QA_Answers.pdf

PDF 107 KB Posted

Attached to
S&RTS BAR, MONTENEGRO Federal contract opportunity
Solicitation number
HTC71121QR013
Issued by
Department of Defense United States Transportation Command

View the file

Other files for this federal contract opportunity

Other files attached to S&RTS BAR, MONTENEGRO, newest first.
File Type Posted
HTC71121QR013_Amd 4.pdf PDF
Atch_2_SORv3 - Bar Montenegro_3-16-21.xlsx XLSX spreadsheet
HTC71121QR013_Amd 3.pdf PDF
Atch_2_SORv3 - Bar Montenegro_3-11-21.xlsx XLSX spreadsheet
HTC71121QR013_amd 2.pdf PDF
Atch_4_Technical Evaluation Criteria (Bar) 3-2-21.docx DOCX document
Atch_2_SORv2 - Bar Montenegro_3-2-21.xlsx XLSX spreadsheet
HTC71121QR013_Amd 1.pdf PDF
Synopsis_Bar Montenegro.pdf PDF
Bar Montenegro_QASP_Final_LH_5Feb2021.pdf PDF
HTC71121QR013.pdf PDF
Atch_1_PWS-v2 Bar Montenegro_2-4-21 (1).pdf PDF
Atch_4_Technical Evaluation Criteria (Bar) 2-4-21.docx DOCX document
Atch_3_RFQ Information Sheet.docx DOCX document
Atch_2_SORv2 - Bar Montenegro_2-4-21.xlsx XLSX spreadsheet
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP Citation, if provided QUESTIONS ANSWERS

1 SF1149, page 15 of 40, para 3. (3)

In Section SF1149, page 15 of 40, para 3. (3) states that following provisions must be included in our SAM record or submitted separately. At this point we are not able to update our SAM record, can we submit required info separately?

Yes, quoters may submit information typically entered into SAM separately, however the information must be in SAM prior to award.

2 FAR 52.204-24 and FAR 52.209-7 are not included by full text in the solicitation. Should we find them in the web, print them, fill in whatever is needed and send them as an attachment?

FAR 52.204-24 has now been updated as full text. FAR 52.209-7 is not required to be in full text, therefore has not been updated. You can view all provisions and clauses at https://www.acquisition.gov/

3 SF1149, page 19 of 40, Under the same para, FAR 52.212-3 is listed twice with different dates (NOV 2017) and (Alt I) (Oct 2014), whereas same number FAR 52.212-3 is listed in the solicitation in page 19 of 40 with date (JAN 2021).

FAR 52.212-3 has been updated to Feb 2021. FAR 52.212-3 (Alt I) is required for all DoD contracts, and reflects the correct date.

4 Technical Worksheet Technical Worksheet, para 3a: It is erroneously noted the Port of Esbjerg. The Technical Worksheet has been corrected to read Bar, Montenegro.

5 SOR

Section SOR, schedule 3C , Line item 192 thru 199 states Guarantee Time, whereas there is no such a term in the PWS. Assume it should state shift differential.

There is no guaranteed time, the schedule has been removed.

6 SOR Section SOR, schedule 3B, description of services is listed twice. Schedule 3B is listed twice to reflect overtime differential for regular Overtime AND Holiday Overtime.

7 SOR

Section SOR, schedule 6, Line item 231 states combination of both… Please clarify if you mean 20’and 40’ container. Price should be separated by 20’ and 40’, as there is a big difference, due to the cubic difference.

Schedule 6, line item 231 has been corrected to read 20' box.