Statement_of_Work_-_Revised_Sept_2.docx

DOCX document 49 KB Posted

Attached to
PONCE SSTG BEARING SERVICE Federal contract opportunity
Solicitation number
N32205-15-T-2273
Issued by
Department of the Navy Military Sealift Command

About this file

Revised SOW with GFM and new dates

View the file

Other files for this federal contract opportunity

Other files attached to PONCE SSTG BEARING SERVICE, newest first.
File Type Posted
COMBINED_SYNOPSIS_SOLICITATION_PONCE_SSTG_CASREP_15-T-2273.doc DOC document
Memorandum_for_Sinplifies_Acquisition_Sole_or_Limited_Source_and_Justification_for_Urgent_Acquisition.PDF PDF
Statement_of_Work.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS PONCE

(AFSBi-15)

TECH REP SERVICES FOR SSTG OVERHAUL Sept 2, 2015

1.0 ABSTRACT

1.1 This work item describes the requirement to provide technical representative services during bearing repair for SSTG 1A.

2.0 REFERENCES:

2.1 NAVSEA Tech Manual 0961-LP-009-0010: Ship Service Turbine Generator

3.0 ITEM LOCATION/DESCRIPTION

3.1 Location/Quantity

3.1.1 Location: MMR1 (7-120-0-E)

3.1.2 Quantity: Turbine generators, 1

4.0 EQUIPMENT/MATERIAL/SERVICES

4.1 Government Furnished Equipment/Material/Services:

4.1.1 Turbine inlet and exhaust bearing sets.

4.2 Contractor Furnished Equipment/Material/Services:

4.2.1 OEM Parts for Bearing Replacement

4.2.1.1 None

Parts required:

Inlet End Complete Bearing
GJ-395 AL U/L
P/N 395-0537, NSN 004660365
QTY 1
Exhaust End Complete Bearing
GJ-395 AN U/L
P/N 395-0538, NSN 004660366
QTY 1

5.0 NOTES: None additional.

6.0 QUALITY ASSURANCE REQUIREMENTS: None additional.

7.0 STATEMENT OF WORK REQUIRED

7.1 Provide the services of one (1) technical representative, acting as the subject matter expert liaison to the MSCREP; to oversee ship force performing work to the SSTGs during the specified performance period. Work to be performed on the SSTGs by the attending technical rep includes:

0. Roll out turbine inlet and outlet bearings for inspection

0. Inspect shaft in way of bearings to be renewed

0. Replace bearings with new bearings provided by the government

7.2 The technical representative shall oversee all work performed by the ship’s crew.

7.3 The technical representative shall oversee operational test of SSTG 1A after bearing repairs are completed and verify proper contact.

7.4 The technical representative shall provide written report of conditions found during critical checkpoints of each generator overhaul. The report shall include recommendations to return the unit to normal operating service.

7.5 The technical representative shall provide a final report detailing all conditions found, parts replaced and readings taken. The report shall include photographs of conditions detailing as found conditions in critical areas of each generator.

201-1

File details come from the government source that posted it. Updated .