Q and A Responses.docx

DOCX document 31 KB Posted

Attached to
N4 NEW ACQUISITION SUPPORT Federal contract opportunity
Solicitation number
N3220523Q0076
Issued by
Department of the Navy Military Sealift Command

About this file

This document provides answers to questions from potential offerors for solicitation N3220523Q0076 from the Military Sealift Command. The solicitation requires contractor support for logistics and acquisition activities related to new classes of ships, including monitoring shipbuilding contracts and ensuring required logistics support is available. The contractor will conduct reviews and provide reports and feedback on technical manuals, provisioning packages, configuration drawings, and other deliverables. Key details include: the contractor must review approximately 100 deliverable requirement list packages, 144 logistics packages, 52 provisioning reviews, and 48 configuration drawing reviews per year. Monthly status reports are due the second Monday of each month. Other deliverables are due three days before Navy deadlines. Travel will be required in support of ship deliveries in San Diego, California and Mobile, Alabama. Pricing must be fixed-price. The period of performance is April 24 to December 19, 2023.

View the file

Other files for this federal contract opportunity

Other files attached to N4 NEW ACQUISITION SUPPORT, newest first.
File Type Posted
N3320523Q0076 Amend 0002.pdf PDF
N3220523Q0076_A0001_CSS.pdf PDF
N3320523Q0076_CSS.pdf PDF
A003 2.4, 2.4.1, 2.4.2 ILS Package Review CDRL.pdf PDF
New Ships DD254Signed.pdf PDF
A004 2.5 Provisioning Review CDRL.pdf PDF
A005 2.6 Configuration Drawing Review CDRL.pdf PDF
A001 2.2 Monthly Status Reports CDRL.pdf PDF
A002 2.3 DRL Review CDRL.pdf PDF
A006 2.7 Configuration Technical Manual Review CDRL.pdf PDF
New Acquisition QASP.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N3220523Q0076

QUESTIONS AND ANSWERS #1

The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.

QUESTION #1:

TITLE: Task 2.7 and Deliverable 2.7

For task 2.7 and deliverable 2.7, is it the Government’s intention to have the contractor physically verify installed label plate data with the tech manual for each of the four tech manuals every month?

ANSWER:

“2.7 Configuration Technical Manual Review: The contractor shall review Technical Manuals against the installed equipment information, to ensure the proper technical support is provided by the shipbuilder and OEM. In addition, review the Logistics Support information of all Technical Manuals submitted by the shipbuilder as part of the MSC review team. Provide report of all discrepancies identified including all recommended actions.”

2.7’s intent is for the contractor to compare the delivered Logistics Support Information and Technical Documents against the Configuration Status Accounting data. CSA data is expected to be correct until a physical validation proves it wrong. If in the course of conducting their review, the Contractor finds that a physical validation is required, we can request assistance from the ILS Rep and provide nameplate pictures to support the installed equipment information contained in the system of record. All elements should be in alignment (Dwgs, TMs, RICs, Config). Physical on board evaluations are not required, but not prohibited.

QUESTION #2:

TITLE: Deliverable Table in Section 3

For the deliverable table in section 3, is everything in the table required per ship class or is that the total required for this effort? For example, if deliverable 2.3 is a 100 total DRL reviews, that is much different than 100 per ship class.

ANSWER:

Task
Deliverable
Due Date
Format
Recipient
2.2 Monthly Status Report
Monthly Status Report

Workload: 12/yr (1/mo= 12/yr)

Second Monday of the month. Allow 3 business days for Government review before Monthly meeting
MS Office
COR and SME
2.3 DRL Review
DRL Review:

Comments and recommended edits to MSC N4 for incorporation prior to consolidated comments submitted to NAVSEA. Workload: Approximately 100 Deliverable Requirement List (DRL) packages per month (Approx 100/mo= approx 1200/yr)

NLT 3 working days prior to Deliverable Requirement List (DRL) due date

MS Office Product COR and SME

2.4, 2.4.1 2.4.2 ILS Package Review ILS Package Review:

(1) Comments and recommended edits to MSC N4 for incorporation prior to consolidated comments submitted to NAVSEA. -

(2) Generate Feedback as required to document provisioning discrepancies discovered during review.

Workload: Approximately 6 New and 6 Legacy packages per quarter per ship.

(Approximately 144 pkgs/yr)

(1) & (2) NLT 3 working days prior to Deliverable Requirement List (DRL) due

COR and SME

2.5 Provisioning Review

Provisioning Review - Workload: Approximately 4 per month (Approx 52/yr) Within 2 working days after the completion of each review

COR and SME

2.6 Configuration Drawing Review
Configuration Drawing Review: Workload: Approximately 1 System Drawing per month per post-delivery ship program.

(FY23~ 36/yr; FY24 ~ 48/yr;

FY25 will be dependent upon ship delivery schedule)

Within 2 working days after the completion of each review

2.7 Configuration Technical Manual Review
Configuration Technical Manual Review Workload: Approximately 4 per month

(Approx 48/yr)

Within 2 working days after the completion of each review

QUESTION #3:

TITLE: Travel Costs

Paragraph 1.6 states that temporary work will be required in San Diego, CA; Houma, LA; and Pascagoula, MS. However, Paragraph 5.4.2 (“for representational purposes only”) only anticipates one trip to San Diego, CA. Since travel costs are required to be bid on a Firm Fixed Price (FFP) basis under this RFQ, respectfully request that the Government confirm that no travel other than that specified in Paragraph 5.4.2 is expected within the identified period of performance.

ANSWER:

Travel will be required in support of ship delivery efforts as noted and is dependent upon the DASN Ship Delivery Schedule. Currently, showing delivery of TAO 206 in May 2023 in San Diego, CA & EPF14 in Aug 2023 in Mobile, AL.