About this file

This is a solicitation seeking proposals for the manufacture of burst discs in accordance with specified NAVSEA drawings. Key capabilities required include manufacturing burst discs for gas generators, CO2 containers, and mixing manifolds per the drawings and technical requirements. Proposals are due by the date and time specified on the electronically posted solicitation. Award will be made to a single offeror providing the lowest price technically acceptable proposal. Applicable NAICS code is 332999 with a size standard of 750 employees. This is an unrestricted procurement. Offerors must have a current NIST SP 800-171 assessment of basic confidence level that is no more than three years old, and must be registered in SAM. Drawings and inquiries can be requested from the identified POC.

View the file

Other files for this federal contract opportunity

Other files attached to Burst Disc Assembly, newest first.
File Type Posted
N0025322R0030_0005 Released.pdf PDF
N0025322R0030-0004 Released.pdf PDF
N0025322R0030_0003.pdf PDF
N0025322R0030_0002.pdf PDF
N0025322R0030_0001.pdf PDF
A001 CDRL Burst Disc Assy Test Proc.pdf PDF
A002 CDRL Burst Disc Assy Test Report Final (2).pdf PDF
ATTACHMENT 4_N0025322R0030.pdf PDF
ATTACHMENT 5_N0025322R0030.pdf PDF
ATTACHMENT 6_N0025322R0030.pdf PDF
A003 CDRL Burst Disc Assy Failure Analysis and Corr Act Rpt Final.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 10:00 AM local time 17 Oct 2022

X

A X B X C X D

EX

X

G F 69 - 86

87 - 99 X H 100 - 105 lindsay.k.carrington.civ@us.navy.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

DX-A8C 1 105

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

N00253 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 0 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and lindsay.carrington@navy.mil conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

LINDSAY CARRINGTON 360-315-4549

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 12

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

13 - 25 26 - 28

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

29 - 32 33 - 36

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 37 - 45 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 46 - 47 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIONS AND INSTRUCTIONS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

48 - 67

PART II - CONTRACT CLAUSES

NAVAL UNDERSEA WARFARE CENTER

ATTN: LINDSAY CARRINGTON

LINDSAY.CARRINGTON@NAVY.MIL

610 DOWELL STREET, BLDG 206

KEYPORT WA 98345

360-315-4549

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.5. DATE ISSUED

09 Sep 2022

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

N0025322R0030

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

BURST DISC ASSEMBLY- GAS GENERATOR

FFP

5624005 (53711) Rev E, Burst Disc Assy – Gas Generator. See drawing for details.

NET AMT

0001AA 32 Each

FIRST ARTICLE TESTING

FFP

Burst Disc Assembly - Gas Generator IAW NAVSEA Drawing 5624005 (53711) REV J, and Section C, Statement of Work.

FOB: Destination

PSC CD: 4820

0001AB 20 Each

PRODUCTION LOT SAMPLES

FFP

Burst Disc Assembly - Gas Generator IAW NAVSEA Drawing 5624005 (53711) REV J, and Section C, Statement of Work.

0001AC 100 Each

PRODUCTION UNITS

FFP

Burst Disc Assembly - Gas Generator IAW NAVSEA Drawing 5624005 (53711) REV J, and Section C, Statement of Work.

BURST DISC ASSEMBLY -- CO2 CONTAINER

FP-EPA

5816525 (53711) Rev J, Burst Disc Assembly, Safety-CO2 Container. See drawing for details.

0002AA 32 Each

FIRST ARTICLE TESTING

FP-EPA

Burst Disc Assembly -- CO2 CONTAINER IAW NAVSEA Drawing 5816525 (53711) REV J, and Section C, Statement of Work.

0002AB 20 Each

PRODUCTION LOT SAMPLES

FP-EPA

Burst Disc Assembly -- CO2 CONTAINER IAW NAVSEA Drawing 5816525 (53711) REV J, and Section C, Statement of Work.

0002AC 100 Each

PRODUCTION UNITS

FP-EPA

Burst Disc Assembly -- CO2 CONTAINER IAW NAVSEA Drawing 5816525 (53711) REV J, and Section C, Statement of Work.

BURST DISC ASSEMBLY -- MIXING MANIFOLD

FFP

5816567 (53711) Rev E, Burst Disc Assy – Mixing Manifold. See drawing for details.

0003AA 32 Each

FIRST ARTICLE TESTING

FFP

Burst Disc Assembly -- Mixing Manifold IAW NAVSEA Drawing 5816567(53711) REV E, and Section C, Statement of Work.

0003AB 20 Each

PRODUCTION LOT SAMPLES

FFP

Burst Disc Assembly -- Mixing Manifold IAW NAVSEA Drawing 5816567 (53711) REV E, and Section C, Statement of Work.

0003AC 100 Each

PRODUCTION UNITS

FFP

Burst Disc Assembly -- Mixing Manifold IAW NAVSEA Drawing 5816567 (53711) REV E, and Section C, Statement of Work.

CONTRACT DATA REQUIREMENTS LIST (CDRL)

FFP

Exhibit A001, Test Procedures Exhibit A002, Test Report Exhibit A003, Failure Analysis and Corrective Action Report Note: CDRL A001 applies to Test and Qualification CLINS only. CDRLs A002 and A003 apply to all Base and Option quantities.

OPTION BURST DISC ASSEMBLY, GAS GENERATOR

5624005 (53711) Rev E, Burst Disc Assy – Gas Generator. See drawing for details.

