the area seen from the East side. The building in the distance is the school.
Utilities are not available in the vicinity.
The water supply to the village is provided by truck.
3. Site Analysis p. 17/81
3.2 SITE DEVELOPMENT REQUIREMENTS
An example of the health post compound final layout is sketched below.
Exact new facility orientation and layout shall be determined to best fit the topography and the prevailing winds, and shall be coordinated with the health post officials.
Facility Footprint A scaled drawing with exact dimensions showing the site lay-out including location of all existing buildings, latrines, and perimeter wall (if any) with gate locations shall be included in the concept design. The drawing shall show the items to be removed, those to stay, and those to be built.
DESIGN CONSTRAINTS
Design of the facility and its location and orientation within the proposed site shall take into consideration all natural and man-made constraints, which include but aren’t limited to:
Topography: all site slopes shall be taken in account in order to minimize the need for cut and fill operations Vegetation / Landscaping: vegetation shall be protected, and landscaping design shall be maintainable Climatology (solar orientation, etc.): Design shall take advantage of prevailing wind direction and solar orientation to naturally moderate the interior temperature of the buildings Geotechnical Data: Foundations and structural components of the buildings shall be designed in accordance with geotechnical soils report information. Geotechnical engineering services shall be provided if no current report exists for the site. Design shall be in accordance to the seismic zone of classification of the project site.
Hydrographic Survey: a hydrographic survey shall be performed to determine the storm water runoff
3. Site Analysis p. 18/81
Vehicular Access and Circulation: existing vehicular access shall be taken in account Site Utilities: location and capacity of all existing utilities on site shall be verified prior to start design Site Drainage: the facilities shall be designed without negative impact from storm water runoff to the adjacent area of the site.
Existing Buildings: Identify and accurately locate on the site plan all existing buildings on the site.
Fencing: Identify and accurately locate on the site plan all existing fencing on the site.
Permits: all permits, approvals, and authorizations needed to implement the design shall be obtained prior to start construction.
ACCESS, CIRCULATION, AND SITE DEVELOPMENT
Any proposed vehicular and/or pedestrian access, paths, sidewalks, steps, parking areas, outdoor recreation area, landscaping etc. shall be reported on the site plan, as well as areas of material storage and temporary security fencing.
All proposed drainage channels shall be shown on the site plan.
The location of the construction sign and any other signage required by local authorities shall be indicated on the site plan.
~~~ End of Part 3 ~~~
4. Building Requirements p. 19/81
4 BUILDING REQUIREMENTS
4.1 SPACE TABULATION
Indicative data regarding the size of the new facilities are provided in the tables below.
On the concept design submittal the contractor is required to provide exact dimensions corresponding to the actual design; a variance exceeding ±10% of the indicative size will not be considered acceptable.
Health Post Building
Space Name # Unit m2
(Net)
Total m2
(Net)
Optimal Dimensions (m)
Ceiling Height
(m) people per room Remarks
Veranda 1 29 29 1.80 x 16.00 2.90
Delivery Room 1 16 16 4.00 x 4.00 2.90 3 1 tiled counter with sink, A/C* Pre-delivery Consultation Room 1 14 14 3.50 x 4.00 2.90 3 close to delivery room, 1 sink Treatment Room 1 16 16 4.00 x 4.00 2.90 3 1 tiled counter with sink Consultation Room 1 14 14 3.50 x 4.00 2.90 3 1 sink; 1 tiled counter Office 1 15 15 3.70 x 4.00 2.90 2 Pharmacy 1 6 6 2.30 x 3.00 2.90 2 cage to public; A/C* Storage/Wardrobe 1 5 5 2.30 x 1.80 2.90 0 Technical Room 1 3 3 2.30 x 1.50 2.90 0 battery; fridge** Entrance Hall 1 17 17 3.50 x 4.80 2.90 6 Double door to exterior Corridor 1 7 7 1.00 x 7.00 2.90 Half grated and glazed door to exterior
Subtotal Net Area (m2) 118 * just set up the electrical system to feed A/C equipment
Net to Gross Factor 1.1 ** just set up the electrical system to feed a fridge
TOTAL GROSS AREA (m2) 130 8 x 16
Other Facilities
Facility Name Qty Optimal Size Remarks
Roofed Waiting Area 1 6.0 m x 8.0 m no enclosing walls
VIP Toilet Stall 4 1.5 m x 1.0 m 2 wall vents on opposite walls, 6 m deep pit below the slab, 1 pipe vent
Incinerator 1 1.45 m x 1.45 m to be in accordance to MoH standards
Underground Water Tank 1 4,000 l to be fillable by a water truck, to be connected to the elevated tank through a pump
Elevated Water Tank 1 500 l to be installed on a 2m tall concrete support and connected to the plumbing system
Rain Water Tank 1 3,000 l to be equipped with a tap and connected to the water catchment system
Fence Wall 1 25 m x 40 m 1 m tall masonry wall with 1 m tall metal frame on top
4. Building Requirements p. 20/81
4.3 RAIN WATER COLLECTION SYSTEM
The health post building roof and waiting area roof shall be equipped with gutters connected to a 3,000 liter tank to collect rain water. The collection tank shall be provided with a foundation, a masonry base, a tap, and all accoutrements to ensure proper functionality and ease of use.
