Load Bank SOW.docx

DOCX document 19 KB Posted

Attached to
REACTIVE LOAD BANK Federal contract opportunity
Solicitation number
70Z04022P60051Y00
Issued by
Department of Homeland Security US Coast Guard

View the file

Other files for this federal contract opportunity

Other files attached to REACTIVE LOAD BANK, newest first.
File Type Posted
SOLICITATION 70Z04022P60051Y00- REACTIVE LOAD BANK.docx DOCX document
Far Smart Matrix SERVICES.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW for Reactive Load Bank Reference PR 2122402Y61A1499006

CGC SENECA

Contractor shall provide, deliver, and pick- up a reactive a load bank to be utilized in the testing phase of the newly install diesel generator shipboard system and C18 diesel generators onboard CGC SENECA. The period of performance is from 22 February 2022 to 22 March 2022. The following requirements must be meet for the contractor provided load bank.

Load Bank Specifications:

· 480 Volts, 3 phase, 60 Hertz

· Load Bank Reactive- Provide Minimum 2640 kW

· 120 QTY of 4/0, 375 Amp Cable- 50 FT Loose with Camlocks

· 40 QTY of Cable Tail 4/0- Eyelet + Female Camlock Loose

· 40 QTY of Cable Tail 4/0- Male Camlock + Eyelet Loose

The reactive load bank accurately simulates the types of loads the generator sets will see with equipment startup loads and reacting to the inrush. CGC SENECA is a prototype installation needed to validate the following requirement below which can only be done with a reactive load bank:

Load Sharing- Over the range of the test, the real loads (kW) on the individual generator sets are not to differ from their equal share of the total real load (kW) by more than 15% of the generators’ rated real power (kW) output. The reactive loads (kVA) on the individual generator sets are not to differ from their equal share of the total reactive load (kVA) by more than 10% of the generators’ rated reactive (kVA) output.

Normal operating hours of the Yard are from 0700 to 1530 Monday through Friday.

The contractor may opt to work past 1600 hours Monday through Friday, and work may work weekends if deemed necessary. If work is scheduled other than normal Yard operating hours the contractor must notify the Ship Superintendent of his/her intentions. NOTE: No work will be done after 1530 unless authorized by the Contracting Office or Contract Specialist.

The contractor provided load bank shall be delivered to the following address:

POC: Katherine Murray, 443-829-6430 CG Yard 2401 Hawkins Point Rd Baltimore, MD 21226