About this file
Questions and Answers 16 through 23
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N32205-16-R-4206-0003.docx | DOCX document | |
| Amendment_N32205-16-R-4209-0001.docx | DOCX document | |
| 16-R-4209_Amend_002.docx | DOCX document | |
| Amendment_0004_RFP-_Q_ _A_8_-_15.docx | DOCX document | |
| RFP-_Q_ _A_5_-_7.docx | DOCX document | |
| RFP-_Q__ _A_1_-_4.docx | DOCX document | |
| Solicitation_N32205-16-R-4209_(Posting).docx | DOCX document | |
| Solicitation_No._N32205-16-R-4209.docx | DOCX document | |
| J_-_Attachments.zip | ZIP file | |
| J_-_6_CDLS.zip | ZIP file | |
| J A_N32205-16-R-4209_Combined_USNS_ARC_ROH-DD_Feb_2017_(Posting).pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N32205-16-R-4209
QUESTIONS AND ANSWERS
The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.
SPECIFICATION ITEM NO.: _0602___________
PARAGRAPH / SECTION / PART NO: 2.1, 2.3, 3.1.2, 3.2.1, 3.2.2, 3.2.3,7.3, 7.3.1, 7.5.1
QUESTION 16:
WI 602 CARGO REFRIGERATION HOLD DECK REPLACEMENT
Need clarification: 3.1.2. states approximately 800 square feet of deck renewal per storeroom, when 7.3.1. states deck plating will be in minimum of three pieces, approximately 5 feet wide and 9 feet long?
Is it your intention for new diamond tread deck plate to replace the temporarily removed grating?
Where is the new diamond tread plate to be installed?
Why is the material in 3.2.1, 3.2.2, & 3.2.3. called out there is no direction to install it?
Why are references 2.1 and 2.3 in this spec when deck covering work is not in the statement of work required?
Are the new deck plates in 7.3 to be painted IAW 7.4?
ANSWER:
The work item has been revised and the installation of the diamond plate steel has been removed. Revised WI 0602 available on request.
SPECIFICATION ITEM NO.: _915___________
PARAGRAPH / SECTION / PART NO: 7.5
QUESTION 17:
Propeller shaft Installation Preparations
Please clarify the following:
1. Do the new GFM Propeller Shafts have GFR already installed?
1. It is our interpretation that the intent of item 915, paragraph 7.5.3 is to align each pair (port and starboard) of propeller and intermediate shafts as follows:
· Verify that the radial difference between flange diameters of the two shafts does not exceed .002”.
GOVERNMENT RESPONSE:
Concur.
· Verify axial alignment between the flanges by ensuring that a .0015” feeler gage cannot be inserted between the flange faces.
GOVERNMENT RESPONSE:
Concur.
· Verify best-fit angular alignment between boltholes on the intermediate and propeller shaft mating flanges, with the #1 bolthole in the intermediate shaft aligned to the propeller shaft #1 keyway.
GOVERNMENT RESPONSE:
Initially identify the legacy propeller shaft position to intermediate shaft when the shaft line is placed in the docking position prior to removal. The new propeller shaft can be placed in an identical position (with respect to the old propeller shaft position) See answer to next question for further definition.
· It is permissible to utilize the original coupling bolts as temporary fasteners during coupling boring and fitting operations by turning down the bodies to have a slight clearance between to the holes in both mating flanges.
GOVERNMENT RESPONSE :
The government is providing new fasteners however would like to reuse any legacy fasteners wherever possible. It is recommended that the bolt holes are measured on the intermediate and new propeller shafts, and the old fasteners are measured to determine how many can be reused. The shafts can be coupled and the ship can establish a new docking position mark on the interior of the ship.
· For the sake of good order we believe the estimated level of effort of eighty (80) hours allotted in paragraph 7.5.5 is not a sufficient amount of machining time for fitting the tapered bolts.
GOVERNMENT RESPONSE.
The contractor can track machine hours and submit a condition report if the 80 hours is depleted.
See answers above.
SPECIFICATION ITEM NO.: _107__________
PARAGRAPH / SECTION / PART NO: 2.1
QUESTION 18:
CARGO TANK LEVEL INDICATION SYSTEM SENSOR INSTALLATION
Drawing 506-NAG-SK-0053 file only contains sheet 21 of 21. Contractor requests that the Government provide the entire drawing.
The government provided sheet 21 of 21 because it is the only relevant sheet to Work Item 107.
The remainder of the drawing deals with the system installation on the ARCTIC, to which NAG is being identified as the installer. If the drawings are required, they can be obtained from NAG LLC.
SPECIFICATION ITEM NO.: _407__________
PARAGRAPH / SECTION / PART NO: 4.2
QUESTION 19:
VDR Installation
The government indicates that it is providing a JRC JYC-1900 VDR. This is a full VDR that requires connections to radars, ECDIS, fire alarm, rudder order & actual, propulstion, WT doors etc. Fitting the JYC-1900 (VDR) rather than the JYC-1950 (SVDR) in place of the existing Transas S-VDR will require all the additional connections and interfaces in order for JRC to issue the APT COC.
S-VDR’s are allowed on non-passenger ships constructed prior to July 1, 2002 as an alternative to a full VDR.
Please indicate the government’s intent as to installation of the full VDR rather than an S-VDR.
As of July 1, 2014, ABS is only accepting VDRs and not S-VDRs.
The installation is for a full VDR. Any known additional connections should be included in the contractors pricing.
SPECIFICATION ITEM NO.: _901__________
PARAGRAPH / SECTION / PART NO: 2.1.1
QUESTION 20:
DRY-DOCKING AND UNDOCKING VESSEL
Contractor requests missing reference 801-6360504.
Drawing shall be provided.
SPECIFICATION ITEM NO.: _Various___________
PARAGRAPH / SECTION / PART NO: Various
QUESTION 21:
CARGO JP5 FUEL VALVE OVERHAUL
Can the government provide a potential source for an authorized OEM Tech Rep there are multiple possible OEMS for the subject valves.
Item 507 Can you please provide the following references:
261-8392997
| 20002298 |
| 300-8392999 |
| 20001700 |
| 541-6360558 |
| 541-8392996 |
| 300-8392998 |
Item 510 Can you please provide reference 2.4 – SSDG Hose List
All references available on request.
SPECIFICATION ITEM NO.: _0913 - 0915___________
PARAGRAPH / SECTION / PART NO: N/A
QUESTION 22:
Main Propulsion Shafting
Please clarify the disposition of the two (2) Propeller shafts removed from the ship. There is no requirement to preserve and package these shafts.
WI 915 Rev A and included reference material available on request.
SPECIFICATION ITEM NO.: _913__________
PARAGRAPH / SECTION / PART NO: 7.15
QUESTION 23:
Main Propulsion Shafting
Paragraph 7.15 directs contractor to transport all shafts to the shop and remove all paint and install the shafts in a lathe. The propeller shafts are being renewed. However, there is no direction as to disposition of the old propeller shafts.
Contractor recommends that the government have contractor refurbish the shafts and ship to government storage so the government will have suitable spare propellers on hand when needed.
In response to previoius question clarifying the disposition of the two (2) Propeller shafts removed from ship, the government revised WI915 to include preservation and packaging of the old propeller shafts for shipment to MSC. MSC currently doesn’t have the required liners to refurbish the propeller shafts. In addition, it is not certain that the refurbishment could be completed in the original POP.
Revised WI 915 Rev A and included reference material available on request.
File details come from the government source that posted it. Updated .