4.4 EXTERIOR CHARACTER
The design is to maintain an indigenous character and to match the surrounding features of the facilities located nearby.
4.5 MAIN BUILDING SPACE REQUIREMENTS
The space layout for the main building is sketched below: the design shall be in line with this concept.
The entrance side shall be oriented towards south (opposite of prevailing wind direction).
Exact position shall be determined in accordance to the area topography.
4. Building Requirements p. 21/81
4.6 DRY VIP LATRINES
One 4-stall dry VIP latrine facility shall be built on the side of the main building. Exact position to be determined in order to guarantee proper ventilation and easy access.
Special attention shall be provided to make sure the VIP facility is placed downwind of the clinic facilities, preferably where the soil is firmer and has good drainage. The doorway of the VIP latrine shall face the prevailing winds.
Separate male/female access to be implemented.
The reference scheme for the VIP design is reported above and on the side.
The design shall reflect this concept, and shall incorporate all requirements described at par. 5.4.
4.7 SETTLEMENT OF EXTERNAL AREAS
The Contractor shall grade the site to limit water from ponding and promote positive drainage off of the grounds.
4. Building Requirements p. 22/81
4.8 PROJECT SIGN
The Contractor shall provide a painted project sign to be located at the worksite as soon as the construction starts. The sign shall be made of wood and supported by wooden or metal posts.
The approximate size of the sign shall be 800mm x 1200mm and the sign shall be placed in such a way so as to provide the most visibility to passers-by; the location shall be agreed with the COR.
The Contractor shall submit a proof of the sign for approval prior to construction.
The paint shall be water resistant and display the following:
BOUHADJRA HEALTH CLINIC CONSTRUCTION
<Mauritanian flag> <American flag>
In cooperation with the Mauritanian Government, funding for this project is provided by the U.S. Government.
<Contractor’s Name>
Project name shall appear at the top center in 76mm (3 inch) tall capital block letters. The sentence below the flags shall be in 38mm (1.5 inch) sentence case lettering. Contractor company name may be added at the bottom of the sign.
4.9 DEDICATION SIGN
At least 2 weeks prior to project completion a project dedication sign shall be affixed at the project site. The sign shall be affixed directly to the building at a location approved by the facility administrator and the COR to provide optimal visibility.
The sign shall be constructed of sheet metal with a water resistant coating and shall have a frame around it. The frame material shall be wood and be approved by the COR prior to installation. The size of the sign shall be approximately 800 mm x 1200 mm.
No later than 4 weeks prior to the planned project completion, the Contractor shall contact the KO or the COR regarding final wording for the dedication sign.
The Contractor shall provide a proof of the sign for acceptance prior to manufacturing the sign.
The sign shall display the following:
BOUHADJRA HEALTH CLINIC CONSTRUCTION
An everlasting example of friendship between the people of Mauritania and the United States.
<translation into the Host Nation primary language>
<Mauritanian flag> <American flag>
Completed by the people of Mauritania and the United States of America on:
DD MONTH, YYYY
The project name shall appear at the top center in 76mm (3 inch) tall block letters, followed by the above sentence in 38mm (1.5 inch) sentence case lettering that shall be repeated in the Host Nation primary language. The Host Nation and American flags shall be placed as displayed in the above sketch. The sentence at the bottom shall be in 20mm (0.75 inch) sentence case lettering.
~~~ End of Part 4 ~~~
5. Room Minimum Requirements p. 23/81
5 ROOM MINIMUM REQUIREMENTS
5.1 FLOORS, WALLS AND CEILING
All floors shall be tiled flooring granting good resistance and easiness to be kept sanitized.
All walls shall be plastered and painted with glaze suitable for hospital use.
All rooms shall be provided with false ceilings.
Complete details are reported at Part 7 and Part 8, Section C30 of this document.
5.2 DOORS AND WINDOWS
Windows shall be adequately sized and positioned to guarantee ventilation.
All doors and windows shall be equipped with lintels.
