About this file
Revised SOW with GFM and new dates
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| COMBINED_SYNOPSIS_SOLICITATION_PONCE_SSTG_CASREP_15-T-2273.doc | DOC document | |
| Memorandum_for_Sinplifies_Acquisition_Sole_or_Limited_Source_and_Justification_for_Urgent_Acquisition.PDF | ||
| Statement_of_Work.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USNS PONCE
(AFSBi-15)
TECH REP SERVICES FOR SSTG OVERHAUL Sept 2, 2015
1.0 ABSTRACT
1.1 This work item describes the requirement to provide technical representative services during bearing repair for SSTG 1A.
2.0 REFERENCES:
2.1 NAVSEA Tech Manual 0961-LP-009-0010: Ship Service Turbine Generator
3.0 ITEM LOCATION/DESCRIPTION
3.1 Location/Quantity
3.1.1 Location: MMR1 (7-120-0-E)
3.1.2 Quantity: Turbine generators, 1
4.0 EQUIPMENT/MATERIAL/SERVICES
4.1 Government Furnished Equipment/Material/Services:
4.1.1 Turbine inlet and exhaust bearing sets.
4.2 Contractor Furnished Equipment/Material/Services:
4.2.1 OEM Parts for Bearing Replacement
4.2.1.1 None
Parts required:
| Inlet End Complete Bearing |
| GJ-395 AL U/L |
| P/N 395-0537, NSN 004660365 |
| QTY 1 |
| Exhaust End Complete Bearing |
| GJ-395 AN U/L |
| P/N 395-0538, NSN 004660366 |
| QTY 1 |
5.0 NOTES: None additional.
6.0 QUALITY ASSURANCE REQUIREMENTS: None additional.
7.0 STATEMENT OF WORK REQUIRED
7.1 Provide the services of one (1) technical representative, acting as the subject matter expert liaison to the MSCREP; to oversee ship force performing work to the SSTGs during the specified performance period. Work to be performed on the SSTGs by the attending technical rep includes:
0. Roll out turbine inlet and outlet bearings for inspection
0. Inspect shaft in way of bearings to be renewed
0. Replace bearings with new bearings provided by the government
7.2 The technical representative shall oversee all work performed by the ship’s crew.
7.3 The technical representative shall oversee operational test of SSTG 1A after bearing repairs are completed and verify proper contact.
7.4 The technical representative shall provide written report of conditions found during critical checkpoints of each generator overhaul. The report shall include recommendations to return the unit to normal operating service.
7.5 The technical representative shall provide a final report detailing all conditions found, parts replaced and readings taken. The report shall include photographs of conditions detailing as found conditions in critical areas of each generator.
201-1