This document is a Site Evaluation report for the Mojave National Preserve (MOJA) Dome Fire site. The report covers pre-planning activities, sampling and analysis plan, ash/debris and soil sampling, and an asbestos survey conducted at the Kessler Spring and Valley View sites within MOJA. The key findings include analytical test results, comparison to background soil threshold values, and waste characterization. Appendices include the Sampling and Analysis Plan, site reconnaissance trip reports, field sampling documentation, laboratory analytical results, asbestos survey findings, and background statistical calculations.

The related federal contract opportunity is a pre-solicitation for the Dome Fire Demo & Soil Remediation project within the Mojave National Preserve, to be conducted by the Department of the Interior National Park Service Northeast Region. The project involves demolition of fire debris and removal of contaminated soils.

View the file

Other files for this federal contract opportunity

Other files attached to Dome Fire Demo & Soil Remediation, newest first.
File Type Posted
Site_Evaluation_Report_1.pdf PDF
Statement_of_Work_1.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Valley View Site Kessler

Spring Site

Kelso Depot Visitor Center

Nipton

Hole-in-the-Wall

Cima Road

Interstate 15

Project No.

073.20.001

Date

3/29/21 GW

Drawn By

BR

Checked By

PROFESSIONAL

ENVIRONMENTAL

ENGINEERS, INC.

Figure 1 Park Location and Sites Location Map

Mojave National Preserve (MOJA) Kessler Spring and Valley View Sites

LEGEND

MOJA Boundary

Roadways

MOJA AML Site Location

1" = 8 Miles When Printed 11 in by 17 in

N

1" = 2 Miles When Printed 11 in by 17 in

Kessler Spring

Valley View

Appx Surface Water Runoff

Divide

Draft MOJA Dome Fire Site Eval CLEAN WORD
Table of Contents
List of Tables iii
List of Figures iii
Appendices iii
1. Introduction 1-1
2. Site Evaluation Activities 2-2
3. Site Evaluation Results 3-4
4. Conclusions 4-6
5. References 5-7
List of Tables
List of Figures
Appendices
Appendix A – Sampling and Analysis Plan
Appendix B – Site Reconnaissance Trip Report
Appendix C – Field Sampling Documentation
Appendix D –Laboratory Analytical Results
Appendix E – Asbestos Survey
Appendix F – Background ProUCL Calculations
List of Abbreviations and Acronyms
1. Introduction
1.1 Background
1.2 Purpose
2. Site Evaluation Activities
2.1 Pre-Planning Activities
2.2 Sampling and Analysis Plan
2.3 Ash/Debris and Soil Sampling
2.4 Asbestos Survey
3. Site Evaluation Results
3.1 Analytical Testing
3.2 Background Soil Threshold Values
3.3 Analytical Results Compared to Screening Levels
3.4 Waste Characterization
4. Conclusions
5. References
Tables
Table1_Background Summ Stats CIMA Dome Fire Site (002)
Sheet1
Table2_3_Analysis Comparison Tables
KSR Comparison
VVR Comparison
Table4_5_Analysis Comparison Tables
KSR Data
VVR Data
Draft MOJA Dome Fire Site Eval CLEAN WORD
Figures
Figs 1-5
Figure 1 - Park Location and Site Location Mapc
Sheets and Views
Figure 1 - Park Location and Site Location Map
Figure 2 - Site Layout Map Kessler Spring
Sheets and Views
Figure 2 - Site Layout Map - Kessler
Figure 3 - Site Layout Map Valley View
Sheets and Views
Figure 3 - Site Layout Map - Valley View
Figure 4 - Kessler SU Location Map
Sheets and Views
Figure 4 - Kessler SU Map
Figure 5 - Valley View SU Location Map
Sheets and Views
Figure 5 - Valley View SU Map
Draft MOJA Dome Fire Site Eval CLEAN WORD
Appendix A – Sampling and Analysis Plan
AppA_MOJA Final Dome Fire COMPLETEpdf
MOJA Final Dome Fire COMPLETEpdf SAP
Table of Contents
1. Introduction 1-1
2. Site Description, Previous Investigations, and Conceptual Site Model 2-1
3. DQO Planning Team and Stakeholders 3-1
4. Data Quality Objectives 4-1
5. Field Sampling Plan 5-1
6. Data Management 6-1
7. Assessment and Oversight 7-1
8. Investigation Outputs 8-1
9. References 9-1
Appendices
Appendix A – Trip Report
Appendix B – PE Standard Operating Procedures
Appendix C – Laboratory QA / QC Procedures
List of Tables
List of Figures
List of Abbreviations and Acronyms
1. Introduction
1.1 CERCLA and National Park Service (NPS) Authority
1.2 Purpose of Field Sampling
1.3 Site Location
2. Site Description, Previous Investigations, and Conceptual Site Model
2.1 Key Site Features
2.1.1 Site Descriptions
2.1.2 Operational History
2.1.3 Waste Characteristics
2.1.4 Site Geology and Hydrogeology
2.1.5 Site Hydrology
2.1.6 Local Climate
2.1.7 Sensitive Environments
2.2 Summary of Previous Investigations
2.2.1 Data Quality/Usability
2.2.2 Preliminary Identification of Data Gaps
2.2.3 Contaminants of Potential Concern
2.3 Current and Future Property Use Scenarios
2.3.1 Graphical Conceptual Site Model
2.3.2 Key CSM Assumptions
3. DQO Planning Team and Stakeholders
3.1 DQO Planning Team
3.2 Decision-Makers
3.3 Stakeholders
4. Data Quality Objectives
4.1 The Problem
4.2 Investigation Goals
4.2.1 Principal Investigation Questions
4.2.2 Decision Criteria
4.3 Information Inputs
4.3.1 Previous Data Usability
4.3.2 Data to be Collected in the Current Investigation
4.4 Define the Boundaries of the Investigation
4.4.1 Spatial Boundaries
4.4.2 Decision Units
4.4.3 Sampling Units
4.4.4 Temporal Boundaries
4.5 Develop the Analytical Approach
4.5.1 Decision or Estimation Parameters
4.5.2 Action Levels
4.6 Performance or Acceptance Criteria
4.6.1 Quality Assurance/Quality Control
4.6.1.1. Laboratory Quality Assurance/Quality Control
4.6.1.2. Field Quality Assurance/Quality Control