All room building windows shall be fully openable to guarantee ventilation, and grated to be protected from access.
All window fixtures shall be equipped with mosquito screens.
The main entrance door shall be at least 180 cm large and equipped with an emergency bar; all external doors shall open to the exterior.
Complete details are reported at Part 7 and Part 8, Section C10 of this document.
5.3 PLUMBING AND FIXTURES
The water distribution system shall be connected to the overhead water tank.
The underground tank shall be connected to the overhead tank through a pump fed by the solar power system.
In case of power shortage the pump shall be manually operated.
The underground tank shall be designed to be filled by truck.
One faucet with relevant sink shall be installed in each side of the latrine block. They shall be connected to the overhead water tank.
The gutters collecting the storm water shall be connected to the rain water storage tank. The water shall be drawn from the tank by means of a tap situated at 1 m from ground.
Complete details are reported at Part 7 and Part 8, Section D20 of this document.
5.4 DRY VIP LATRINES
Stall floors shall be reinforced concrete slabs with an opening to serve as a squat hole.
Stall roof shall be galvanized corrugated metal sheeting on timber rafters and purlins.
Dry pit shall be 6 m deep with plan dimensions equal to the total stall area.
Pit walls shall be lined with the masonry block.
Wall vents shall be at least 0.5m x 0.1m.
Each stall shall be equipped with a uPVC vent pipe 150mm extending at least 0.5m above the roof.
Vent pipe shall be covered with gauze mesh or fly-proof netting and shall ensure unobstructed air flow.
A 2m tall masonry screen wall shall be provided at the front of the latrine block, at least 1.1 m off the latrine doors.
The concept design for a 4-stall latrine is provided at par. 4.6 as a reference. The design shall be in accordance to that concept and with the above requirements.
5. Room Minimum Requirements p. 24/81
5.5 ELECTRICITY AND LIGHTING
The source of electricity shall be a solar power system properly dimensioned to suit the facility electrical loads (to be determined with the end user).
The electrical system shall be designed and implemented by a qualified installator able to release a valid certificate of compliance with electrical regulations.
The electrical design shall keep into consideration the room use and the equipment to be installed. At least one 16A sockets shall be installed in each room.
Three-way switches shall be installed close to each entry point to any space having more than one entrance.
Emergency lights shall be installed on each room’s main door.
It is required the installation of low consumption lamps in a number and size sufficient to guarantee proper illumination to each type of space. The average illumination over the room area at 80 mm above the floor shall be at least 107 lux for offices and rooms and at least 11 lux for corridors.
Electrical cables shall be dimensioned in accordance to the loads relevant to each circuit.
In order to properly dimension the section of an electrical cable it is recommended to make reference to the table below showing the typical max resistance values for copper cables of different sizes and the relevant maximum current each one can bear.
Section (mm2)
R (Ω/km)
Max Current (A)
1 19.5 5
1.5 13.3 10
2.5 7.98 16
4 4.95 26
6 3.30 32
10 1.91 50
16 1.21 68
25 0.78 92
35 0.55 120
The potential drops (depending on the cable resistance and on the current through it, V=R*I) shall be kept under 4%.
The connection to the public electrical network shall be done in agreement to the electrical company requirements.
Complete details are reported at Part 7 and Part 8, Section D50 of this document.
5.6 GROUNDING SYSTEM
A grounding (earthing) system consisting of multiple connected rods shall be designed and implemented.
Rods shall be located away from most accessible areas, shall be protected from involuntary/unauthorized access and signposted by the earth symbol shown on the side. At least two rods per building shall be installed.
Grounding Symbol
5. Room Minimum Requirements p. 25/81
Fig. 7 – Example of Panelboard
5.7 ELECTRICAL PANELBOARD
The electrical power feed shall be divided into subsidiary circuits by a panelboard providing a protective circuit breaker for each circuit. A main panelboard - providing a breaker for each line connecting to subpanels located at each new and renovated room block - shall be located immediately downstream the delivery point (meter). All electrical panels shall be housed in a common enclosure.
The panelboard enclosure shall be galvanized sheet steel cabinet minimum 1.5 mm thickness, properly mating the panelboard to be enclosed; enclosure’s door shall be lockable.
A main switch located upstream the main panelboard shall protect the electrical system against both overcurrents and residual (ground fault) currents through a Residual Current Breaker with Overcurrent (RCBO) protection whose sensitivity ID is 30 mA.
Sensitivity may be bigger in case other RCDs (Residual Current Devices) with ID = 30 mA are provided downstream to protect groups of circuits.
Fig. 6 shows an example of RCBO.
