N32253-19-R-0024_Q&A.pdf

PDF 80 KB Posted

Attached to
Commercial Industrial Services (CIS) Interior Decking Federal contract opportunity
Solicitation number
N3225319R0024
Issued by
Department of the Navy Naval Sea Systems Command

View the file

Other files for this federal contract opportunity

Other files attached to Commercial Industrial Services (CIS) Interior Decking, newest first.
File Type Posted
N3225319R0024-Amendment03.pdf PDF
N3225319R0024-Amendment02.pdf PDF
Interior_Decking_SOW_HRMC_RevA.pdf PDF
N3225319R0024-Amendment01.pdf PDF
3._Safety_and_Health_MOA__final_6sept2017.pdf PDF
5._099-010PH_RMMCO_Check-In_v01_2014_updates.pdf PDF
N3225319R0024-Solicitation.pdf PDF
4._Environmental_Guide_for_Ktr_on_Ship_Projects.pdf PDF
2._099-01_thru_07_2010_with_FOUO_pages_removed.pdf PDF
1._Interior_Decking,_Sec_C,_SOW_HRMC.pdf PDF
Interior_Decking,_Sec_C,_SOW_HRMC.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pearl Harbor Naval Shipyard and Intermediate Maintenance Facility CIS Interior Decking Services

N32253-19-R-0024 Q&A Q1 Section 52.211-11 Liquid damages - “Contract to pay the government liquid damages of $ 133,640.00 per calendar day of delay” is this a correct amount? It seems very extreme for this type of contract.

A1 Liquidated damages amount has been removed and the amount will be determined per task order.

Q2 Section C states draft on the top pages, is there a final version?

A2 Yes, the final version has been uploaded without the draft mark.

Q3 Section C 2.16 Interferences - The contractor normally does not have the expertise or qualifications to remove equipment and or advanced interferences, is the contractor required to hire companies for interferences removal or should the ships force be responsible for removal?

A3 Per section 2.16 of the SOW, the Contractor shall be responsible for the removal of all interferences or equipment necessary to accomplish the work specified on this contract and task order.

Q4 Section C.14 Install slip resistant deck covering (peel & stick nonskid): There is not a CLIN for this requirement, is this an oversite or will a CLIN be added?

A4 CLIN 0010 has been added for the installation of slip resistant deck covering.