ITB-25-022-2025 Residential Streets.pdf

PDF 303 KB Posted

Attached to
2025 Residential Streets Program State and local contract opportunity
Solicitation number
25-022
Issued by
Colorado

About this file

This is an Invitation to Bid (ITB) document from the City of Wheat Ridge, Colorado, for the 2025 Residential Streets Program (ITB-25-022-2025). The project involves comprehensive street rehabilitation, including asphalt and concrete work, striping, and accessibility improvements. Specific scope includes milling and overlaying designated streets, replacing concrete sidewalks, updating striping, installing an ADA sidewalk ramp, and creating four sidewalk extensions to reduce pedestrian crossing distances. Unique elements include refreshing striping on Harlan from the I-70 bridge to 44th Avenue and adding bicycle shared lane symbols on Parfet from 38th to 35th Street. The bid is scheduled to be issued on April 1, 2025, with an optional pre-bid conference on April 15, 2025, via Microsoft Teams. Bids are due on May 1, 2025, at 1:00 PM local time, with a project start anticipated by June 2025 and completion expected by September 1, 2025.

Bidders must submit a 5% bid bond and complete a Contractor Qualification Form, with the City reserving the right to reject any or all bids. The project will be funded through the City's annual budget, with contractors required to be on the Colorado Department of Transportation's approved contractor list and use both LCPTracker and B2GNow. Insurance requirements include general liability coverage with $500,000 per person bodily injury, $1,000,000 for property damage, and $1,000,000 for automobile liability. Disadvantaged business enterprises are afforded full opportunity to submit bids, and contractors must comply with labor regulations including the Colorado Revised Statutes. The project documents are available on OpenGov.com, and the point of contact is Whitney Mugford-Smith, Procurement and Contracts Manager.

View the file

Other files for this state and local contract opportunity

Other files attached to 2025 Residential Streets Program, newest first.
File Type Posted
03-Bid Summary.pdf PDF
07-Improvement Zones Map.pdf PDF
04-M_O_Striping_Exhibits.pdf PDF
05-Resi Street Striping 2025.pdf PDF
ITB-25-022-Forms 2025 Residential Streets.pdf PDF
06-M-608-1_Curb_Ramps.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITB-25-022-2025 Residential Streets 1

PROJECT DOCUMENTS

VERSION [11/2024]

2025 Residential Streets

25-022

Prepared by:

Public Works Department

CIP Division

Procurement Manager Whitney Mugford-Smith, NIGP-CPP, CPPB wmsmith@ci.wheatridge.co.us

CITY OF WHEAT RIDGE

7500 W. 29TH AVENUE

WHEAT RIDGE, CO 80033

ANTICIPATED PROJECT SCHEDULE

ITB Issued April 1, 2025 Optional Pre-Bid Conference/Meeting April 15, 2025 at 2pm on MS Teams Deadline for Questions April 21, 2025 Addendum Issuance April 24, 2025 Bid Due Date and Time May 1, 2025 at 1:00 PM local time Project Start Date By June 2025 Completion Date By September 1, 2025

The engineering material and data contained in these Project Documents were prepared under the supervision and direction of Dustin Lanning, Engineering Technician III.

ITB-25-022-2025 Residential Streets 2

Table of Contents

INVITATION TO BID

INFORMATION FOR BIDDERS

GENERAL PROVISIONS

SAMPLE AGREEMENT & FORMS

CDOT STANDARD SPECIFICATIONS

CITY SPECIAL PROVISIONS

REQUIRED SUBMITTAL DOCUMENTS (Under Separate Cover)

Bidder Acknowledgement Form Contractor’s Qualification Form List of Subcontractors and Amount Non-Discrimination Assurance Form Non-Collusion Affidavit Keep Jobs in Colorado Form Proposal Form Bid Bond Form

BID SCHEDULE (Protected Excel Spreadsheet Under Separate Cover)

DRAWINGS

EXHIBITS

MS Teams Info:

Meeting ID 213 777 131 800 Passcode: K7xo29d5

To receive a link, please email Whitney Mugford-Smith at wmsmith@ci.wheatridge.co.us

ITB-25-022-2025 Residential Streets 3

INVITATION TO BID

ITB-25-XXXX-2025 Residential Streets

Bid Due Date: May 1st, 2025 by 2:00 pm local time, via OpenGov.com

Scope of Work: Asphalt and concrete rehabilitation including striping. Mill and overlay indicated streets. Replace indicated concrete sidewalks. Replace/Update striping as shown in striping plan. Replace striping as exists unless otherwise indicated. An ADA sidewalk ramp will be installed as well as 4 sidewalk extensions to reduce pedestrian crossing distance at crosswalk designated by pavement markings and channelization (MUTCD Figure 3J-6). Harlan from I-70 bridge to 44th striping will be refreshed only. Parfet from 38th to 35th will be bicycle shared lane symbols added only.

Pre-bid Meeting: Microsoft Teams April 15th, 2025 at 2pm local time

Meeting ID: 213 777 131 800 Passcode: K7xo29d5

Deadline for Questions: April 21st, 2025 at 2pm local time.

