STATEMENT_OF_WORK-N23193-5324-4313.pdf

PDF 18 KB Posted

Attached to
CARGO REFRIGERATION REPAIR Federal contract opportunity
Solicitation number
N32205-16-T-7378
Issued by
Department of the Navy Military Sealift Command

About this file

STATEMENT OF WORK DETAILS

View the file

Other files for this federal contract opportunity

Other files attached to CARGO REFRIGERATION REPAIR, newest first.
File Type Posted
SOW_REVISION_2-N23193-5324-4313.pdf PDF
SERVICE_ORDER_REVISION_2-N23193-5324-4313.pdf PDF
STATEMENT_OF_WORK-N23193-5324-4313-REVISION_1.pdf PDF
SERVICE_ORDER-N23193-5324-4313.pdf PDF
IMECO _JOHNSON_CONTROL_JUSTIFICATION.pdf PDF
Combined_Synopsis_Solicitation-N23193-5324-4313.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS ALAN SHEPARD

(T-AKE 3)

AUXILIARY MACHINERY SYSTEMS

19 November 2016 ITEM NO. SO-16-007 Category "A" MSC/EO

STALECTRONIC 2200 WORKSTATION REPAIR

1.0 ABSTRACT:

1.1 This item describes the requirement to repair the Cargo

Refrigeration/Air Conditioning Plant STALECTRONIC 2000 Control and Management System Master Computer Operating Station 2. Test and repair Cargo Refrigeration Units 1 through 3 and Air Conditioning Units 1 through 5.

2.0 REFERENCES:

2.1 References:

2.1.1 T/M T9516-BA-MMC-010; Refrigeration, Marine, Control and Management System, STALECTRONIC 2200

2.1.2 T/M T9516-A8-MMC-010; Refrigeration Plant, Cargo

2.1.3 T/M T9516-BB-MMC-010; Refrigeration Plan, Air

Conditioning

3.0 ITEM LOCATION/DESCRIPTION:

3.1 Location/Quantity

3.1.1 Location: AMR 5-58-01

3.1.2 Quantity: One (1) Cargo Refrigeration Control and

Management System. Three (3) Cargo Refrigeration Units and Five (5) Air Conditioning Units

3.2 Item Description/Manufacturer’s Data.

3.2.1 Bill of Materials: (Contractor Supplied)

Description Part Number QTY

Master Operating Computer #2

N/A 1

3.2.2 Quantities are considered estimates.

4.0 GOVERNMENT-FURNISHED EQUIPMENT/MATERIAL/SERVICES: None

5.0 NOTES:

5.1 This ship contains High Voltage (HV) electrical systems.

The contractor and subcontractors shall obey all posted and verbal instructions regarding safety and exclusion from High Voltage areas. At no time shall a contractor or subcontractor approach, work on, or enter a High Voltage area without proper authorization.

5.2 THE USNS ALAN B. SHEPARD ELECTRICAL COLOR CODING DOES NOT

FOLLOW CONSISTENT COLOR SCHEME. THE SHIP IS KNOWN TO

HAVE CURRENT CARRYING CONDUCTORS COLORED GREEN, BLUE,

BLACK AND WHITE. THE CONTRACTOR SHALL ASSUME ALL

ELECTRICAL CABLES ARE HOT UNTIL TESTED OTHERWISE. THE

CONTRACTOR SHALL TEST ALL ELECTRICAL CABLES TO ENSURE

THEY ARE DEAD PRIOR TO WORKING ON THE ITEM.

5.3 All Electrical cables and components shall be installed

in accordance with the IEEE STD 45 Latest Rev.

6.0 QUALITY ASSURANCE REQUIREMENTS: None Additional

7.0 STATEMENT OF WORK REQUIRED:

7.1 Arrangements/Outfitting: None additional

7.2 Structural: None Additional

7.3 Mechanical/Fluid:

Location: Khalifa Port Abu Dhabi 7-18 March 2016

7.3.1 Upon satisfactory installation of the Master

Operating Control Station #2 perform testing of Cargo Refrigeration Units 1, 2, and 3 and Air Conditioning Units 1, 2, 3, 4, and 5.