Each circuit in the panelboard shall be protected against over-currents by a thermal magnetic breaker whose nominal current is ≤ of the max current associated to the relevant cable section, as shown in the table at par. 5.3.
Each breaker shall be labeled to show which circuit it controls.
Lighting circuits and utilization circuits shall be kept separated and individually protected on the panel board.
~~~ End of Part 5 ~~~
Fig. 6 - RCBO
6. General Work Requirements p. 26/81
6 GENERAL WORK REQUIREMENTS
6.1 REFERENCE STANDARDS
Construction shall be in accordance with sound construction practices, and shall conform to the latest revision/edition of the codes, criteria, and standards referenced below except as otherwise indicated by this Request for Proposal.
Construction shall also comply with applicable codes, ordinances and regulations of the Republic of Mauritania governing life/safety, fire protection, building construction, HVAC (heating ventilation and air conditioning) systems, plumbing systems and electrical systems in effect during this contract, except where specifically stated herein.
Any material installed that does not meet the requirements of the following Performance Technical Specification (PTS) and/or applicable codes, ordinances and regulations will be removed and reinstalled at Contractor’s expense.
6.2 WORK REQUIREMENTS
The building renovation and the exterior area settlement as described from Part 1 through 5 shall be in accordance to the specifications provided in the following Parts 7 and 8. All the engineering system requirements described in the Part 7 are more detailed in the corresponding Part 8.
Special attention shall be paid to develop and to adhere to the STRUCTURAL DESIGN and to the
ELECTRICAL DESIGN.
All the concrete and electrical work shall be tested and delivered with a Test Certificate issued by a local qualified entity.
6.3 DESIGN GUIDANCE
Design shall be in accordance with sound design and engineering practices, and shall conform to the latest revision/edition of the codes, criteria, and standards referenced below except as otherwise indicated by this Request for Proposal. Design shall also comply with applicable codes, ordinances and regulations of the Republic of Mauritania governing life/safety, fire protection, building construction, plumbing systems, electrical systems and sanitation systems in effect during this contract, except where specifically stated herein.
The advisory provisions of all codes, requirements, and standards shall be mandatory; substitute words such as “shall”, “must”, or “required” for words such as “should”, “may”, or “recommended,” wherever they appear. The results of these wording substitutions incorporate these code and standard statements as requirements. Reference to the “authority having jurisdiction” shall be interpreted to mean “Contracting Officer”. Comply with the required and advisory portions of the current edition of the standard at the time of contract award.
The last two sections of this document, in many instances, give multiple options for material and processes. It is the intent to give the contractor’s designer freedom to use one or multiple options in the design, based upon sound design and engineering practices and the requirements of the project.
Once an option is selected for the project, all requirements outlined in the PTS for that option are to be incorporated in the design.
6.4 PERFORMANCE TECHNICAL SPECIFICATIONS
The specifications for this project are requirements based, meaning that the technical details of how to meet this requirement are not included in the PTS.
The contractor shall determine the technical requirements for satisfying these specifications and present them as part of the design package.
The contractor’s design shall provide the technical requirements for the project and the contractor shall be responsible for ensuring their design meets all specifications presented in this SOW.
6. General Work Requirements p. 27/81
6.5 SUBMISSIONS
The Contractor shall be responsible for developing a design for the facility that meets all the operational requirements identified in this document. Contractor shall provide a full design of the facility to include drawings and all calculations and details required to validate the design.
CONCEPT DESIGN
Within 50 calendar days since the contract award, the contractor shall submit a concept design to consist of the following drawings:
- Current Site Plan (identifying existing items to demolish and existing items to remain)
- Final Site Plan (identifying existing items to remain and new items with dimensions)
- Floor Plans of new structures
- Exterior Elevations of new structures
- Sections of new structures
- List of final design documents to be submitted, to include an explanation of any documents listed below but not required
The Government shall review the submission and provide written comments to the contractor.
In the event the contractor does not concur with the Government comments, the contractor shall notify the Government in writing of the reasons for the non-concurrence.