Contractor Qualification: Bidder must complete and submit the Contractor Qualification Form provided with the bid document. Failure to complete this form and submit with bid may result in the disqualification of the contractor. The City’s acceptance of this bid shall be based on information provided by the contractor in this form. Bid amount and qualifications are evaluated after bid opening to determine the successful bidder. The City does not pre-qualify contractors. Contractor must be on the Colorado Department of Transportation’s approved list of contractors for the work included in this contract and be a user of both LCPTracker and B2GNow. On federally funded projects, Contractor cannot be banned or debarred, per current sam.gov information at www.sam.gov.

Disadvantaged Businesses: Disadvantaged business enterprises are afforded full opportunity to submit bids and will not be discriminated against on the grounds of race, color or national origin in consideration for an award.

Labor Compliance: Contractors shall comply with the amended provisions of CRS 8-17-101 et seq., regarding performance on public contracts.

Bid Bond: A 5% bid bond is required to be submitted with the bid. Payment and performance bonds for 100% of the contract price and insurance will be required for the successful bidder.

Mark Electronic Submittal: Company Name, 2025 Residential Streets

Comments: All bids will be validated. No bids will be accepted after the bid due time. The City of Wheat Ridge reserves the right to reject any and all bids or any part and to waive any formalities or informalities to make an award in the best interest of the City.

Bid Documents: Available at OpenGov.com. Visit OpenGov for bid tab sheets and project updates.

Point of Contact: Whitney Mugford-Smith, Procurement and Contracts Manager, wmsmith@ci.wheatridge.co.us

Do not contact the requesting department.

ITB-25-022-2025 Residential Streets 4

INFORMATION FOR BIDDERS

1. BID SUBMISSION REQUIREMENTS

1.1. Electronic Bids for 2025 Residential Streets will be received by the City of Wheat Ridge, Office of Procurement and Contracts via OpenGov.com, as stated in the Advertisement.

Point of Contact: Whitney Mugford-Smith, by email wmsmith@ci.wheatridge.co.us Questions about this bid should be posed on the OpenGov Platform.

1.2. Bid Documents are available on OpenGov at OpenGov.com

The City does not assume any responsibility for errors or misinterpretations resulting from the use of incomplete sets of bidding documents.

The City in making copies of the bidding documents available on the terms in this Project Manual does so only for the purpose of obtaining bids on the Work and does not confer a license of grant for use.

1.3. Electronic Project Document/Proposal must be submitted and signed, either digitally or in ink and scanned. All blank spaces for prices must be filled in and the Proposal Form must be fully completed and executed when submitted. In the case of discrepancies, the unit price shall govern the extension and subsequent total. No alteration in bid prices by erasures, deletions or strike-outs, will be acceptable unless each alteration is signed or initialed by the Bidder. A conditional or qualified Bid will not be accepted.

The Project Documents contain an affidavit certifying that the Bidder has not participated in any collusion or taken any action in restraint of free competitive bidding. This form must be signed and submitted with the Bid.

Names of all subcontractors and the amounts of their subcontract work shall be provided on the List of Subcontractors, as provided in this bid. If none, state “none”.

1.4. Not used

1.5. Each Bid must be accompanied by a digital Bid Bond payable to the City for five percent (5%) of the total amount of the Bid. Securities may not be substituted for Bid Bonds.

Attorneys-in-Fact who sign Bid Bonds must file with each Bond a certified and effective dated copy of their Power of Attorney.

Surety companies executing bid and performance bonds must appear on the Treasury Departments most current list (Circular 570 as amended) and be authorized to transact business in the State of Colorado.

1.6. A bidder may withdraw or revise a proposal after it has been deposited with the City. Withdrawal of bids may be made either in writing or in person; however, any bid withdrawn for purpose of revision must be re-deposited with the City before the time set for opening of bids. Bids may not be withdrawn after the time set for opening of bids.

1.7. The City assumes no responsibility for late deliveries of e-mail. Only electronic bids received by the Procurement & Contracting Division will be accepted.

1.8. Issuance of this Request for Bid does not commit The City of Wheat Ridge to award any contract or to procure or contract for any equipment, materials, or services. The City further reserves the right to waive informalities or irregularities, and the right to accept or reject any and all bids, including but not limited to, any bid which does not meet bonding requirements, or bids which do not furnish the quality, or offer the availability of materials, equipment or services as required by the specifications, description or scope of services, or bids from bidders who lack experience or financial responsibility, or bids which are not to form, or to award bids to the lowest and most responsive and responsible bidder, or to require new bids.

No award will be made to any person, firm, or corporation that is in arrears upon any obligation to the City.

ITB-25-022-2025 Residential Streets 5

1.9. The City of Wheat Ridge is exempt from City, County, State and Federal Sales/Excise Taxes. Certificates will be issued upon request.

2. BID DOCUMENTS

2.1. The Contract Documents consist of the Contract Bid Documents including construction specifications, if any.

The Contract Bid Documents contain the provisions required for the bidding and construction of the Project.

The Owner shall provide to Bidders, prior to Bidding, all information that is pertinent to, and delineates and describes, the Work. This may occur on the plans or on a separate document.

2.2. Each Bidder is responsible for inspecting the site and for reading and being thoroughly familiar with the Contract Documents, including Addenda. The failure or omission of any Bidder to do any of the foregoing shall in no way relieve any Bidder from any obligation in respect to his Bid. After Bids have been submitted, the Bidder shall not assert that there was a misunderstanding concerning the quantities of Work or of nature of the Work to be done or any materials specified for the Work.

2.3. If it should appear to a Bidder that the work to be done or matters relative thereto are not sufficiently described or explained in the Contract Documents or that the Contract Documents are not definite and clear, the Bidder may make written inquiry regarding same to the Procurement Contact at least five (5) working days or a designated date set by the Procurement Contact, before the scheduled closing time for filing Bids. Then, if in the judgment of the Procurement Manager, additional, information or interpretation is necessary, such information will be supplied in the form of an Addendum, and will be delivered to all individuals, firms and corporations who have received the Contract Documents. Such Addendum shall have the same binding effect as though contained in the main body of the Contract Documents. Oral instructions or information concerning the contract documents or the project given out by officers, employees, or agents of the owner to prospective bidders shall not bind the owner. If no request is made in the five working days or the designated time, Bidder waives right to any conflict in the Contract Documents.

2.4. All applicable laws, ordinances and the rules and regulations of all authorities having jurisdiction over construction of the Project shall apply to the Contract throughout. Further, the Bidder agrees to abide by the following federal requirements: Executive Order No. 11246 as amended, including specifically the provisions of the Equal Opportunity Clause, the Immigration Reform and Contract Act of 1986 and the Americans with Disabilities Act of 1991.

As a recipient of Federal funds, subject to United States Department of Transportation Title VI Regulations at 49 CFR Part 21 the Civil Rights Act of 1964, the City of Wheat Ridge, and its responsible agents, contractors and consultants assure that no person shall on the grounds of race, color, or national origin be excluded from participation in the opportunity to bid or be discriminated against in consideration of award of this project.

Disadvantaged business enterprises will be afforded full opportunity to submit bids in response to all invitations subject to the Regulations. The United States has a right to seek judicial enforcement with regard to any matter arising under Title VI, 49 CFR Part 21 and assurances.

2.5. Bidder must complete and submit the Contractor Qualification Form provided with the bid document. Failure to complete this form and submit with bid may result in the disqualification of the contractor. The City’s acceptance of this bid shall be based on information provided by the contractor in this form. Bid amount and qualification shall be evaluated after bid opening to determine the successful bidder. The City does not pre-qualify contractors.

3. CONTRACT AWARD

3.1. The Owner may make such investigations as deemed necessary to determine the ability of the Bidder and

Subcontractors to perform the Work, and the Bidder shall furnish to the Owner all such information and data for this purpose as the Owner may request. The Owner reserves the right to reject any Bid if the evidence submitted, or investigation fails to satisfy the Owner that such Bidder or any Subcontractor is properly qualified to carry out the obligations of the Agreement. If the owner rejects any Subcontractor as unqualified, the Bidder may substitute another Subcontractor for approval by the Owner but no change to the Bid Price will be allowed.

3.2. The Award of Contract, is anticipated, within 60 calendar days after the opening of bids to the lowest most responsive, responsible qualified bidder whose bid complies with all the requirements of this request for bids.

Evaluation and award will only include the alternate if the base bid and the alternate price combined are

ITB-25-022-2025 Residential Streets 6 within the advertised cost range. If more than one alternate, the order or the selection of the alternates for award is at the discretion of the City. Award is in the best interest of the City.

3.3. The successful bidder shall be notified of the recommendation for award and to provide signed agreements, insurance, and bonds. A Performance Bond and Payment Bond, each in the amount of 100 percent (100%) of the Contract Price, with a corporate surety approved by the Owner, will be required for the faithful performance of the Contract. Securities may not be substituted for Payment or Performance Bonds. Attorneys-in-Fact who sign Payment and Performance Bonds must file with each Bond a certified and effective dated copy of their Power of Attorney.

3.4. The successful bidder shall return copies of the executed Agreement and acceptable Performance and Payment Bonds by a designated date. In case the Bidder fails to comply by the designated date or if the Bidder fails to provide acceptable bonds, the Owner may, at its option, consider the Bidder in default, in which case the Bid Bond accompanying the Proposal (Bid) shall become the property of the Owner.

3.5. The Owner, within 10 working days of receipt of the requirement stated in 3.3 above, shall execute the Agreement and issue the Notice to Proceed at a pre-construction meeting with the Contractor. If the Owner cannot issue the Notice to Proceed within such time period, the time period will be extended by mutual agreement between the Owner and Contractor. If the Notice to Proceed has not been issued within the 10 working day period or within the period mutually agreed upon, the Contractor may terminate the Agreement, by Written Notice, without further liability on the part of either party.

3.6. Upon receiving notice of award, the Contractor may obtain from the City three sets of documents at no cost.

Additional sets of drawings and specifications may be purchased on a cash sale basis from the City. The Contractor and the Owner will agree on the date that Work will commence which shall be within 10 working days of the date of the Notice to Proceed, unless a time extension is approved by the Owner.

3.7. Section 2-3 (a) – (e) of the City's Code of Laws is presented below:

(a) Fiscal year. Fiscal year for the City shall commence on January 1 and end on December 31.

(b) Budget contains appropriations. The City Council shall annually adopt a budget in a manner consistent with the provisions of Chapter X of the Home Rule Charter of the City of Wheat Ridge.

Upon the annual adoption by the City Council of each fiscal year's budget, levels of authorized expenditures from the funds indicated within the annual budget itself and/or the adopting resolution shall constitute the appropriation of the amounts specified therein for the purposes specified therein. During the course of each fiscal year, approval by the City Council of contracts for goods or services, and/or approval of bids for the provision of specified goods or services, shall likewise constitute appropriations of the amounts specified therein for the purposes specified therein.