1001AB 20 Each

OPTION PRODUCTION LOT SAMPLES

FFP

Burst Disc Assy – Gas Generator IAW NAVSEA drawing 5624005 (53711) Rev E, and Section C, Statement of Work.

1001AC 100 Each

OPTION PRODUCTION UNITS

FFP

Burst Disc Assy – Gas Generator IAW NAVSEA drawing 5624005 (53711) Rev E, and Section C, Statement of Work.

OPTION 5816525 (53711) REV J, CO2 CONTAINER

FFP

5816525 (53711) Rev J, Burst Disc Assembly, Safety-CO2 Container. See drawing for details.

1002AB 20 Each

PRODUCTION LOT SAMPLES

FP-EPA

Burst Disc Assembly - CO2 container IAW NAVSEA Drawing 5816525 (53711) REV J, and Section C, Statement of Work..

1002AC 100 Each

PRODUCTION UNITS

FP-EPA

Burst Disc Assembly - CO2 container IAW NAVSEA Drawing 5816525 (53711) REV J, and Section C, Statement of Work..

OPTION BURST DISC ASSEMBLY, MIXING MANIFOLD

5816567 (53711) Rev E, Burst Disc Assy – Mixing Manifold

1003AB 20 Each

OPTION PRODUCTION LOT SAMPLES

FFP

Burst Disc Assy – Mixing Manifold IAW NAVSEA drawing 5816567 (53711) Rev E, and Section C, Statement of Work.

1003AC 100 Each

OPTION PRODUCTION UNITS

FFP

Burst Disc Assy – Mixing Manifold IAW NAVSEA drawing 5816567 (53711) Rev E, and Section C, Statement of Work.

OPTION CONTRACT DATA REQUIREMENTS LIST (CDRL)

FFP

Exhibit A001, Test Procedures Exhibit A002, Test Report Exhibit A003, Failure Analysis and Corrective Action Report Note: CDRL A001 applies to Test and Qualification CLINS only. CDRLs A002 and A003 apply to all Base and Option quantities.

Section C - Descriptions and Specifications

STATEMENT OF WORK

STATEMENT OF WORK

BURST DISC ASSEMBLY

1. SCOPE

1.1. Manufacture three separate Burst Discs for the MK54 Lightweight Torpedo, in accordance with (IAW) all drawings and specifications referenced herein.

1.2. Testing and Non-recurring expenses (NRE) shall be included in First Article Test (FAT) Unit Pricing.

1.3. Technical Point of Contacts (POC) for this contract are Kristine Chavez (kristine.p.chavez.civ@us.navy.mil (360-315-2251) and Anthony Luchini (anthony.r.luchini.civ@us.navy.mil 360-315-6766).

2. REQUIREMENTS

2.1. Technical Capabilities

2.1.1. The Vendor shall manufacture IAW listed NAVSEA Drawings, associated drawing and all requirements listed in, standards, specifications and references noted in each drawing.

5624005 (53711) Rev E, Burst Disc Assy – Gas Generator

5816525 (53711) Rev J, Burst Disc Assembly, Safety-CO2 Container

5816567 (53711) Rev E, Burst Disc Assy – Mixing Manifold

TR5624413 (53711) Rev G, Technical Requirements for Verification and Annotated and Unannotated Characteristics

2.1.2. Exception to the drawings – 5624005, 5816525, and 5816567; Notes 1, 2 and the Approved Source of Supply block is not applicable.

2.2. Testing Capabilities

2.2.1. The Vendor shall have the capability to perform testing on their facility or through subcontracting.

2.2.1.1. Should the Vendor need to perform testing at Government’s facility, Vendor shall form a work for private party agreement (WFPPA) with the Government prior to Sample Testing.

2.2.1.2. Work for Private Party Agreement (WFPPA). Performance of this contract by the Contractor does not preclude the Contractor from entering into future WFPPA with NUWC Division, Keyport. Work conducted under individual WFPPA shall not be issued as a technical instruction under any resultant contract. Contractors are allowed to contract with NUWC Division, Keyport for test facilities and test personnel support. The Government shall not be responsible for conflicts, delays, or disruptions to any work performed by the Contractor under this contract due to use of WFPPAs. The Contractor is not limited to

WFPPA with NUWC Division, Keyport and may make agreements with other government organizations or commercial entities for support.

2.3. First Article Testing

2.3.1. Test Procedure (CDRL A001)

2.3.1.1. The Test Procedure for first article testing and periodic sample testing shall be submitted 30 days after contract award. The government shall review the Test Procedure within 30 days.

2.3.1.2. The Test Procedure shall include a minimum of the test and inspection requirements identified in note 14 and 15 of the specified drawings.

2.3.2. Testing Requirements

2.3.2.1. Vendor shall manufacture a sample size of thirty-two (32) First Article units IAW note 14 of specified drawings.

2.3.2.2. Each First Article shall be subjected to the various testing as noted in the drawings.

2.3.2.3. The government shall be notified 30 days prior to testing, in order to be present to witness test and inspection at the facility where the testing is performed.

2.3.3. Test Report (CDRL A002)

2.3.3.1. Upon completion of First Article testing, a Test Report shall be submitted to the government for quality and conformance with drawing specifications. (CDRL A002)

2.3.3.2. The Test Report shall be IAW with the approved Test Procedure and shall be provided within 210 days after contract award.

2.3.3.3. The government shall review the Test Report within 30 days to determine if the vendor is qualified to proceed with the production manufacturing of the Burst Disc Assembly.

2.4. Manufacturing Requirements

2.4.1. Sample Units

2.4.1.1. Upon approval of the Test Report (section 2.3.3), and notification to proceed from the contracting officer, the Vendor shall manufacture the Burst Disc Assembly production units.

2.4.1.2. A total of twenty (20) units shall be chosen at random from each production lot for periodic sample testing IAW ANSI/ASQC Z1.4 (via TR5624413) and note 15 of specified drawings.

Samples shall be randomly selected by DCMA (Defense Contract Management Agency) from the manufactured lot.

2.4.1.3. A Test Report (CDRL A002) for each lot delivery shall be submitted within 210 days after First Article acceptance or after option exercise. The government reserves the right to witness testing at the test facility and shall be notified 30 days prior to testing commencement.

2.4.2. Production Unit Acceptance

2.4.2.1. Government representative will review the test report to ensure quality and conformance requirements are met based on drawing specifications, CDRL test data results, and statement of work.

2.4.2.2. Government shall have up to 30 days for end user inspection and acceptance. The Government reserves the right to inspect 100% of production units to validate compliance with Test Report data.

2.4.2.3. Any unit that does not pass inspection will result in rejection of entire lot and will be returned to the manufacturer for failure analysis and resolution IAW ANSI/ASQC Z1.4 (via TR5624413). A proposal for resolution requirements, test reports, and an updated delivery schedule should be submitted to the Government for review and concurrence within 30 days. (See CDRL A003)

2.4.3. No substitution of materials is authorized without prior government approval.

2.4.4. Form DD1694 shall be submitted to the technical POC if the vendor requires a request for variance or waiver.

2.4.5. Marking: Each unit will be electrolytic etched IAW MIL-STD-130, with all requirements noted in paragraph 12 of applicable NAVSEA drawing(s) 5816525, 5624005, 5816567.

2.4.6. Packaging label shall include the contract number, Cage Code and name of manufacturer, NSN, and PN.

2.5. Conference

2.5.1. Post award conference will be set up within 10 days after award.

2.6. Data and Reporting

2.6.1. Vendor shall provide a Test Procedure for first article and periodic sample testing referenced in section 2.3.1. (See CDRL A001)

2.6.2. Vendor shall provide a Test Report for the first article requirement referenced in section 2.3.3 and

2.4.2.1 and with each lot delivery. (See CDRL A002)

2.6.3. Vendor shall provide a Failure Analysis and Corrective Action Report referenced in section

2.4.2.3 and 2.7.3 as required. (See CDRL A003)

2.7. Delivery Schedule

2.7.1. Test Procedure (CDRL A001) for first article and periodic sample testing to be provided to government within 30 days after award date.

2.7.2. Test Report (CDRL A002) for first article testing to be provided 210 days after acceptance of Test Procedure.

2.7.3. Lot Deliveries and test report (CDRL A002) to be 210 days after acceptance of first articles or option exercise.

2.7.4. Early and partial deliveries are acceptable.

2.7.5. Vendor shall notify Technical POC with tracking numbers of each shipment.

3. CONTRACT ADMINISTRATION

3.1. Post-award meetings shall be conducted as needed for the term of the contract.

3.1.1. The initial post-award meeting will occur within 10 days after award of the contract.

3.2. The government reserves the right to witness specific test events at the facility where the testing is performed, and requests notification of testing events.

3.3. Contractor Site Survey can be requested by the Government at any time.

CLAUSES INCORPORATED BY FULL TEXT

C-202-H001 ADDITIONAL DEFINITIONS–BASIC (NAVSEA) (OCT 2018)

(a) Department - means the Department of the Navy.

(b) Commander, Naval Sea Systems Command - means the Commander of the Naval Sea Systems Command of the Department of the Navy or his duly appointed successor.

(c) References to The Federal Acquisition Regulation (FAR) - All references to the FAR in this contract shall be deemed to also reference the appropriate sections of the Defense FAR Supplement (DFARS), unless clearly indicated otherwise.

(d) National Stock Numbers - Whenever the term Federal Item Identification Number and its acronym FIIN or the term Federal Stock Number and its acronym FSN appear in the contract, order or their cited specifications and standards, the terms and acronyms shall be interpreted as National Item Identification Number (NIIN) and National Stock Number (NSN) respectively which shall be defined as follows:

(1) National Item Identification Number (NIIN). The number assigned to each approved Item Identification under the Federal Cataloging Program. It consists of nine numeric characters, the first two of which are the National Codification Bureau (NCB) Code. The remaining positions consist of a seven digit non-significant number.

(2) National Stock Number (NSN). The National Stock Number (NSN) for an item of supply consists of the applicable four-position Federal Supply Class (FSC) plus the applicable nine-position NIIN assigned to the item of supply.

(End of text)

C-204-H001 USE OF NAVY SUPPORT CONTRACTORS FOR OFFICIAL CONTRACT FILES (NAVSEA)

(OCT 2018)

(a) NAVSEA may use a file room management support contractor, hereinafter referred to as "the support contractor", to manage its file room, in which all official contract files, including the official file supporting this procurement, are retained. These official files may contain information that is considered a trade secret, proprietary, business sensitive or otherwise protected pursuant to law or regulation, hereinafter referred to as “protected information”. File room management services consist of any of the following: secretarial or clerical support; data entry; document reproduction, scanning, imaging, or destruction; operation, management, or maintenance of paper-based or electronic mail rooms, file rooms, or libraries; and supervision in connection with functions listed herein.

(b) The cognizant Contracting Officer will ensure that any NAVSEA contract under which these file room management services are acquired will contain a requirement that:

(1) The support contractor not disclose any information;

(2) Individual employees are to be instructed by the support contractor regarding the sensitivity of the official contract files;

(3) The support contractor performing these services be barred from providing any other supplies and/or services, or competing to do so, to NAVSEA for the period of performance of its contract and for an additional three years thereafter unless otherwise provided by law or regulation; and,

(4) In addition to any other rights the contractor may have, it is a third party beneficiary who has the right of direct action against the support contractor, or any person to whom the support contractor has released or disclosed protected information, for the unauthorized duplication, release, or disclosure of such protected information.

(c) Execution of this contract by the contractor is considered consent to NAVSEA's permitting access to any information, irrespective of restrictive markings or the nature of the information submitted, by its file room management support contractor for the limited purpose of executing its file room support contract responsibilities.

(d) NAVSEA may, without further notice, enter into contracts with other contractors for these services. Contractors should enter into separate non-disclosure agreements with the file room contractor. Contact the Procuring Contracting Officer for contractor specifics. However, any such agreement will not be considered a prerequisite before information submitted is stored in the file room or otherwise encumber the government.

C-209-H001 FIRST ARTICLE (CONTRACTOR TESTING) (NAVSEA) (OCT 2018)

(a) The First Article shall conform in every respect to the requirements of this contract. The First Article shall be manufactured with tools, materials, and methods which are the same as the tools, material and methods which will be used to manufacture the production units. All items delivered under the contract shall be manufactured under the same conditions and quality established by the First Article. Any changes to tools, material, or methods after the first article approval shall be documented by the contractor and approved by the Contracting Officer before they are used.

(b) The Contractor shall make a record of all data obtained during such tests in a form similar to the guidance provided in MIL-HDBK-831A.

(c) Pursuant to paragraph (e) of the clause entitled "First Article Approval--Contractor Testing" (FAR 52.209-3), the First Article shall not be delivered as part of the production quantity.

C-209-H003 WAIVER OF FIRST ARTICLE REQUIREMENTS (NAVSEA) (OCT 2018)

If the First Article is waived by the Government, the Contractor shall deliver supplies that are identical or substantially identical to those previously accepted by the Government under the following contract(s):

(Offeror to fill in contract number(s), as applicable. See Section M)

(End of Text)

C-211-H016 SPECIFICATIONS AND STANDARDS (NAVSEA) (OCT 2018)

(a) Definitions.

(i) A "zero-tier reference" is a specification, standard, or drawing that is cited in the contract (including its attachments).

(ii) A "first-tier reference" is either: (1) a specification, standard, or drawing cited in a zero-tier reference, or (2) a specification cited in a first-tier drawing.

(b) Requirements. All zero-tier and first-tier references, as defined above, are mandatory for use. All lower tier references shall be used for guidance only unless specifically identified below.

None

C-211-H017 UPDATING SPECIFICATIONS AND STANDARDS (NAVSEA) (DEC 2018)

The contractor may request that this contract be updated to include the current version of the applicable specification or standard if the update does not affect the form, fit or function of any deliverable item or increase the cost/price of the item to the Government. The contractor should submit update requests to the Procuring Contracting Officer with copies to the Administrative Contracting Officer and cognizant program office representative for approval. The contractor shall perform the contract in accordance with the existing specifications and standards until notified of approval/disapproval of its request to update by the Procuring Contracting Officer. Any approved alternate specifications or standards will be incorporated into the contract.

C-211-H018 APPROVAL BY THE GOVERNMENT (NAVSEA) (JAN 2019)

Approval by the Government as required under this contract and applicable specifications shall not relieve the Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.

C-215-H002 CONTRACTOR PROPOSAL (NAVSEA) (OCT 2018)

(a) Performance of this contract by the Contractor shall be conducted and performed in accordance with the detailed obligations to which the Contractor committed itself in Proposal * dated * in response to Solicitation No.

N0025322R0030.

(b) The technical volume(s) of the Contractor's proposal is(are) hereby incorporated by reference and made subject to the "Order of Precedence" (FAR 52.215-8) clause of this contract. Under the "Order of Precedence" clause, the technical volume(s) of the Contractor's proposal referenced herein is (are) hereby designated as item (f) of the clause, following "the specifications" in the order of precedence.

* To be identified upon contract award.

C-227-H006 DATA REQUIREMENTS (NAVSEA) (OCT 2018)

The data to be furnished hereunder shall be prepared in accordance with the Contract Data Requirements List, DD Form 1423, Exhibit(s) A001, A002, and A003, attached hereto.

C-233-H001 DOCUMENTATION OF REQUESTS FOR EQUITABLE ADJUSTMENT--BASIC (NAVSEA) (OCT 2018)

(a) For the purposes of this special contract requirement, the term "change" includes not only a change that is made pursuant to a written order designated as a "change order" but also (1) an engineering change proposed by the Government or by the Contractor and (2) any act or omission to act on the part of the Government in respect of which a request is made for equitable adjustment.

(b) Whenever the Contractor requests or proposes an equitable adjustment of $100,000 or more per vessel in respect to a change made pursuant to a written order designated as a "change order" or in respect to a proposed engineering change and whenever the Contractor requests an equitable adjustment in any amount in respect to any other act or omission to act on the part of the Government, the proposal supporting such request shall contain the following information for each individual item or element of the request:

(1) A description (i) of the work required by the contract before the change, which has been deleted by the change, and (ii) of the work deleted by the change which already has been completed. The description is to include a list of components, equipment, and other identifiable property involved. Also, the status of manufacture, procurement, or installation of such property is to be indicated. Separate description is to be furnished for design and production work.

Items of raw material, purchased parts, components and other identifiable hardware, which are made excess by the change and which are not to be retained by the Contractor, are to be listed for later disposition;

(2) Description of work necessary to undo work already completed which has been deleted by the change;

(3) Description of work not required by the terms hereof before the change, which is substituted or added by the change. A list of components and equipment (not bulk materials or items) involved should be included. Separate descriptions are to be furnished for design work and production work;

(4) Description of interference and inefficiencies in performing the change;

(5) Description of each element of disruption and exactly how work has been, or will be disrupted:

(i) The calendar period of time during which disruption occurred, or will occur;

(ii) Area(s) aboard the vessel where disruption occurred, or will occur;

(iii) Trade(s) disrupted, with a breakdown of manhours for each trade;

(iv) Scheduling of trades before, during, and after period of disruption;

(v) Description of measures taken to lessen the disruptive effect of the change;

(6) Delay in delivery attributable solely to the change;

(7) Other work attributable to the change;

(8) Supplementing the foregoing, a narrative statement of the direct "causal" relationship between any alleged Government act or omission and the claimed consequences therefor, cross-referenced to the detailed information provided as required above; and

(9) A statement setting forth a comparative enumeration of the amounts "budgeted" for the cost elements, including the material costs, labor hours and pertinent indirect costs, estimated by the Contractor in preparing its initial and ultimate proposal(s) for this contract, and the amounts claimed to have been incurred and/or projected to be incurred corresponding to each such "budgeted cost" elements.

(c) Each proposal in excess of $100,000 submitted in support of a claim for equitable adjustment under any requirement of this contract shall, in addition to the information required by paragraph (b) hereof, contain such information as the Contracting Officer may require with respect to each individual claim item.

(d) It is recognized that individual claims for equitable adjustment may not include all of the factors listed in paragraph

(b) above. Accordingly, the Contractor is required to set forth in its proposal information only with respect to those factors which are comprehended in the individual claim for equitable adjustment. In any event, the information furnished hereunder shall be in sufficient detail to permit the Contracting Officer to cross-reference the claimed increased costs, or delay in delivery, or both, as appropriate, submitted pursuant to paragraph (c) of this requirement, with the information submitted pursuant to paragraph (b) hereof.

C-242-H001 EXPEDITING CONTRACT CLOSEOUT (NAVSEA) (OCT 2018)

(a) As part of the negotiated fixed price or total estimated amount of this contract, both the Government and the Contractor have agreed to waive any entitlement that otherwise might accrue to either party in any residual dollar amount of $1,000 or less at the time of final contract closeout. The term "residual dollar amount" shall include all money that would otherwise be owed to either party at the end of the contract, except that, amounts connected in any way with taxation, allegations of fraud and/or antitrust violations shall be excluded. For purposes of determining residual dollar amounts, offsets of money owed by one party against money that would otherwise be paid by that party may be considered to the extent permitted by law.

(b) This agreement to waive entitlement to residual dollar amounts has been considered by both parties. It is agreed that the administrative costs for either party associated with collecting such small dollar amounts could exceed the amount to be recovered.

C-242-H002 POST AWARD MEETING (NAVSEA) (OCT 2018)

(a) A post-award meeting with the successful offeror will be conducted within 30 calendar days after award of the contract. The meeting will be held at the address below:

Conference Call-In Number / Participant Code: Provided to Contractor after contract award

(b) The contractor will be given 10 working days notice prior to the date of the meeting by the Contracting Officer.

(c) The requirement for a post-award meeting shall in no event constitute grounds for excusable delay by the contractor in performance of any provisions in the contract.

(d) The post-award meeting will include, but is not limited to, the establishment of work level points of contact, determining the administration strategy, roles and responsibilities, and ensure prompt payment and close out.

Specific topics shall be mutually agreed to prior to the meeting.

C-243-H003 CONFIGURATION MANAGEMENT (NAVSEA) (JAN 2019)

(a) Baseline Definition - All contractual documentation in effect at the time of contract award shall constitute the Contract Baseline, which shall be considered incorporated in the baseline documentation.

(b) General Requirement - (1) The Contractor shall maintain a Configuration Control Program to assure that all detail level work being performed under this contract is in compliance with appropriate baseline documentation.

The Contractor shall prepare a Configuration Management Plan in accordance with the requirements of the contract.

If required, the Contractor’s Configuration Management Plan shall be submitted through the appropriate Contract Data Requirements List (CDRL) for approval by the Government.

(2) Whenever a situation arises wherein the Contractor cannot comply with a baseline document, or whenever intent of such documentation is significantly changed by detail level documentation, the Contractor shall submit change documents to modify the baseline to resolve the conflict or to allow non-compliance. Whenever the cost of implementing a proposed change is less than the threshold requiring certified cost or pricing data, the Contractor shall provide such detail of related costs as to allow the Government to determine an equitable adjustment for the change document submission. Whenever the contract cost changes by an amount greater than the threshold requiring certified cost or pricing data, the Contractor shall complete such cost and pricing data as the Contracting Officer shall require detailing all related costs, and attach it to the change document. Requirements for cost and pricing data shall be determined by the gross amount of the change unless otherwise directed by the Contracting Officer. Change documentation shall be submitted to the Contracting Officer in accordance with the appropriate CDRL, and as described in paragraphs (c) through (f) below.

(c) Engineering Change Proposals (ECPs) - ECPs shall be prepared in accordance with the approved configuration management plan and the requirements of the contract. DI-SESS-80639D approved 7 April 2015, EIA-649-1 of Nov 2014 and MIL-HDBK-61A of 7 Feb 2001 apply. An ECP shall be submitted whenever the detail level physical configuration, material quality, operational or functional performance of equipment or installed systems will not be in compliance with baseline design-related documents (Specifications, Contract Drawings, etc.), and a change to the baseline document is considered an appropriate means of resolving a design-related issue. The contractor shall develop documentation in sufficient detail to enable Government review and evaluation of the merits of the proposed change, including cost and scheduling impact, ship class impact if applicable, and consequences if disapproved. List all existing drawings and technical manuals impacted by the change, including a brief narrative explanation of needed changes to incorporate the ECP if approved. Provide weight and moment data incidental to the change, if applicable. The Contractor shall also prepare applicable baseline document insert sheets, with specific word changes or proposed re-write, to facilitate baseline documentation changes.

(d) Non-Engineering Change Proposals (NECPs) – An NECP shall be submitted whenever necessary to document administrative, procedural, scheduling, or documentation changes that do not directly impact the physical configuration of the equipment. The NECP shall explain the nature of the problem, identify the applicable baseline document (i.e., Contract Data Requirement List (CDRL), Contract Clause, etc.) and provide a detailed explanation justifying the proposed course of action desired to resolve the problem. Insert sheets for applicable documents shall also be attached to facilitate change action in the event the NECP is approved.

(e) Deviations/Waivers - In the event that a baseline design-related document requirement cannot be met, and a change to the baseline document is considered inappropriate, the Contractor shall submit a Request for Variance.

The explanation of "Need for Deviation/Waiver" in the DD1694 shall provide detailed justification and consequences of approval, to include technical details explaining the degree of non-compliance and the effect on ship equipment or system operation.

(f) Equitable Adjustments for Change Documentation Preparations - For its effort expended in preparing ECPs, NECPs, and Deviations/Waivers, the Contractor shall receive equitable adjustment under the following circumstances:

(1) In the event the Contractor, on its own initiative, and without written request from the Contracting Officer, develops a change document that is later disapproved by the Government, the Contractor shall bear the cost of this effort.

(2) To avoid such loss, and at its option, the Contractor may submit a "preliminary" document that outlines intent, but without detailed supporting documentation and request the Contracting Officer's approval for expenditure of effort to complete the detailed supporting documentation. In the event the Contracting Officer denies this request, the Contractor will bear the cost of development of the "preliminary" document, and shall make no further effort to complete detailed supporting documentation.

(3) In the event the Contracting Officer approves the Contractor's request to develop supporting documentation, the Contractor shall be equitably compensated for its effort for both the "preliminary" and "final" documentation, regardless of whether or not the change document is later approved.

(4) In the event the Contracting Officer requests in writing that the Contractor develop change documentation, the effort expended by the Contractor in developing such documentation shall be subject to equitable adjustment, regardless of whether or not the change document is later approved.

(5) In the event the Contractor, on its own initiative, and without written request from the Government, develops a change document that is later approved by the Contracting Officer, the cost of developing such documentation shall be subject to equitable adjustment.

(6) Failure to agree to such equitable adjustment in contract price shall constitute a dispute, and shall be adjudicated in accordance with the requirements of the clause entitled "Disputes" (FAR 52.233-1).

(g) Any cost reduction proposal submitted pursuant to the clause entitled "Value Engineering" (FAR 52.248-1) shall be submitted as a Value Engineering Change Proposal (VECP). The Contractor shall follow the VECP preparation requirements of FAR 52.248-1(c) and any additional guidance provided by the Contracting Officer.

C-245-H005 INFORMATION AND DATA FURNISHED BY THE GOVERNMENT--ALTERNATE I

(NAVSEA) (MAY 2019)

(a) Contract Specifications, Drawings and Data. The Government will furnish, if not included as an attachment to the contract, any unique contract specifications or other design or alteration data cited or referenced in Section C.

(b) Government Furnished Information (GFI). GFI is defined as that information essential for the installation, test, operation, and interface support of all Government Furnished Material identified in an attachment in Section J. The Government shall furnish only the GFI identified in an attachment in Section J. The GFI furnished to the contractor need not be in any particular format. Further, the Government reserves the right to revise the listing of GFI as follows:

(1) The Contracting Officer may at any time by written order:

(i) delete, supersede, or revise, in whole or in part, data identified in an attachment in Section J; or

(ii) add items of data or information to the attachment identified in Section J; or

(iii) establish or revise due dates for items of data or information in the attachment identified in Section J.

(2) If any action taken by the Contracting Officer pursuant to subparagraph (1) immediately above causes an increase or decrease in the costs of, or the time required for, performance of any part of the work under this contract, the contractor may be entitled to an equitable adjustment in the contract amount and delivery schedule in accordance with the procedures provided for in the "CHANGES" clause of this contract.

(c) Except for the Government information and data specified by paragraphs (a) and (b) above, the Government will not be obligated to furnish the Contractor any specification, standard, drawing, technical documentation, or other publication, notwithstanding anything to the contrary in the contract specifications, the GFI identified in an attachment in Section J, the clause of this contract entitled "Government Property" (FAR 52.245-1) or "Government Property Installation Operation Services" (FAR 52.245-2), as applicable, or any other term or condition of this contract. Such referenced documentation may be obtained:

(1) From the ASSIST database via the internet at https://assist.dla.mil/online/start/; or

(2) By submitting a request to the

Department of Defense Single Stock Point (DoDSSP)

Building 4, Section D

700 Robbins Avenue Philadelphia, Pennsylvania 19111-5094 Telephone (215) 697-6396 Facsimile (215) 697-9398.

Commercial specifications and standards, which may be referenced in the contract specification or any sub-tier specification or standard, are not available from Government sources and should be obtained from the publishers.

C-246-H002 GOVERNMENT USE OF CONTRACTOR’S INSPECTION EQUIPMENT (NAVSEA) (OCT 2018)

The contractor's gages, measuring, and testing devices shall be made available to the Government when required to determine contractor conformance with contract requirements. If conditions warrant, the contractor’s personnel shall be made available for operation of such devices and for verification of their accuracy and condition.

C-247-H001 PERMITS AND RESPONSIBILITIES (NAVSEA) (DEC 2018)

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits for complying with any applicable Federal, State, and Municipal laws, codes, and regulations for shipping and transportation including, but not limited to, any movement over public highways of overweight/over dimensional materials.

Section D - Packaging and Marking

D-211-H001 PACKAGING OF DATA (NAVSEA) (FEB 2022)

Data to be delivered by Integrated Digital Environment (IDE) or other electronic media shall be as specified in the contract.

All unclassified data to be shipped shall be prepared for shipment in accordance with best commercial practice.

Classified reports, data, and documentation shall be prepared for shipment in accordance with National Industrial Security Program Operating Manual (NISPOM), 32 CFR Part 117.

D-211-H005 IDENTIFICATION MARKING OF PARTS – ALTERNATE I (NAVSEA) (OCT 2018)

(a) For all parts not subject to the marking requirements in DFARS 252.211-7003 – Item Unique Identification and Valuation, marking shall be accomplished in accordance with the following:

(1) Parts not manufactured to Government specifications shall be marked in accordance with generally accepted commercial practice.

(2) Parts manufactured to Government specifications shall be marked as follows:

(i) Electrical Parts - that is, all parts in electrical equipment and electrical parts when used in equipment which are not electrical in nature (e.g., electric controls and motors in a hydraulic system) - shall be identified and marked in accordance with MIL-STD-1285D(2) dated 22 June 2018, or, where MIL-STD-1285D(2) does not cover such a part, in accordance with MIL-STD-130N(1) dated 16 November 2012. Requirements of MIL-STD-1686C dated 25 October 1995 for Electrostatic Discharge Control shall be addressed.

(ii) Electronic Parts - that is, all parts in electronic equipment and electronic parts when used in equipment which are not electronic in nature (e.g., electronic fuel controls in some engines) - shall be identified and marked in accordance with Requirement 67 of MIL-HDBK-454B dated 15 April 2007 with Notice 1 dated 12 December 2012. Requirements of MIL-STD-1686C for Electrostatic Discharge Control shall be addressed.

(iii) Parts other than electrical or electronic parts (as described above) shall be identified and marked in accordance with MIL-STD-130N(1).

(b) In cases where parts are so small as not to permit identification marking as provided above, such parts shall be appropriately coded so as to permit ready identification.

D-247-H001 ADDITIONAL MARKING REQUIREMENTS FOR FMS ITEMS (NAVSEA) (OCT 2018)

(a) The following identifying marks shall appear on the outside of each box, parcel and/or crate and all shipping papers included in each shipment:

NAVY

FMS CASE _________________________________________________________

REQUISITION NO. ___________________________________________________

ITEM DESCRIPTION _____________________________________________

If a consolidated shipment of several items in one container is forwarded, add to the above information

"CONSOLIDATED SHIPMENT, CONTAINS ____ ITEMS".

(b) The inscription "UNITED STATES OF AMERICA" shall be affixed in a suitable size indelible stencil, label or printed form on all external shipping containers or the exterior surface of uncrated items.

(c) All invoices, correspondence, reports and other documents shall be identified with the appropriate FMS case designator, requisition number(s), and item description(s).

D-247-H002 PACKAGING OF SUPPLIES—BASIC (NAVSEA) (DEC 2020)

Item(s) The supplies furnished hereunder shall be packaged in accordance with ASTM-D-3951-18, Standard Practice for Commercial Packing.

D-247-H003 PACKAGING OF SUPPLIES—ALTERNATE I (NAVSEA) (AUG 2019)

Item(s) The supplies furnished hereunder shall be packaged in accordance with MIL-STD-2073-1E with Change 4 dated 22 April 2019.

D-247-H004 MARKING AND PACKING LIST(S) – BASIC (NAVSEA) (FEB 2022)

(a) Marking. Shipments, shipping containers and palletized unit loads shall be marked in accordance with ASTM- D-3951-18 approved 1 May 2018, Standard Practice for Commercial Packing.