4.6.2 Data Verification and Usability

4.7 Plan for Obtaining the Data

5. Field Sampling Plan
5.1 Ash/Debris Sampling
5.1.1 Ash/Debris Sampling Locations
5.1.2 Ash/Debris Sampling Protocol
5.1.3 Ash/Debris Sampling Health and Safety
5.1.4 Ash/Debris Field Measurements
5.1.5 Ash/Debris Analytical Methods
5.2 Sample Handling
5.2.1 Sample Designation
5.2.2 Sample Labeling
5.2.3 Sample Handling and Chain of Custody
5.2.4 Documentation and Records

5.3 Investigation Derived Waste Handling

6. Data Management
6.1 Data Collection
6.2 Laboratory Analysis and Data Deliverables
6.3 Data Verification
6.3.1 Field Data
6.3.2 Analytical Data
7. Assessment and Oversight
7.1 Assessment and Corrective Actions
7.1.1 Field Audit and Response Actions
7.2 Quality Assessment Reporting
7.2.1 Data Verification

7.3 Reconciliation with DQOs and Data Usability

8. Investigation Outputs
9. References
MOJA Final Dome Fire SAP Fig.App
MOJA Draft Cima Dome Fire SAP042321
Figures
Dome Fire SAP Figures
Sheets and Views
Figure 1 - Park Location and Site Location Map
Figure 2 - Site Layout Map Kessler Spring.pdf
Sheets and Views
Figure 2 - Site Layout Map - Kessler
Figure 3 - Site Layout Map Valley View.pdf
Sheets and Views
Figure 3 - Site Layout Map - Valley View
Figure 4 - Graphical CSM.pdf
Sheets and Views
Figure 4 - Graphical CSM
Figure 5 - Kessler SU Location Map.pdf
Sheets and Views
Figure 5 - Kessler SU Map
Figure 6 - Valley View SU Location Map.pdf
Sheets and Views
Figure 6 - Valley View SU Map
MOJA Draft Cima Dome Fire SAP042321
Appendix A – Trip Report
Cima Dome Fire Kessler Spring and Valley View
1-Trip Report - CIMADOME
Binder1c
2a-Photolog Cover
Photolog - Kessler Spring
Photolog - Valley View
3a-Field Notes Cover
Field Notes 3.8.21
MOJA Draft Cima Dome Fire SAP042321
Appendix B – PE Standard Operating Procedures
Dome Fire SAP Appendix B
Cima Dome Fire Appx
SOP No. 1 - Bulk Asbestos Sampling Method draft final
SOP NO. 1—BULK ASBESTOS SAMPLING
Purpose and Scope
Definitions:
Procedural Precautions
Apparatus, Materials, and Chemicals
Summary of Bulk Asbestos Sampling Procedure
Personnel Training for Bulk Asbestos Sampling
Records and Review Documentation
Safety Precautions
References
MOJA Dome Fire Appendix A SOPs
SOP NO. 3—SOIL/SEDIMENT SAMPLING
Purpose and Scope
Procedures for Soil Sampling
Equipment List
Decontamination
Soil Sample Collection
Soil Sample Collection
Field Quality Assurance/Quality Control Procedures and Samples
Duplicate (QC) Samples
Sample Identification, Handling, and Documentation
Documentation
Field Logbook
SOP NO. 5—DECONTAMINATION
Introduction and Types of Contamination
Site and/or Sample Cross-Contamination
Equipment List
Decontamination Procedures
Personnel
Sampling Equipment
Decontamination Solutions
Responsible Authority
Wastewater
Emergency Decontamination
Documentation
SOP NO. 6—SAMPLE HANDLING, DOCUMENTATION, AND TRACKING
Purpose and Scope
Sample Identification
Field Samples
Sample Handling
Sample Containers
Sample Preservation
Sample Handling and Shipping
Holding Times and Analyses
Sample Documentation and Tracking
Field Notes
Sample Chain-Of-Custody
MOJA Dome Fire Appendix A SOPs
SOP NO. 3—SOIL/SEDIMENT SAMPLING
Purpose and Scope
Procedures for Soil Sampling
Equipment List
Decontamination
Soil Sample Collection
Soil Sample Collection
Field Quality Assurance/Quality Control Procedures and Samples
Duplicate (QC) Samples
Sample Identification, Handling, and Documentation
Documentation
Field Logbook
SOP NO. 5—DECONTAMINATION
Introduction and Types of Contamination
Site and/or Sample Cross-Contamination
Equipment List
Decontamination Procedures
Personnel
Sampling Equipment
Decontamination Solutions
Responsible Authority
Wastewater
Emergency Decontamination
Documentation
SOP NO. 6—SAMPLE HANDLING, DOCUMENTATION, AND TRACKING
Purpose and Scope
Sample Identification
Field Samples
Sample Handling
Sample Containers
Sample Preservation
Sample Handling and Shipping
Holding Times and Analyses
Sample Documentation and Tracking
Field Notes
Sample Chain-Of-Custody
MOJA Draft Cima Dome Fire SAP042321
Appendix C – Laboratory QA/QC Procedures
Dome Fire SAP App C
sac-qam_r6_sept2020
Pace Minn QAM
Signature Manifest
Quality Manual
1.0 Purpose and Scope
1.1 Purpose
1.2 Scope and Application
1.2.1 Quality Manual Template
1.2.2 Laboratory Quality Manual
1.2.3 References to Supporting Documents
2.0 References
3.0 Terms and Definitions
4.0 Management Requirements
4.1 Organization
4.1.1 Legal Identity
4.1.1.1 Change of Ownership
4.1.2 Compliance Responsibility
4.1.3 Scope of the Quality Management System
4.1.4 Organization History and Information
4.1.4.1 Organization Structure
4.1.5 Management Requirements
4.1.5.1 Personnel
4.1.5.2 Roles and Responsibilities
4.1.5.3 Conflict of Interest
4.1.5.4 Confidentiality
4.1.5.5 Communication
4.2 Quality Management System
4.2.1 Quality Management System Objectives
4.2.1.1 Impartiality
4.2.1.2 Risk and Opportunity Assessment
4.2.1.3 Communication of the Quality Management System
4.2.2 Quality Policy Statement
4.2.2.1 Ethics Policy / Data Integrity Program
4.2.3 Management Commitment: Quality Management System
4.2.4 Management Commitment: Customer Service
4.2.5 Supporting Procedures
4.2.5.1 Quality Management System Document Structure
4.2.6 Roles and Responsibilities
4.2.7 Change Management
4.3 Document Control
4.3.1 General
4.3.2 Document Approval and Issue
4.3.3 Document Review and Change
4.4 Analytical Service Request, Tender, and Contract Review
4.5 Subcontracting and In-Network Work Transfer
4.6 Purchasing Services and Supplies
4.7 Customer Service
4.7.1 Commitment to Meet Customer Expectations
4.7.2 Customer Feedback
4.8 Complaints
4.9 Nonconforming Work
4.9.1 Definition of Nonconforming Work
4.9.1.1 Authorized Departure from SOP
4.9.1.2 Authorized Departure from Test Methods (Method Modifications)