7.3.2 Verify Cargo Refrigeration Units 1, 2, and 3 can

properly start/stop and maintain all required parameters using reference 2.1.2.

7.3.3 Verify all units can operate on line when with

other units in operation without locking up.

7.3.4 Adjust unit components to correct out of tolerance

parameters.

7.3.5 Replace faulty components discovered during testing

and adjustment. Ship’s force will provide new components from on board spares.

7.3.6 Verify Air Conditioning Units 1, 2, 3, 4, and 5 can

properly start/stop and maintain all required parameters using reference 2.1.3.

7.3.7 Adjust unit components to correct out of tolerance

parameters.

7.3.8 Replace faulty components discovered during testing

and adjustment. Ship’s force will provide new components from on board spares.

7.4 Electrical: None additional

7.5 Electronics:

7.5.1 Provide a new Master Operating Control Station #2

Computer.

7.5.2 Install all required hardware and load all required

computer software necessary to provide a fully functional Master Operating Station #2.

7.5.3 Ship the Master Operating Control Station computer

to BAT’s Warehouse for follow on shipment to ALAN

SHEAPRD.

7.5.4 Provide the services of one IMECO field support

technician to install and operationally test the Master Operating Station.

7.5.5 Verify the newly installed Master Operating Control

Station communicates and controls Cargo Refrigeration Units 1,2, and 3, and Air Conditioning Plants 1, 2, 3, 4, and 5 using reference 2.1.1.

7.5.6 Demonstrate in the presence of the Chief Engineer, 1ST Engineer, and Refrigeration Engineer functional testing that includes starting, controlling under loaded condition, and stopping Cargo Refrigeration Units 1, 2, and 3, and Air Conditioning Plants 1, 2, 3, 4, and 5 using Master Operating Control Station #2.

7.6 Preparation of Drawings/Documents:

7.6.1 Guidance drawings- None Provided.

7.6.2 Working drawings- None

7.6.3 Redline drawings-None

7.6.4 As-built drawings-None

7.6.5 Service Reports:

7.6.5.1 A detailed service report shall be

provided detailing all service performed, as-found and document components replaced in each unit, document operational test performance and set points, and any other pertinent information required for life cycle documentation.

7.6.5.2 The IMECO Technical Representative shall

orally brief the Chief Engineer of the status of the Cargo Refrigeration and Air Conditioning System prior to departure.

7.7 Inspections and Testing:

7.7.1 After systems have been restored, systems shall be

brought to operating temperatures and pressures in the presence of the ship’s Cargo Engineer. The ship’s First Engineer and MSCREP shall witness the unit in operation when the unit is at operating temperatures and pressures.

7.8 Painting, labeling and Markings: None additional

7.9 Marking: None additional

7.10 Manufacturer’s Representative:

8.0 GENERAL REQUIREMENTS: None additional.

1.0 ABSTRACT:
1.1 This item describes the requirement to repair the Cargo Refrigeration/Air Conditioning Plant STALECTRONIC 2000 Control and Management System Master Computer Operating Station 2. Test and repair Cargo Refrigeration Units 1 through 3 and Air Condit...
2.0 REFERENCES:
2.1 References:
2.1.1 T/M T9516-BA-MMC-010; Refrigeration, Marine, Control and Management System, STALECTRONIC 2200
2.1.2 T/M T9516-A8-MMC-010; Refrigeration Plant, Cargo
2.1.3 T/M T9516-BB-MMC-010; Refrigeration Plan, Air Conditioning
3.0 ITEM LOCATION/DESCRIPTION:
3.1 Location/Quantity
3.1.2 Quantity: One (1) Cargo Refrigeration Control and Management System. Three (3) Cargo Refrigeration Units and Five (5) Air Conditioning Units
3.2 Item Description/Manufacturer’s Data.
5.0 NOTES: