About this file

This Manufacturing Qualification Requirements (MQR) document outlines the requirements for becoming a qualified source to manufacture the MAF Chiller (NSN: 4130015475215, P/N: EAS80202-103) for the Minuteman III ICBM Environmental Control System. The document is associated with solicitation SPRHA2-25-R-0304 from Defense Logistics Agency Aviation for six units of the chiller.

The qualification process requires potential manufacturers to notify the government of intent to qualify, demonstrate adequate facilities and testing capabilities, verify possession of complete technical data package including EAS80202 and EAS82000 drawings, manufacture items meeting government requirements, conduct qualification testing at their expense (estimated cost $1,016,480), and provide a pre-contract qualification test article. The qualification process is estimated to take 500 days. Qualification waivers may be granted to sources who have previously supplied the articles to the government, have acquired qualified facilities through business transactions, or have access to an EAS82000 Brine Chiller Test Stand. Successful qualification does not guarantee contract award, and a post-award first article may still be required.

View the file

Other files for this federal contract opportunity

Other files attached to ICBM CHILLER, WATER, REFRI, newest first.
File Type Posted
SPRHA225R0304_______0002.pdf PDF
SPRHA225R0304_______0001.pdf PDF
CDRLCPP.pdf PDF
SPRHA225R0304.pdf PDF
SOW.pdf PDF
EDL.pdf PDF
CDRLFATR.pdf PDF
SPI.pdf PDF
Unmarked Eng Data 2022.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MANUFACTURING QUALIFICATION REQUIREMENTS

NSN: 4130015475215

P/N: EAS80202-103

Noun: MAF Chiller Application: Minuteman III ICBM Environmental Control System (LGM-30)

13 Jan 2025 Section C 1/3

SECTION C:

1. QUALIFICATION REQUIREMENTS THAT MUST BE SATISFIED TO BECOME A QUALIFIED SOURCE

a. Prequalification Notice/Sources Sought: The offeror shall notify the appropriate government Small Business Office or, if responding to a solicitation, the contracting officer in the appropriate government contracting office, of intent to qualify as a source for this MAF Chiller.

b. Facilities, Testing, and Inspection Capabilities: The offeror must certify to the government that they have, or have access to, the required facilities and equipment to manufacture, inspect, test, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.

c. Data Verification: The offeror must verify that he has a complete data package. This verification must include a complete list of all procedures, drawings, and specifications, including change notices, in the offeror’s possession including, at a minimum EAS80202 and all sub level drawings and EAS82000 and all sub level drawings. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications.

d. Manufacture/Process Verification: The offeror must manufacture this item to conform to the government requirements as prescribed within the ESA-approved engineering/technical data package. The offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by (414 SCMS). The offeror shall also identify its sources for materials and its standards for internally used processes.

e. Test and Evaluation and/or Verification: The offeror, at their own expense, shall prepare and submit to (414 SCMS) for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by Drawing EAS82000 and all sub level drawings and EAS80202 and all sub level drawings. After completion of the approved qualification testing, the offeror shall be required to submit a complete test report of the results to (414 SCMS) for their review and approval prior to the contract award. The government retains the right to exercise the option to inspect the testing processes, including on-site witnessing of any or all documented testing. To allow accomplishing this, the offeror shall notify the government at least 30 days in advance of the occurrence of any testing that will be used as a basis for qualification. The offeror’s facilities shall be made available for government inspection during these tests.

f. Qualification Article Verification: The offeror must provide, at their own expense, a pre-contract award qualification Brine Chiller Test Stand article for evaluation by the government. This article must comply with all the requirements of Drawing EAS82000 and all subassembly drawings and.

This article shall be subjected to a form, fit, and function evaluation to demonstrate compatibility with the weapon

P/N: EAS80202-103

Noun: MAF Chiller Application: Minuteman III ICBM Environmental Control System (LGM-30)

13 Jan 2025 Section C 2/3 system and to evaluate the manufacturing capability of the offeror. Offerors will be notified whether their qualification article passed or failed the required qualification testing within 60 days of submitting a product for qualification testing. Note that successful completion of the qualification testing does not guarantee any contract award. If the offeror is deemed qualified and awarded the contract, a post-contract award first article exhibit may be required to verify production capability.

g. Qualification Requirement Cost Estimate: Estimated likely costs for testing and evaluation, which will be incurred by the potential offering party to become qualified: $1,016,480.

h. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 500 days. This is based on complexity of the MAF Chiller and other factors.

i. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the contracting officer that the offeror (or its product) meets these standards for qualification or can meet them before the date specified for award of the contract. The award will not be delayed to provide the vendor with an opportunity to demonstrate its ability to meet the standards specified in this qualification requirement.

j. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract.

Once all requirements are met, the offeror will be listed as an approved source for this item.

Approval, however, does not guarantee subsequent contract award.

P/N: EAS80202-103

Noun: MAF Chiller Application: Minuteman III ICBM Environmental Control System (LGM-30)

13 Jan 2025 Section C 3/3

2. SOURCE QUALIFICATION WAIVER REQUIREMENTS

Sources who meet any of the following source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify production capability:

a. QWC1: The potential source submits written certification that the articles have been supplied to the government or original equipment manufacturer (e.g., DD Form 250, Material Inspection and Receiving Report, Purchase Order invoice, etc).

b. QWC6: A source previously qualified to provide an item, but which has been purchased, sold, merged, absorbed, reformed, split, etc., may qualify if it can be established that the qualification is currently with the requester and that the requester has the same or equivalent facilities, tooling, equipment, personnel, and utilizes the original forging, castings, etc., in the manufacturing process.

c. QWC7: The potential source has access to an EAS82000 Brine Chiller Test Stand other than the USAF owned EAS82000 asset.