About this file

This document outlines manufacturing qualification requirements for a Missile Alert Facility Chiller to be procured by the Defense Logistics Agency Aviation. Potential sources must complete all qualification requirements including notifying the Small Business Office of intent to qualify, demonstrating manufacturing and testing facilities, verifying the technical data package, conducting qualification testing estimated at $382,100 over 150 days, and providing a qualification article. Waivers may be granted for sources that have previously supplied the item to the government or original equipment manufacturer or are qualified to provide earlier or related items. The related solicitation is for the MMIII MAF Chiller and is restricted to the approved source HDT Global. Interested parties can view the technical data package and qualification requirements to pursue becoming an approved source.

View the file

Other files for this federal contract opportunity

Other files attached to MMIII MAF Chiller, newest first.
File Type Posted
FATR.pdf PDF
EDL.pdf PDF
SPRHA223R0059.pdf PDF
Pkg_SOW.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MANUFACTURING QUALIFICATION REQUIREMENTS

NSN: 4130015475215

P/N: EAS80202-103

Noun: MAF Chiller Application: Missile Alert Facility Chiller Unit

12 Dec 2022 Section C 1/3

SECTION C:

1. QUALIFICATION REQUIREMENTS THAT MUST BE SATISFIED TO BECOME A QUALIFIED SOURCE

a. Prequalification Notice/Sources Sought: The offeror shall notify the appropriate government Small Business Office or, if responding to a solicitation, the contracting officer in the appropriate government contracting office, of intent to qualify as a source for this MAF Chiller.

b. Facilities, Testing, and Inspection Capabilities: The offeror must certify to the government that they have, or have access to, the required facilities and equipment to manufacture, inspect, test, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.

c. Data Verification: The offeror must verify that they have a complete data package. This verification must include a complete list of all procedures, drawings, and specifications, including change notices, in the offeror’s possession. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications.

d. Manufacture/Process Verification: The offeror must manufacture this item to conform to the government requirements as prescribed within the ESA-approved engineering/technical data package. The offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by [ESA]. The offeror shall also identify its sources for materials and its standards for internally used processes.

e. Test and Evaluation and/or Verification: The offeror, at their own expense, shall prepare and submit to [ESA] for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by Drawing EAS80202-103. After completion of the approved qualification testing, the offeror shall be required to submit a complete test report of the results to [ESA] for their review and approval prior to the contract award. The government retains the right to exercise the option to inspect the testing processes, including on-site witnessing of any or all documented testing. To allow accomplishing this, the offeror shall notify the government at least 30 days in advance of the occurrence of any testing that will be used as a basis for qualification. The offeror’s facilities shall be made available for government inspection during these tests.

f. Qualification Article Verification: The offeror must provide, at their own expense, a pre-contract award qualification article for evaluation by the government. This article must comply with all of the requirements of Drawing EAS80202-103. This article shall be subjected to a form, fit, and function evaluation to demonstrate compatibility with the weapon system and to evaluate the manufacturing capability of the offeror. Offerors will be notified whether or not their

P/N: EAS80202-103

12 Dec 2022 Section C 2/3 qualification article passed or failed the required qualification testing within 90 days of submitting a product for qualification testing. Note that successful completion of the qualification testing does not guarantee any contract award. If the offeror is deemed qualified and awarded the contract, a post-contract award first article exhibit may be required to verify production capability.

g. Qualification Requirement Cost Estimate: Estimated likely costs for testing and evaluation, which will be incurred by the potential offering party to become qualified: $382,100.

h. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 150 days. This is based on complexity of the MAF Chiller and other factors.

i. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the contracting officer that the offeror (or its product) meets these standards for qualification or can meet them before the date specified for award of the contract. The award will not be delayed to provide the vendor with an opportunity to demonstrate its ability to meet the standards specified in this qualification requirement.

j. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract. Once all requirements are met, the offeror will be listed as an approved source for this item. Approval, however, does not guarantee subsequent contract award.

P/N: EAS80202-103

12 Dec 2022 Section C 3/3

2. SOURCE QUALIFICATION WAIVER REQUIREMENTS

Sources who meet any of the following source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify production capability:

a. QWC1: The potential source submits written certification that the articles have been supplied to the government or original equipment manufacturer (e.g., DD Form 250, Material Inspection and Receiving Report, Purchase Order invoice, etc).

b. QWC2: A source qualified to provide an assembly is usually qualified to provide subassemblies, major components, and items of that assembly.

c. QWC3: A source qualified to provide earlier dash numbers of a basic P/N may be qualified to provide other dash numbers of that same basic P/N, provided there is no increase in complexity, criticality, or other relevant requirements.

d. QWC4: A source previously qualified to provide an item, but which has been purchased, sold, merged, absorbed, reformed, split, etc., may qualify if it can be established that the qualification is currently with the requester and that the requester has the same or equivalent facilities, tooling, equipment, personnel, and utilizes the original forging, castings, etc., in the manufacturing process.