(c) No contract to exceed appropriation. During each and any fiscal year, no contract entered into by or on behalf of the City shall expend or contract to expend any money, or incur any liability, nor shall any contract be entered into nor any bid be awarded by or on behalf of the City which, by its terms, involves the expenditure of money for any of the purposes for which provision is made either in the adopted budget or adopting resolution, including any legally authorized amendments thereto, in excess of the amount appropriated in the budget or the approved contract or bid award. Any contract or bid award, either verbal or written, made in violation of the provisions of this section shall be void as to the City and no City monies from any source whatsoever shall be paid thereon.

(d) Amendments and authorized expenditures. Nothing contained herein shall preclude the city council from adopting a supplemental appropriation in a manner consistent with the provisions of Section

10.12 of the Home Rule Charter of the City. Further, nothing contained in this section shall prevent the making of contracts for governmental services or for capital outlay for a period exceeding one

(1) year if such contracts are otherwise allowed by the Home Rule Charter of the City; provided, however, any contract so made shall be executory only for the amounts agreed to be paid for such services to be rendered in succeeding fiscal years.

(e) Notice to parties contracting with the City. All persons contracting with, or selling goods or services to, the city are hereby placed upon notice of the provisions of this section. The provisions of this

ITB-25-022-2025 Residential Streets 7 section shall become a part of the Merit System Personnel Rules and Regulations of the City of Wheat Ridge; shall be referred to specifically in all public works bid documents and contracts; and shall be incorporated into, and specially noted within, all other contracts entered into by or on behalf of the City wherein City funds are used to pay for said contract.

3.8. Section 2-4 of the City Code of Laws is presented below:

(a) The city may, by contract, require the contractor awarded a public works contract to waive, release or extinguish its rights to recover costs or damages, or obtain an equitable adjustment, for delays in performing such contract if such delay is caused, in whole or in part, by acts or omissions of the City or its agents, if the contract provides that an extension of time for completion of the work is the contractor's remedy for such delay. Such a clause is valid and enforceable, any provision of state law to the contrary notwithstanding.

(b) The City Council, by this ordinance (Ordinance No. 812), declares its local contracting powers to be a matter of purely local concern, and further specifically intends to supersede, pursuant to its powers under Article XX of the Colorado Constitution, the provisions of Sections 24-91-101 and 24- 91-103.5, C.R.S., insofar as they conflict with the provisions of this section of the Code of Laws of the City of Wheat Ridge, Colorado.

3.9. To the extent that the agreement may be executed and performance of the obligations of the parties may be accomplished within the intent of the agreement, the terms of this agreement are severable.

Should any term or provision hereof be declared invalid or become inoperative for any reason, such invalidity or failure shall not affect the validity of any other term or provision hereof. The waiver of any breach of a term hereof shall not be construed as a waiver of any other term, or the same term upon subsequent breach.

ITB-25-022-2025 Residential Streets 8

GENERAL PROVISIONS

1. DEFINITIONS:

"City" (also sometimes referred to as "Owner") means the City of Wheat Ridge, Colorado. The City is represented by employees who will assume Project administration, oversight, and inspection responsibilities as further defined in the Contract, the General and Special provisions, and the current edition of CDOT Standard Specifications for Road and Bridge Construction. At the time of the preconstruction meeting, or when requested by the Contractor, the City shall provide an official list of City representatives and their titles as applies to the Project.

"Contractor" means the person, partnership, firm or corporation responsible for the physical accomplishment of the project.

"Subcontractor" means only those having a direct contract with the Contractor and includes one who furnished materials worked to a special design according to the plans or specifications for the work under the Contract, but does not include one who merely furnishes material not so worked.

"Notice" means written demand, instruction or order duly served. Written notice shall be deemed to have been duly served if delivered in person to the Contractor, or if delivered in person or sent by registered mail to the address given in the Contract and shall have been duly served upon the City if delivered to the City Clerk of the City of Wheat Ridge, Municipal Building, Wheat Ridge, Colorado, either in person or by registered mail.

"Work" means performance of the Contractor or Subcontractor including labor and materials and all services incidental thereto.

"Cost" means all charges and expenditures of every kind applicable to the accomplishment of the work.

"Final Completion" means when all items are one hundred percent (100%) complete and when all known defective work has been corrected as certified by the City Representative.

"Substantial Completion Date" is the date on which the City Representative certifies the readiness of the work for beneficial occupancy or use, and is the date for terminating liability for liquidated damages and for determining incentive payments due for early completion.

2. MATERIALS, SERVICES, AND FACILITIES:

The Contractor shall and will, in good workmanlike manner, do and perform all work and furnish and pay for all labor, superintendence, material, utilities, machinery, equipment, tools, transportation, facilities, temporary construction of every nature and all other services and facilities of every nature, except as herein otherwise expressly specified, necessary or proper to perform and complete all the work, within the time stated, in accordance with the plans, drawings and specifications covered by the Contract, and any and all supplemental plans, drawings and specifications. He shall furnish, erect, maintain and remove such construction plant and such temporary works as may be required. It will be the responsibility of the Contractor to locate/negotiate a staging area. The City will not provide a staging area on City owned property. Any work necessary to be performed after regular working hours, on Saturdays, Sundays, or Legal Holidays, shall be performed without additional expense to the City.