FINAL DESIGN
Within 100 calendar days after the concept design submittal is complete and comments are returned to the contractor, the contractor shall submit a complete, final design incorporating all the comments from the Government, to consist of the following (as required):
- Civil Drawings
- Site Demolition Plan
- Site Plan
- Grading Plan
- Architectural Drawings
- Floor Plans
- Roof Plans
- Room Finish Schedule
- Door and Window Schedules
- Exterior Elevations
- Building Sections
- Wall Sections
- Enlarged Plans
- Reflected Ceiling Plans
- Interior Elevations
- Door and Window Details
- Miscellaneous Details
- Structural Drawings
- Structural Notes/Basis of Design
- Pier Plan/Schedule
- Foundation Plan
- Floor and Roof Framing Plans
- Lateral-Force Resisting System
6. General Work Requirements p. 28/81
- Sections and Details
- Structure Calculation
- Plumbing Drawings
- Plumbing Plans
- Rain Drainage Plans
- Water tanks design
- Miscellaneous Details
- Electrical Drawings
- Notes, Legends, Symbols List
- Distribution Switchboard Scheme
- Grounding System Plan
- Single Line Diagrams
- Floor Plans, power and lighting
- Circuit/breaker size calculation
- Miscellaneous Details
CONSTRUCTION SCHEDULE
The contractor shall prepare a Construction Schedule in a format approved by the PM. The schedule shall identify the different work segments associated to the timeframe set for completion.
Payment will be tied to satisfactory completion of each of these work segments. The construction schedule shall state which work segments completion determines the achievement of the construction steps associated to the progressive invoicing (typically 10% (design completion), 40%, and 70% construction progress, but it can be more divided). The contractor shall submit the proposed schedule to the PM within the timeline allowed for the final design submission. The contractor shall have 270 calendar days to complete the work.
QUALITY CONTROL PLAN
The Contractor will prepare a Quality Control Plan describing personnel, procedures, tests and installation techniques that he plans to perform to ensure the quality required by these TR and by his design is obtained.
ACCIDENT PREVENTION PLAN
Within the timeframe allowed for the final design submission, the Contractor will prepare and submit an Accident Prevention Plan [APP] describing procedures he will put in place to ensure the safety of personnel and equipment on the job site.
The APP shall consist of the following 10 sections:
1. Signature Sheet
2. Background Information (area map)
3. Statement of Safety and Health Policy (signed company Safety Policy)
4. Responsibilities and Lines of Authority (Proof of competency/qualification of listed personnel)
5. Subcontractors and Suppliers (List)
6. Training
7. Safety and Health Inspections
8. Accident Reporting
9. Plans (Programs, Procedures)
10. Risk Management Processes (Activity Hazard Analysis [AHA], required for each Definable Feature Of Work [DFOW])
Several sections require certain supporting documents (resumes, certificates of training, organization chart, specific plans (crane lift plan medical support plan, etc.). The supporting documents and plans must be attached to the APP.
6. General Work Requirements p. 29/81
Generic AHAs will be made available by the PM. To use the Generic AHA the contractor shall provide a table like the one below to indicate which Generic AHAs are incorporated in the APP;
furthermore he/she shall fill all blanks in each generic AHA that applies (which shall be checked and signed).
Generic AHA used in the APP Yes No/NA G1- Mobilization / General Construction G2 - Demolition G3 – Scaffolding / Fall Protection G4 – Excavation / Trenching G5 - Electrical
Upon final acceptance of the design by the Government, the contractor shall be issued a written notice to proceed with construction [NTPC].
No construction work is authorized to start prior to the NTPC is issued.
6.6 CONSTRUCTION GUIDANCE
Construction shall start after a NTPC is issued by NAVFAC EURAFSWA.
Construction shall be in accordance with sound construction practices, and shall conform to the latest revision/edition of the codes, criteria, and standards referenced below except as otherwise indicated by the Request for Proposal.
Construction shall also comply with applicable codes, ordinances and regulations of the Republic of Mauritania governing life/safety, fire protection, building construction, HVAC (heating ventilation and air conditioning) systems, plumbing systems, electrical systems and sanitation systems in effect during this contract, except where specifically stated herein.
Any material installed that does not meet the requirements of this document and/or applicable codes, ordinances and regulations will be removed and reinstalled at Contractor’s expense.
6.7 CERTIFICATIONS, LICENSES, PERMITS, FEES, ETC.
The Contractor shall be responsible for determining and paying all fees associated with, and obtaining any required permits for this project including, but not necessarily limited to permits for on-site and off-site hauling, demolition/disposal, storm water discharge, construction activity, utilities, road improvements, communications, etc.
The contractor is responsible for acquiring any required certifications (licensing). Coordinate all permit requirements with the Contracting Officer. Submit all completed permit application material, and associated back-up material, required to operate facilities, to the Contracting Officer for approval prior to agency submission.
Contractor shall be responsible for complying with environmental laws, regulations and requirements.
6.8 COORDINATION
All coordination with the local, regional, national authorities shall be the responsibility of the contractor.
The Contracting Officer shall be notified of any disputes between agencies or approvals that will affect Contract Completion or Contract Price.
6.9 VEGETATION CONTROL
The Contractor shall control vegetation within the work area during construction by treating with an approved herbicide/soil sterilizant and removing dead material as directed by the…