15-T-2000_Amendment_0001.doc
DOC document 47 KB Posted
- Attached to
- Tech Rep Services for Turbine Overhaul Federal contract opportunity
- Solicitation number
- N32205-15-T-2000
About this file
N32205-15-T-2000 Amendment 0001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation_15-T-2000_USS_PONCE.doc | DOC document | |
| J_ _A__SOR_Tech_Sevices_USS_PONCE.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 19-Nov-2014 10:00 AM to 20-Nov-2014 10:00 AM.
The following have been modified:
SOW
USS PONCE
(AFSB-i-15) Technical Representative Services for Turbine Overhaul
Period of Performance December 1, 2014- January 5, 2015
Performance Location: Port KHALIFA ABU DHABI, UAE 1.0
ABSTRACT
1.1 This work item describes the requirement to provide technical representative services for the inspection of the main propulsion #1 and #2 HP and LP turbines. The reduction gear as well as the replacement of the MMR1 and MMR 2 slip rings on all four SSTG’s will also be serviced by a technical representative in this overhaul.
2.0 REFERENCES:
2.1 NAVSEA Tech Manual 0961-LP-009-0010: Ship Service Turbine Generator
2.2 NAVSEA Tech Manual 0941-LP-028-4011: Propulsion Turbines, 12,000 SHP W/CHGS 1-3
2.3 NAVSEA Tech Manual 0942-LP-004-9010: Reduction Gear.
3.0 ITEM LOCATION/DESCRIPTION
3.1 Location/Quantity
3.1.1 Location:
MMR1 (7-120-0-E), MMR2 (7-160-0-E)
3.1.2 Quantity:
Two (2) each main Propulsion LP and HP Turbines and reduction gear. Four (4) Ship Service Turbine Generators.
4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None.
5.0 NOTES:
5.1 Contractor shall work on all equipment as stated in section 7.0 of this request, and as needed to complete all work four (4) days prior to dock trials.
6.0
QUALITY ASSURANCE REQUIREMENTS:
None additional.
7.0
STATEMENT OF WORK REQUIRED
7.1 Provide the services of two (2) technical representative, One to work in MMR#1and the other for MMR#2. These technical representatives will act as the subject matter expert liaison to the MSCREP; to oversee ship force and local contractors performing work to the SSTG slip ring, main propulsion #1 & #2 and reduction gear inspection during the specified performance period. Work to be performed on the SSTGs by local ktrs and overseen by the attending technical rep includes but not excluded to:
a. Removal and reinstallation of SSTG covers and end plates
b. Bearing and Reduction Gear Inspections.
c. Main propulsion #1 and #2 HP and LP turbine inspection
d. Rolling out of bearings for inspection and cleaning
e. Journal inspections and cleaning
f. Roll out inspect and clean thrust shoes
g. Renew labyrinth seals - ( (GFM )/Government Furnish Material)
h. Inspection of Generator Drive Couplings
i. Open and inspect of mechanical overspeed trip assemblies
j. Conduct blueing as required
k. SSTG slip ring replacement
l. Take and record all measurements and readings and submit reports
7.2 The ship’s crew or government provided shipyard trades will carry out the required physical work sequences. The technical representative shall oversee all work performed by local ktrs and ship force, and liaison with the MSCREP.
7.3 The technical representative shall provide written report of conditions found during critical checkpoints of each generator overhaul. The report shall include recommendations to return the unit to normal operating service.
7.4 The technical representative shall provide a final report detailing all conditions found, parts replaced and readings taken. The report shall include photographs of conditions detailing as found conditions in critical areas of each generator.