3. CONTRACTOR'S TITLE TO MATERIALS:

No materials or supplies for the work shall be purchased by the Contractor or by any Subcontractor subject to any chattel mortgage or under a conditional sale contract or other agreement by which an interest is retained by the seller. The Contractor warrants that he has good title to all materials and supplies used by him in the work, free from all liens, claims or encumbrances.

4. OBSERVATION AND TESTING:

All work performed and all workmanship, equipment and materials used in the construction shall be subject to Observation, examination and test, at any and all times during construction.

5. WEATHER CONDITIONS:

In the event of temporary suspension of work, or during inclement weather or whenever the City shall direct, the Contractor will, and will cause his Subcontractors to, protect carefully his and their work and materials against damage or injury from weather. If, in the opinion of the City, any work or materials have been damaged or injured

ITB-25-022-2025 Residential Streets 9 by reason of failure on the part of the Contractor or any of his Subcontractors to so protect his work, such materials shall be removed and replaced at the expense of the Contractor.

6. EMERGENCY PROTECTION OF LIFE AND PROPERTY:

In case of an emergency which threatens loss of injury or property, and/or safety of life, the Contractor is hereby permitted to act at his own discretion and in a diligent manner without prior instructions from the City to prevent the threatened loss or injury. He shall notify the City immediately thereafter. Any claim for compensation by the Contractor due to such extra work shall be promptly submitted in writing to the City for approval. The amount of any reimbursement claimed by the Contractor shall be determined in the manner provided in Article 9 of this Contract.

7. REPORTS, RECORDS, AND DATA:

The Contractor shall submit to the City such schedule of quantities and costs, progress schedules, payrolls, reports, estimates, records and other data as may be requested concerning work performed or to be performed under this Contract.

8. SUPERINTENDENCE BY CONTRACTOR:

At the site of the work, the Contractor shall employ a construction superintendent or foreman who shall have full authority to act for the Contractor. It is understood that such Representative shall be acceptable to the City and shall be one who can be continued in that capacity for the particular job involved unless he ceases to be on the Contractor's payroll. All directions given to such Representative in the Contractor's absence shall be as binding as if given to the Contractor.

9. CHANGES IN THE WORK:

The City may, at any time, by written order and without notice to the sureties, require the performance of extra work or make changes by altering, adding to, or deducting from the work. The amount of compensation to be paid to the Contractor shall be adjusted accordingly without invalidating the Contract and in accordance with whichever of the following plans the City elects: (1) a price agreed upon, (2) a price based on unit prices of the Contract; or

(3) a price determined by adding fifteen percent (15%) to the reasonable cost of the extra work, addition, alteration, or deduction; provided however, that no additions to the Contract Price shall be agreed upon by, or shall be binding upon the City if the effect of said price increase is to increase the Contract amount beyond the amount of money appropriated by the City Council, as specified in Section 2 3 of the Code of Laws of the City of Wheat Ridge.

In giving instructions, the City may authorize minor changes in the work, not involving extra cost and not inconsistent with the purpose of the project. Otherwise, except in an emergency endangering life or property, no extra work or change shall be made unless in pursuance of a written approved Change Order or RFI response by the City.

10. TIME EXTENSIONS:

The Contractor shall, within seven (7) days from the beginning of any delay, notify the City, in writing, of the causes thereof and the City shall ascertain the facts, the extent of the delay and notify the Contractor of the decision in the matter.

The completion time shall be extended when delay in completion of the work by the Contractor is due to unforeseeable causes beyond his control and without his fault or negligence, including, but not restricted to, acts of God or the public enemy, acts or neglect of the City, acts of neglect of any other contractor, fires, floods, epidemics, quarantine restrictions, strikes, riots, civil commotions or freight embargoes. The time of completion of his work shall be extended by such time as shall be fixed by the City.

No such extension of time shall be deemed a waiver by the City of its right to terminate the Contract for abandonment or delay by the Contractor as herein provided or relieve the Contractor from full responsibility for performance of his obligations hereunder. The City's liability for delay shall be limited pursuant to the provisions of Section 2-4 of the Code of Laws of the City of Wheat Ridge and shall be limited to granting a time extension to the Contractor.

ITB-25-022-2025 Residential Streets 10

11. DEFECTIVE WORK:

The observation of the work by the City shall not relieve the Contractor of any of his obligations to fulfill his Contract as herein prescribed, and defective work shall be made good, and unsuitable materials may be rejected, notwithstanding that such work and material have been previously overlooked by City representative(s) and accepted or estimated for payment or paid for. If the work or any part thereof shall be found defective or at any time before the final acceptance of the whole work, or the final payment therefore, the Contractor shall forthwith make good such defect in a manner satisfactory to the City and if any material brought upon the ground for use in the work, or selected for the same, shall be condemned by the City as unsuitable, the Contractor shall forthwith remove such materials from the vicinity of the work and shall replace, at his own expense, damaged or unsuitable materials with the new materials of satisfactory quality.

Neither the foregoing nor any provision of these Contract Documents, nor any special guarantee time limit, shall be held to limit the Contractor's liability for defects to less than the legal limit of liability in accordance with the law of the place of the construction.

The Contractor shall pay the City all expenses, losses, and damages as determined by the City incurred in consequence of any defect, omission, or mistake of the Contractor or his employees or the making good thereof.

12. UNEXPECTED UNDERGROUND STRUCTURES; CHANGE OF CONDITIONS:

Should the Contractor encounter underground structures at the site materially differing from those shown on the Plans or indicated in the Specifications, he shall immediately give notice to the City of such conditions before they are disturbed. The City will thereupon promptly investigate the conditions, and if it is determined that they materially differ from those shown on the Plans, may authorize changes to be made to the Plan and/or Specifications as may be necessary.

It is understood and agreed that the Contractor has considered in his bid all of the permanent and temporary utility appurtenances in their present or relocated position as shown on the plans and that additional compensation will not be allowed except for any unreasonable delays, or damage sustained by him due to any interference from the said utility appurtenances. Unreasonable delays shall constitute delays caused by a complete shutdown of all operations. It is understood that utilities are not owned, operated or controlled or subject to control by the City of Wheat Ridge. Relocations of facilities owned by said utilities are not a matter over which the City has control. The Contractor shall adjust his schedule in anticipation of such delays so that work in other areas may be completed away from the area of utility conflict.

The locations of all utilities shown on the Project plans should be considered approximate. It is therefore the responsibility of the Contractor to notify the appropriate utility and obtain more precise locations. No compensation will be made to the Contractor for any damage, delay or additional cost incurred as a result of failure to obtain utility locations.

Information on the Plans in the Contract Documents referring to the existence of utilities or other underground structures is not guaranteed to be correct or to be a complete representation of all existing data. Every effort has been made, however, to make this information complete and accurate on the basis of all data and information which could be procured by the City. The Contractor shall make his own examination and shall draw his own conclusions as to the underground facilities which will be encountered, and he shall have no claim for damages of any kind on account of any errors, inaccuracies or omission that may be found.

There shall be no adjustment in Contract Price based on changed site conditions. The Contractor is required hereby to make an on site inspection and investigation, which includes determination of location of utilities and said and other natural conditions. Representations regarding site and soil conditions and utility locations are based on the best information available to the Owner and final determination as to both site and soil conditions and utility locations is left to the Contractor, without recourse to the City. The City shall allow reasonable and necessary access to the site to Contractor and his representatives to make such determination and site review.

13. CLAIMS FOR EXTRA COSTS:

No claim for extra work or cost shall be allowed unless the same was done in pursuance of written order of the City, as provided for in Article 9, and the claim was presented prior to the issuance of the final payment. When work is performed under the "reasonable cost" method as outlined in Article 9 of the General Conditions, the Contractor shall furnish satisfactory bills, payrolls and vouchers covering all items of cost, and when requested by the City, give the City access to accounts relating thereto.

NO adjustments will be allowed for fuel cost of asphalt cement.

ITB-25-022-2025 Residential Streets 11

14. RIGHT OF CITY TO TERMINATE CONTRACT:

If (1) the Contractor or any of his Subcontractors shall be adjudged bankrupt or (2) if he shall make a general assignment for the benefit of his creditors or (3) if a receiver shall be appointed of his property, or (4) if the work to be done under this Contract shall be abandoned, or (5) if this Contract or any part hereof shall be sublet, without the previous written consent of the City, or (6) if the Contract or any claim thereunder shall be assigned by the Contractor otherwise than as herein specified, or (7) at any time the City shall certify in writing that the rate of progress of the work or any part thereof is unsatisfactory or (8) that the work or any part thereof is unnecessarily or unreasonably delayed, or (9) that the Contractor, his subcontractors, agents or employees have violated any of the provisions of this Contract, or of the plans and specifications, or construction schedule, the City shall notify Contractor and the Surety, and shall be entitled immediately to terminate the Contract. The Surety shall have the right to take over and perform the Contract, provided, however, that if the Surety does not commence performance thereof within ten (10) days from the date of the mailing to such Surety of notice of termination, the City may take over the work and prosecute the same to completion by contract or by force account for the account and at the expense of the Contractor, and the Contractor and his Surety shall be liable to the City for any excess cost occasioned the City thereby, and in such event the City may take possession of and utilize in completing the work, such materials, machinery, appliances and plant as may be on the site of the work and necessary therefore. The Contractor, by signing this Contract, gives to the City in the event of default, right to use such aforesaid articles to the full extent which they could be used by the Contractor. The City shall not be liable to the Contractor for trespass or conversion.

All expenses charged under this article shall be deducted and paid for by the City out of money then due to become due the Contractor under this Contract or any part thereof, and in such account the City shall not be held to obtain the lowest figures for the work of completing the Contract or any part thereof or for insuring its proper completion, but all sums actually paid hereafter shall be charged to the Contractor and his Surety. In case the expenses so charged are less than the sum which would have been payable under this Contract if the same had been completed by the Contractor, the City shall be entitled to retain the difference and in case such expenses shall exceed the said sum, the Contractor and his Surety shall pay the amount of the excess to the City upon completion of the work without further demand being made therefore.

15. CONSTRUCTION SCHEDULE:

Before any work is begun, the Contractor shall provide to the City a written schedule detailing the order and manner of doing the work. Before the first partial payment is made, the Contractor shall deliver to the City an estimated construction progress schedule in form satisfactory to the City, showing the proposed dates of commencement and completion of each of the various subdivisions of work required under the Contract. The Contractor shall provide an updated schedule every 30 days.

16. PAYMENTS TO THE CONTRACTOR:

During the course of construction, the Contractor shall request payment of work actually performed during the preceding month. The City will once each month make a progress payment to the Contractor on the basis of an evaluation of the claim by the City as to amount of work done and that the City has received full value thereof. In accordance with House Bill 11-1115, the City shall retain five percent (5%) of the value of the completed work.

Retainage shall be held until final completion and acceptance of all work, as part security for the fulfillment of the Contract by the Contractor. The amount of the progress payments shall be the balance not retained as aforesaid, after deducting all previous payments and all other sums to be kept or retained under the provisions of this Contract. The Contractor shall have no right to either terminate the Contract or to claim damages if he considers partial payments inadequate.

17. CERTIFICATE OF COMPLETION:

Upon completion of all work whatsoever required including completion of all known defective work, the City shall file a written certificate with the Contractor as to the entire amount of work performed and compensation earned by the Contractor including Extra Work and compensation therefore, and including the date of completion.

18. FINAL PAYMENT:

After the filing of the Certificate of Completion, the City shall pay to the Contractor in accordance with applicable Colorado laws (Article 38, Chapter 26, Section 101 Et. Seq. Colorado Revised Statutes) and C.R.S. 38-26-107 (2012), upon authorization of funds disbursement by the City Council the amount therein stated, less all prior payments

ITB-25-022-2025 Residential Streets 12 and advances whatsoever, to or for the Account of the Contractor. All prior estimates and payments including those relating to extra work shall be subject to correction by this payment.

19. PAYMENT WITHHELD:

The City, as a result of subsequent discovered evidence, may withhold or nullify the whole or a part of any payment to such extent as may be necessary to protect the City from loss on account of:

(a) Defective work not remedied.

(b) Claims filed or reasonable evidence indicating probable filing of claim.

(c) Failure of the Contractor to make payments properly to Subcontractor or for material or labor, or to comply with laws relative thereto.

(d) A reasonable doubt that the Contract can be completed for the balance then unpaid.

(e) Damage to another Contractor.

(f) Damage to the real or personal property of another and failure to repair or replace the same.

When the grounds for withholding payment have been corrected to the satisfaction of the City, the City shall proceed to process any amounts due.

20. FINAL PAYMENT TO TERMINATE LIABILITY OF CITY:

The acceptance by the Contractor of the last payment made as aforesaid under the provisions of Article 19 shall operate as and shall be a release to the City, its officers, or agents from all claims and liability to the Contractor, his vendors, laborers or Subcontractors for anything done or furnished for, relating to, or for any act or neglect of the City or of any persons relating to, or affecting the work, except the claim against the City for the remainder, if any there be, of the amounts kept or retained as provided in Article 17, 19 and 20 of these. Said acceptance shall also operate as a general release of the City by the Contractor.

21. EFFECT OF CERTIFICATION AND PAYMENT:

Neither the certification nor payment made to the Contractor, not partial or entire use or occupancy of the work by the City shall be an acceptance of any work or materials not in accordance with the Contract. The making and acceptance of the final payment shall constitute a bar of all claims by the Contractor, except those previously made in writing and still unsettled.

22. GENERAL WARRANTY:

The Contractor shall guarantee the work against defective materials or workmanship for a period of one (1) year from the final completion date. Upon discovery of any defects including any damage to other work resulting, repair and replacement that is required, in the opinion of the City, shall be done immediately by the Contractor at the Contractor's expense. Should the Contractor fail to repair such defective material and/or workmanship, or to make replacement within five (5) days after written notice by the City, it is agreed that the City shall make such repairs and replacements and the actual cost of the required labor and materials shall be chargeable to and payable by the Contractor.

23. INSURANCE:

The Contractor shall maintain general liability and property damage insurance (the “Liability Policy”) to protect the Contractor and the City from any and all claims for damages including but not limited to claims for property damage and bodily injury, including death, which may arise from operations under this Contract, including the operations of subcontractors. The Liability Policy shall state that it is the primary insurance for such claims and shall not contain any “excess” or “other insurance” clauses which limit its application as the primary coverage for those claims. The Contractor shall be individually liable for any and all defects in the Liability Policy. The Liability Policy shall not be terminated or cancelled prior to the completion of this Contract without at least 45 days prior written notice to the City.

For bodily injury $500,000 each person/ $500,000 each accident/ $500,000 each disease For property damage $1,000,000 for each occurrence For automobile liability $1,000,000 combined single limit

ITB-25-022-2025 Residential Streets 13

In lieu of the foregoing, a single limit public liability policy for personal injury, property and/or vehicle damage will be accepted in the amount of $2,000,000.00.

Such insurance shall be without prejudice to coverage otherwise existing, and shall name as additional insured, the City of Wheat Ridge, its officers and employees, and the Colorado Department of Transportation.

Notwithstanding the naming of additional insured, the said policy shall protect each insured in the same manner as though a separate policy had been issued to each, but nothing herein shall operate to increase the insurer's liability as set forth elsewhere in the policy beyond the amount or amounts for which the insurer would have been liable if only one person or interest had been named as insured. A certificate evidencing such insurance, together with the proper endorsement, shall be filed, subject to approval as to the adequacy of protection.

Fire and Standard Extended Coverage Insurance -- The Contractor shall insure the work for 100 percent (100%) of the replacement value thereof for the life of the Contract against all loss or damage covered by the Standard Extended Coverage Insurance endorsement, including theft, vandalism, and malicious mischief, with an insurance company or companies acceptable to the City. The amount of the insurance may vary with the extent of the work completed but shall at all times be at least equal to the replaceable value of the amount paid for the work and materials installed and delivered plus the replaceable value of the work or materials furnished or delivered, but not yet paid for by the City. The insurance policy or policies shall be held jointly in the name of the City and Contractor as their respective interest may appear.

The issue, if any, shall be made adjustable with and payable to the City as a trustee for whom it may concern. Any payments made under such policy shall insure to the benefit of the City to the extent of balance for replacement of the loss suffered. The policy of insurance shall provide that it shall not be terminated or be canceled prior to the completion of this Contract. The Contractor shall be responsible for all damage to the work under construction, whether from fire, water, high winds or other cause during construction and until final completion and acceptance, even though partial payments or progress payments have been made under the Contract.

Workers' Compensation Insurance -- The Contractor shall provide workers' compensation insurance coverage for all persons employed on the work to be done under the Contract and assure that all workers will receive the compensation for compensable injuries.

Certificates of Insurance shall be attached to the executed Contract Documents and shall become a part of the Contract. These Certificates shall include a provision that thirty (30) days prior to insurance cancellation, written notice shall be given to the City of Wheat Ridge.

Indemnification of City -- Contractor hereby indemnifies and agrees to hold the City and its representatives and agents harmless for and on account of any act or omission in the completion and execution of the project specified herein, which indemnification shall extend to and include any damage of whatever sort or description, suffered by any person or entity, and shall include compensatory, punitive or special damages; and Contractor agrees to defend City hereunder, at Contractor's sole expense and if he fails to do so, to thereafter indemnify City, in addition to the above indemnification, for all court costs and attorney fees incurred in any defense required to be undertaken by the City.

Notwithstanding the foregoing, nothing contained herein shall be deemed a waiver by the City of any of the protections afforded the City by virtue of the provisions of the Colorado Governmental Immunity Act (Colo. Rev.

Stat. 24 10 101).

24. RESPONSIBILITY FOR WORK; PRIORITY OF DOCUMENTS:

(a) Debts and claims: The Contractor shall pay all debts for labor and materials contracted for by him on account of the work herein contemplated. The Contractor shall assume the defense of, and indemnify and save harmless, the City and its officers and agents, from all claims relating to labor and materials furnished for the work; to infringement or alleged infringement of invention patents and patent rights used in, or in connection with the work or however originating from any of the work under this Contractor from conditions created thereby; to injuries to any persons or corporation caused by the acts or negligence of the Contractor or any of his agents or employees, or of any Subcontractor or any agents or employees of any Subcontractors, in doing the work or in consequence of any improper materials, implements or labor used therein; and shall fully reimburse and repay to the City all outlay and expense which the City may incur by reason of his failure to do so. The Contractor shall satisfy all suits and claims against the City arising from

ITB-25-022-2025 Residential Streets 14 the violation of any law, ordinance, regulation, order, or decree on the part of the Contractor or any of his agents or employees, or any Subcontractor, or agent or employees of any Subcontractor; shall fully indemnify and save harmless the City against and from all cost, loss, and damage which the City may suffer by reason of his failure to do so; and shall fully reimburse and repay to the City all outlay and expense which the City may incur in making good any such default. The Contractor shall fully complete the work required to be done under this Contract, free from all liens and claims of any kind whatsoever.

(b) Plans and Specifications: It shall be the duty of the Contractor to carefully study and compare all drawings, specifications and instructions, visit the project site and acquaint himself with all conditions, and call to the attention of the City any discrepancy, error, omission or inconsistency that may exist in the plans or specifications, or between the plans and specifications, or any conflict between existing conditions and requirements of the plans and specifications. The execution or work in accordance with the plans, specifications or other instructions will be considered as evidence that the Contractor is thoroughly familiar with the true intent of the plans, specifications or other instructions. Change orders will not be issued to cover any cost, loss, or expense for additional labor or material required to rectify any discrepancies discovered or reported to the City after the execution of the work, unless the discrepancies are errors in structural, mechanical or electrical design as determined by the City.

(c) Priority of Documents: In case of discrepancy or inconsistency in the terms or conditions of any documents, the Contract Documents shall have the following order of priority, in accordance with Subsection 105.09, such that a statement appearing in the document with the higher priority shall control any inconsistent statement in a document of lower priority. (The following are listed from the highest priority to the lowest priority):

i. The Agreement

ii. Special Provisions

iii. Drawings and any notes appearing on the drawings

iv. Current edition of CDOT Standard Specifications for Road and Bridge Construction and all supplements thereto (English Version).

v. General Provisions of the Contract for construction.

25. CARE AND PROTECTION OF PROPERTY:

The Contractor expressly undertakes expense:

To assume full responsibility for the preservation of all public and private property, and use every precaution necessary to prevent damage thereto. If any direct or indirect damage is done to public or private property or on account of any act, omission, neglect or misconduct in the execution of the work on the part of the Contractor, such property shall be restored by the Contractor, at their expense, to a condition similar or equal to that existing before…