4.9.1.3 Stop Work Authority
4.10 Continuous Improvement
4.11 Corrective Action
4.11.1 Root Cause Analysis
4.11.2 Effectiveness Review
4.11.3 Additional Audits
4.12 Preventive Action
4.12.1 Change Management
4.13 Control of Records
4.13.1 General Requirements
4.13.1.1 Procedure
4.13.1.2 Record Legibility and Storage
4.13.1.3 Security
4.13.1.4 Electronic Records
4.13.2 Technical Records
4.13.2.1 Description
4.13.2.2 Real Time Recordkeeping
4.13.2.3 Error Correction
4.14 Audits
4.14.1 Internal Audit
4.14.1.1 Corporate Compliance Audit
4.15 Management Review
4.16 Data Integrity
5.0 Technical Requirements
5.1 General
5.2 Personnel
5.2.1 Personnel Qualifications
5.2.1.1 Competence
5.2.2 Training
5.2.2.1 Training Program and Goals
5.2.2.2 Effectiveness of Training
5.2.3 Personnel Supervision
5.2.4 Job Descriptions
5.2.5 Authorization of Technical Personnel
5.3 Accommodations and Facilities
5.3.1 Facilities
5.3.2 Environmental Conditions
5.3.3 Separation of Incompatible Activities
5.3.4 Laboratory Security
5.3.5 Good Housekeeping
5.4 Test Methods
5.4.1 General Requirements
5.4.2 Method Selection
5.4.3 Laboratory Developed Methods
5.4.4 Non-Standard Methods
5.4.5 Method Validation
5.4.5.1 Validation Description
5.4.5.2 Validation Summary
5.4.5.3 Validation of Customer Need
5.4.6 Measurement Uncertainty
5.4.7 Control of Data
5.4.7.1 Calculations, Data Transfer, Reduction and Review
5.4.7.2 Use of Computers and Automated Acquisition
5.5 Equipment
5.5.1 Availability of Equipment
5.5.2 Calibration
5.5.2.1 Support Equipment
5.5.2.2 Analytical Instruments
5.5.3 Equipment Use and Operation
5.5.4 Equipment Identification
5.5.5 Equipment Lists and Records
5.5.5.1 Equipment List
5.5.5.2 Equipment Records
5.5.6 Out of Service Protocol
5.5.7 Calibration Status
5.5.8 Returned Equipment Checks
5.5.9 Intermediate Equipment Checks
5.5.10 Safeguarding Equipment Integrity
5.6 Measurement Traceability
5.6.1 General
5.6.2 Equipment Correction Factors
5.6.3 Specific Requirements
5.6.3.1 Requirements for Calibration Laboratories
5.6.3.2 Requirements for Testing Laboratories
5.6.4 Reference Standards and Reference Materials
5.6.4.1 Reference Standards
5.6.4.2 Reference Materials
5.6.4.3 Intermediate Checks
5.6.4.4 Transport and Storage
5.7 Sampling
5.7.1 Sampling Plans and SOPs
5.7.2 Customer Requested Deviations
5.7.3 Recordkeeping
5.8 Sample Management & Handling
5.8.1 Procedures
5.8.1.1 Chain of Custody
5.8.1.2 Legal Chain of Custody
5.8.2 Unique Identification
5.8.3 Sample Receipt Checks and Sample Acceptance Policy
5.8.3.1 Sample Receipt Checks
5.8.3.2 Sample Acceptance Policy
5.8.4 Sample Control and Tracking
5.8.5 Sample Storage, Handling, and Disposal
5.8.5.1 Sample Storage
5.8.5.2 Sample Retention and Disposal
5.9 Assuring the Quality of Test Results
5.9.1 Quality Control (QC) Procedures
5.9.1.1 Essential QC
5.9.1.2 Proficiency Testing (PT)
5.9.2 QC Corrective Action
5.9.3 Data Review
5.9.3.1 Primary Review
