About this file
The document is an Invitation to Bid (ITB) from the Tennessee Department of Correction (TDOC) for asphalt paving work at the Mark Luttrell Transition Center located at 6000 State Road in Memphis, Tennessee. The project involves replacing 13,525 square yards of existing asphalt with a 2-inch asphalt wearing course, including 180 tons of asphalt patching and 150 tons of asphalt bushing for drainage in designated areas. The scope of work includes milling existing surfaces, removing and replacing signage, mechanically sweeping and cleaning the pavement, patching cracks and potholes, adjusting drainage slopes, adding a tack coat, applying a new wearing surface, rolling for compaction, and applying 4-inch white stripes and parking space markings.
The ITB specifies a single award approach, with a preference for weekday and daytime work, though contractors can request weekend or nighttime work. Contractors must provide an anticipated schedule and comply with the institution's security procedures, including background checks. The unit costs will be valid upon completion of the designated areas, with the potential for bid adjustments in case of material overruns or underruns. The pricing will be based on per-square-yard rates for milling, per-ton rates for asphalt patching and drainage bushing, and a per-square-yard rate for the 2-inch thick overlay. The document indicates that the contractor must match the new stripes and parking spaces to the current number and type of existing spaces.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Att.1_Non-Institutional_Detention_Project_Procedures.pdf | ||
| MLTC_AsphaltPaving_Specs_4.10.25.pdf | ||
| MLTC_Asphalt_Paving.pdf | ||
| 32916-13647_Amendment_1.pdf | ||
| 32916-13647_Amendment_2.pdf | ||
| SHARE_32916-0000013647_0.00.pdf | ||
| mark_lutrell_center_map_(2).pdf | ||
| MLTC_AsphaltPaving_Specs_4.10.25.pdf | ||
| Att.1_Non-Institutional_Detention_Project_Procedures.pdf | ||
| SHARE_32916-0000013647_0.00.pdf | ||
| 32916-13647_Amendment_1.pdf | ||
| MLTC_Asphalt_Paving.pdf | ||
| mark_lutrell_center_map_(2).pdf | ||
| MLTC_Asphalt_Paving.pdf | ||
| Survey_Document.pdf | ||
| Att.1_Non-Institutional_Detention_Project_Procedures.pdf | ||
| TandC_32916-13647.pdf | ||
| mark_lutrell_center_map_(2).pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Invitation to Bid (ITB) Specifications for Asphalt Paving Road for Mark Luttrell Transition Center
Tennessee Department of Correction (TDOC)
I. Introduction:
Tennessee Department of Correction / Mark Luttrell Transition Center is looking to apply a 2” asphalt overlay of existing asphalt portion of 6000 State Road Memphis, Tennessee 38134 (Shelby County)
II. Goods/Services to be Provided: Replace 13,525 SY 2” asphalt wearing course. Including 180 tons asphalt patching, 150 tons asphalt bushing for drainage in hatched areas shown on the Mark H. Luttrell Transition Center Site Map.
• Mill existing surfaces
• As applicable, remove and replace any signage
• Mechanically broom sweep all areas
• Clean Existing Pavement with air blower
• Patch and fill existing cracks/potholes, adjust drainage slopes to ensure 100% drainage
(no puddles)
• Add tack coat per Tennessee Highway Standards
• Wearing surface per Tennessee Highway Standards compacted thickness of two inches
• Roll with tandem roller for compaction
• Paint Stripping, 4-inch single white stripe outside lanes and delineating all parking spaces.
• Contractor shall match the new stripes and parking spaces to equivalent to the current number and type of spaces
III. Evaluation and Award
Single Award
Weekday and daytime work are preferred. Contractor can request weekend or nighttime work. Contractor shall provide anticipated schedule for work prior to commencement of any performance of duties. Contractor shall follow all applicable security procedures at the institution, including background checks. Please see attachment 1.
These unit costs shall be valid if the designated areas are completed to allow adjustments of bid should there be material overruns or underruns from the estimates in these specifications.
Milling per square yard Asphalt patching per ton Bushing for drainage per ton Overlay per square yard at 2” thick