Item description.docx

DOCX document 33 KB Posted

Attached to
Autoclave System Upgrade Federal contract opportunity
Solicitation number
FA812622Q0035
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

View the file

Other files for this federal contract opportunity

Other files attached to Autoclave System Upgrade, newest first.
File Type Posted
Solicitation - FA812622Q0035.pdf PDF
Technical Evaluation Critical Factor List.docx DOCX document
Appendix A - Autoclave Upgrade Purchase.pdf PDF
Statement of Work.docx DOCX document
Appendix C - Autoclave Upgrade Purchase.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

OKLAHOMA CITY AIR LOGISTICS COMPLEX (OC-ALC)

TINKER AIR FORCE BASE OKLAHOMA

Autoclave System Upgrade M22-037

The 76th MXSG is requesting Autoclave System Upgrades. This requirement must have the following specifications:

· Vacuum System upgrades to include labor, engineering and materials for the following:

· Replacement of the Vacuum/Vent manifolds with a Walton Process Technology (WPT) vacuum header manifold with all wiring, gauges and tubing required to make the system operational.

· Replacement of Threaded Vacuum fittings with stainless steel tubing.

· Replacement of four (4) vacuum source pass throughs.

· Replacement of four (4) vacuum probe pass throughs.

· Replacement of two (2) ½” proportional valves on the vacuum system.

· Replacement of one (1) ½” trim valve, digital, fail close.

· Replacement of one (1) each 1-1/2” main cooling valve, digital fail close.

· Replacement of one (1) each 1-1/2” vent valve.

· Replacement of copper tubing from vacuum pump to vacuum header manifold with stainless steel or copper tubing.

· Preprogramming of the PLC code.

· Replace pneumatic tubing and fittings from door control valve to door open/close actuator.

· Replace copper tubing from the vacuum pump to the vacuum header.

· One (1) Oxygen Analyzer System

· One (1) Nitrogen Block and Bleed System

· One (1) WPT PCS 2.0 Process Controller

· To include Installation, Testing, Tuning and Training

· The result of the vacuum upgrade shall be a vacuum of 28 inches of mercury, unless there are vacuum leaks upstream of the connection at the vacuum pump.

· The result of the operating system upgrade shall allow for access to and import of historical data into the new operating system and reports.

· Training will be for up to seven people and be 4-6 hours in length and be conducted between the hours of 0800 and 1400. The training will include recipe development, operational instructions and theory behind the oxygen analyzer system and the double block and bleed system image1.wmf