5.9.3.2 Secondary Review
5.9.3.3 Completeness Review
5.9.3.4 Data Audits
5.10 Reporting
5.10.1 General Requirements
5.10.2 Test Reports: Required Items
5.10.3 Test Reports: Supplemental Items
5.10.3.1 Supplemental Requirements
5.10.3.2 Test Reports: Sampling Information
5.10.4 Calibration Certificates
5.10.5 Opinions and Interpretations
5.10.6 Subcontractor Reports
5.10.7 Electronic Transmission of Results
5.10.8 Format of Test Reports
5.10.9 Amendments to Test Reports
6.0 Revision History
7.0 Appendices
7.1 Appendix A: Certification / Accreditation Listing
7.1.1 PAS-Minneapolis
7.2 Appendix B: Capability Listing
7.2.1 PAS-Minneapolis
7.3 Appendix C: Glossary
7.4 Appendix D: Organization Chart(s)
7.4.1 PAS-Corporate
7.4.2 PAS-Minneapolis, Bloomington
7.5 Appendix E: Equipment Listing
7.5.1 PAS-Minneapolis, Bloomington
8.0 Addendum: Program requirements
8.1 DoD/DOE
8.2 Ohio VAP
Section 5.6.3.2 Reference Materials
Draft MOJA Dome Fire Site Eval CLEAN WORD
Appendix B – Site Reconnaissance Trip Report
AppB_Cima Dome Fire Trip Report
1-Trip Report - CIMADOME
Binder1c
2a-Photolog Cover
Photolog - Kessler Spring
Photolog - Valley View
3a-Field Notes Cover
Field Notes 3.8.21
Draft MOJA Dome Fire Site Eval CLEAN WORD
Appendix C – Field Sampling Documentation
C
AppC_1Photolog - Kessler Spring
AppC_2Photolog - Valley View
AppC_36.2021 Field Notes Combined
6.2021 Field Notes Combined.pdf
6.7 Field Notes Pg 1 & 2c.pdf
6.8 Notes Pg 1.pdf
6.8 Notes Pg 2,3.pdf
6.8 Notes Pg 4,5.pdf
6.8 Notes Pg 6,7.pdf
6.8 Notes Pg 8.pdf
KS Ranch house map.pdf
Kessler Spring Field Map.pdf
VV site map.pdf
Draft MOJA Dome Fire Site Eval CLEAN WORD
Appendix D – Laboratory Analytical Results
D
AppD_1J74812-1 UDS Level 2 Report Final Report
1. Cover Page
2. Table of Contents
3. Definitions/Glossary
4. Case Narrative
5. Detection Summary
6. Client Sample Results
7. Surrogate Summary
8. Isotope Dilution Summary
9. QC Sample Results
10. QC Association Summary
11. Lab Chronicle
12. Certification Summary
13. Method Summary
14. Sample Summary
15. Subcontract Data
16. Chain of Custody
17. Receipt Checklists
AppD_2J74812-2 UDS Level 2 Report Final Report
1. Cover Page
2. Table of Contents
3. Definitions/Glossary
4. Case Narrative
5. Detection Summary
6. Client Sample Results
7. QC Sample Results
8. QC Association Summary
9. Lab Chronicle
10. Certification Summary
11. Method Summary
12. Sample Summary
13. Chain of Custody
14. Receipt Checklists
Draft MOJA Dome Fire Site Eval CLEAN WORD
Appendix E – Asbestos Survey
E
AppE_121028581_Kessler Springs & Ranch House & Shed
AppE_221028582_Ranch House & VV Dome Fire
AppE_321028583_Bunk House & Valley View Dome Fire
AppE_421028584_Kessler Springs & Bunk House
AppE_521028585_Kessler Springs & Shed
Draft MOJA Dome Fire Site Eval CLEAN WORD
Appendix F – Background ProUCL Calculations
F
AppF_1KSR Background, ProUCL Output File
Sheet1
AppF_2VVR Background, ProUCL Output File
Sheet1