RFP-RFQ_QandA_1.docx

DOCX document 26 KB Posted

Attached to
USNS RAINIER ROH/DD Federal contract opportunity
Solicitation number
N32205-15-R-2000
Issued by
Department of the Navy Military Sealift Command

About this file

Request for Clarification Question 1 Responses

View the file

Other files for this federal contract opportunity

Other files attached to USNS RAINIER ROH/DD, newest first.
File Type Posted
N32205-15-R-2000-0004.doc DOC document
RFP-RFQ_QandA_2.docx DOCX document
15-R-2000-0003.doc DOC document
J_-_2_Category_A_Items_Rev_1-_RAINIER_ROH-DD.xls XLS spreadsheet
N32205-15-R-2000-0002.doc DOC document
N32205-15-R-2000-0001.doc DOC document
RAINIER_15-R-2000_J-ATTACHMENTS.zip ZIP file
N32205-15-R-2000_USNS_RAINIER_ROH-DD.doc DOC document
DD_Form_1423-1_SWI-011_T-AOE_Sep12.pdf PDF
RAINIER_15-R-2000_-_CDRLs_ZIPPED.zip ZIP file
SYNOPSIS_TEMPLATE_(FAR_5.207)_(V1.1 _6-17-14).docx DOCX document
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N32205-15-R-2000

QUESTIONS AND ANSWERS #1

The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.

1. WI 802 OVERHAUL MISCELLANEOUS FANS AND MOTORS paragraph 7.2 7.2 fan/motor removal . Can you provide the Data for the E02-122-2, S02-111-2, E04-626-2 and two unidentified fan/motor listed in para.7.2. This info is needed to provide pricing for the overhaul. References 2.0 - 2.3 does not provide the necessary info.

ANSWER:

E02-122-2:

Motor Data: ½ HP, 440V, 12A, 1800 RPM. DWG: REL 801621-142

Correct Fan number S02-112-2:

Motor Data: 1/3 HP, 440V, 4.5A, 3600 RPM. DWG: REL 801620-026

E04-626-2 Motor Data: ½ HP, 440V, 12A, 1800 RPM. DWG: REL 801621-142

R5-450-1:

Motor Data: Two speed 6/1.8HP, 440V, 76.7/33.3A, 1800/1200RPM, DWG: REL 801627-550

2. Solicitaion N32205-15-R-2000 Ship Availability Period – Section F-1 Section F-1. It is anticipated that ship will arrive at Contractor’s yard on or about 19 July 2015. All work shall be completed in no more than 30 calendar days from actual start date designated by the Government at time of contract award.

Contractor would like to request an alternate start date of 30 August, 2015 to avoid a dry docking schedule conflict with other MSC vessels.

Should this not be possible due to operational commitments, please advise if any alternate date is possible.

ANSWER:

USNS RAINIER needs to complete her availability and be fully operational by 1 Oct 2015. This requirement does not support an availability start date of 30 August 2015. Section F-1 in the solicitation has a start date of 13 July 2015 not 19 July 2015.

3. WI 505 GROOM AND WEIGHT TEST RHIB DAVITS - The Davits listed in Para. 3.2.1 are not the correct Davits as noted by our vendor,davits are actually s/n 2027 and 2028 not s/n 2122 2123, vendor has also confirmed they have performed the work on the davits in 2014 and s/n 2028 is in poor.

Can you verify the Davits to be tested and groomed are s/n 2027 and 2028?

ANSWER: Correct s/n are 2027 and 2028; revised WI will be posted to ARMDEC Safe and an amendment to the solicitation will be posted to FBO.

4. Contractor request an extension for RFC (Q&A) CLOSING DATE: 4/12/15 @ 1400 EST to 4/17/15. 4/12/15 falls on a Sunday.

ANSWER: RFC (Q&A) Closing Date will be extended to 20 April 2015 @ 1400EST. An amendment to solicitation will be posted to FBO with this change.