(b) Packing List(s). A packing list (DD Form 250 Material Inspection and Receiving Report may be used) identifying the contents of each shipment, shipping container or palletized unit load shall be provided by the Contractor with each shipment. When a contract line item identified under a single stock number includes an assortment of related items such as kit or set components, detached parts or accessories, installation hardware or material, the packing list(s) shall identify the assorted items. Where assortment of related items is included in the shipping container, a packing list identifying the contents shall be furnished.

(c) Master Packing List. In addition to the requirements in paragraph (b) above, a master packing list shall be prepared where more than one shipment, shipping container or palletized unit load comprise the contract line item being shipped. The master packing list shall be attached to the number one container and so identified.

(d) Part Identification. All items within the kit, set, installation hardware or material shall be suitably segregated and identified within the unit pack(s) or shipping container by part number and/or national stock number.

D-247-W001 PROHIBITED PACKING MATERIALS (NAVSEA) (OCT 2018)

The use of asbestos, excelsior, newspaper or shredded paper (all types including waxed paper, computer paper and similar hygroscopic or non-neutral material) is prohibited. In addition, the use of yellow wrapping or packaging material is prohibited except where used for the containment of radioactive material. Loose fill polystyrene is prohibited for shipboard use.

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 N/A N/A N/A N/A 0001AA Origin Contractor Destination Government 0001AB Origin Contractor Destination Government 0001AC Origin Contractor Destination Government 0002 N/A N/A N/A N/A 0002AA Origin Contractor Destination Government 0002AB Origin Contractor Destination Government 0002AC Origin Contractor Destination Government 0003 N/A N/A N/A N/A 0003AA Origin Contractor Destination Government 0003AB Origin Contractor Destination Government 0003AC Origin Contractor Destination Government 0004 Origin Contractor Destination Government 1001 N/A N/A N/A N/A 1001AB Origin Contractor Destination Government 1001AC Origin Contractor Destination Government 1002 N/A N/A N/A N/A 1002AB Origin Contractor Destination Government 1002AC Origin Contractor Destination Government 1003 N/A N/A N/A N/A 1003AB Origin Contractor Destination Government 1003AC Origin Contractor Destination Government 1004 Origin Contractor Destination Government

CLAUSES INCORPORATED BY REFERENCE

52.246-2 Inspection Of Supplies--Fixed Price AUG 1996 52.246-11 Higher-Level Contract Quality Requirement DEC 2014 52.246-15 Certificate of Conformance APR 1984 52.246-16 Responsibility For Supplies APR 1984

E-246-H013 INSPECTION AND ACCEPTANCE OF DATA (NAVSEA) (OCT 2018)

Inspection and acceptance of all data shall be as specified on the attached Contract Data Requirements List(s), DD Form 1423.

E-246-H020 QUALITY MANAGEMENT SYSTEM REQUIREMENTS (NAVSEA) (OCT 2018)

The Contractor shall provide and maintain a quality management system that, as a minimum, adheres to the requirements of ASQ/ANSI/ISO 9001:2015 “Quality Management Systems – Requirements” and supplemental requirements imposed by this contract. The quality management system procedures, planning, and all other documentation and data that comprise the quality management system shall be made available to the Government for review. Existing quality documents that meet the requirements of this contract may continue to be used. The Government may perform any necessary inspections, verifications, and evaluations to ascertain conformance to requirements and the adequacy of the implementing procedures. The Contractor shall flow down such standards, as applicable, to lower-tier subcontractors under instances covered in FAR 52.246-11(b) or at the direction of the Contracting Officer. The Government reserves the right to disapprove the quality management system or portions thereof when it fails to meet the contractual requirements.

E-246-H022 INSPECTION AND TEST RECORDS (NAVSEA) (JAN 2019)

Inspection and test records shall, as a minimum, indicate the nature of the observations, number of observations made, and the number and type of deficiencies found. Data included in inspection and test records shall be complete and accurate, and shall be used for trend analysis and to assess corrective action and effectiveness. The data shall, on request, be identified and made available for on-site review by the Contracting Officer or designated Government representative.

E-246-W002 CERTIFICATE OF COMPLIANCE (NAVSEA) (OCT 2018)

(a) A certification of material shall be provided by the Contractor, one (1) copy to accompany the shipment (in the packing list envelope) and (l) copy mailed to arrive at time of receipt of the shipment. Mark all certificates to the attention of Code 00Q.

(b) The certificate shall state compliance of material with drawing specification and contract/order requirements. The certificate shall as a minimum state the company name, contract/order number, drawing or specification number, and date. The certificate shall state, above the signature of a legally authorized representative of the company, the following:

This certification concerns a matter within the jurisdiction of an agency of the United States and the making of a false, fictitious, or fraudulent certification may render the maker subject to prosecution under Title 18, United States Code, Section 1001.

(c) Failure to provide certification at the time of shipment may result in material being rejected and returned at the contractor's expense.

(d) The certificate shall read as follows:

I certify that on ______ [insert date], the ____ [insert Contractor’s name] furnished the supplies called for by the Order/Contract No._____ via ____ [Carrier] on ________ [identify the bill of lading or shipping document] in accordance with all applicable requirements. I further certify that the supplies or services are of the quality specified and conform in all respects with the contract requirements, including specifications, drawings, preservation, packaging, packing, marking requirements, and physical item identification (part number), and are in the quantity shown on this document.

Date of Execution: ________________________________ Signature: _______________________________________ Typed Name: ____________________________________ Title: ___________________________________________

E-246-W003 INSPECTION STANDARDS (NAVSEA) (OCT 2018)

Acceptance inspection of lots or batches will be in…