Amendment 0006.pdf
PDF 37 KB Posted
- Attached to
- Portable Steam Trailers Federal contract opportunity
- Solicitation number
- HSCG87-08-Q-643361
About this file
Amendment 0006
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0008.pdf | ||
| Amendment 0007.pdf | ||
| Amendment 0005.pdf | ||
| Amendment 0004.pdf | ||
| Amendment 0003.pdf | ||
| Amendment 2.PDF | ||
| Amendment 0001.pdf | ||
| HSCG87-08-Q-643361.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
1 4
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
07/28/2008
4. REQUISITION/PURCHASE REQ. NO.
2108878643361
5. PROJECT NO. (If applicable)
633678
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
COMMANDING OFFICER (ko)
CIVIL ENGINEERING UNIT
FEDERAL BLDG. RM 817, 709 W. 9th ST.
P.O. BOX 21747
JUNEAU, AK 99802-1747
9A. AMENDMENT OF SOLICITATION NO.
HSCG87-08-Q-643361
9B. DATED (SEE ITEM 11)
06/26/2008
10A. MODIFICATION OF CONTRACT/ORDER NO.
8. NAME AND ADDRESS OF CONTRACTOR (NO., STREET, COUNTY, STATE AND ZIP CODE)
All Prospective Quoters
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
PORTABLE STEAM BOILER PLANTS FOR ISC KODIAK, ALASKA
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE REFERENCED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET
FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (SPECIFY TYPE OF MODIFICATION AND AUTHORITY)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
RFQ HSCG87-08-Q-643361 FOR PORTABLE STEAM BOILER PLANTS FOR ISC KODIAK, ALASKA, IS AMENDED TO ADDRESS TECHNICAL QUESTIONS BROUGHT ABOUT BY THE SPECIFICATIONS IN THE RFQ. SEE ATTACHED PAGES 2-4 FOR TECHNICAL QUESTIONS AND ANSWERS. THE DATE THAT QUOTES ARE DUE IS NOT CHANGED
AND REMAINS COB 8/01/2008 AS SPECIFIED IN AMENDMENT 0005 DATED 24 JUL 2008.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or Print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
RONALD L. KLAUDT, CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED
16B UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
NSN 7540-01-152-8070 STANDARD FORM 30 (Rev. 10-83) PREVIOUS EDITION UNUSABLE Prescribed by GSA
FAR (48 CFR) 53.243
AMENDMENT 0006 PAGE 2 OF 4
REQUEST FOR QUOTATION (RFQ) HSCG87-08-Q-643361
TECHNICAL QUESTIONS AND CLARIFICATIONS
1. What is the parking space dimensions, that the boiler needs to fit into?
Answer: length 20’ x width 10’
2. What is the maximum towing weight limit for the portable boiler (basically, what is the towing capacity of your pickup trucks?)?
Answer: 8,500 lb dry weight. If you do not drain the water out before you move the boiler then this weight needs to include water in the boiler and feed water tank and we will need to say so.
3. The portable boiler shall be mounted in an enclosed trailer. In the specification replace the word "van" with enclosed trailer.
The enclosed trailer shall have a 2-1/2" ball hitch.
The portable boiler shall have a maximum towing weight of 8,500 lb dry (when boiler/ feed water tank filled with water?)
The Coast Guard intends to pull the portable boiler with a 3/4" ton pickup truck.
Answer: Clarification only
4. The boiler and boiler system equipment shall not be skid mounted.
5. In paragraph 2.8.1 the "new freestanding 17' inside trailer" means a new enclosed freestanding trailer that has an inside length of 17'.
The trailer shall fit in a parking space that is 20 ft long x 10 ft wide.
6. Delete hose reels from the contract.
7. Is it intentional that softeners and chemical treatment was omitted from the contract?
Answer: Yes this is intentional.
AMENDMENT 0006 PAGE 3 OF 4
8. 2.1.5 The gas analyzer is a separate piece of equipment, not integral to the controls, is this sufficient?
Answer: Delete the gas analyzer.
9. Does the Coast Guard want a printer with the analyzer?
Answer: See above, gas analyzer is deleted.
10. Does the Coast Guard want an LCD readout with the volumetric steam flow meter?
Answer: We do not want a LCD readout on the steam flow meter.
11. 2.2 Does the Coast Guard want a blowdown separator/tank
Answer: No.
12. 2.3.3 Would centrifugal pumps (e.g. -grundfos) be acceptable?
Answer: Centrifugal pumps are acceptable.
13. 2.6 What will available voltage be for outside connection? 208 / 240 / 480 / multiple?
Answer: The specification states in section 2.8.1 that the trailer shall be designed for 208/120/3/60.
14. 2.7.2B A 60 gallon oil tank will run a 50 hp boiler for approx. 4 hours at high fire. Is this adequate for the government?
Answer: 60 gallon tank will be adequate for our purposes.
15. 2.8.1 17’ inside space is a nominal 20’ in shipping containers.
Is this adequate for the Coast Guard?
Answer: The specification has been clarified above. The trailer shall be an enclosed trailer vice a van trailer; the trailer shall be new;
the trailer shall have a 2-1/2 ball hitch; it is the intent of the Coast Guard to pull the trailer with a 3/4 ton pickup truck. The inside length of the trailer shall be 17'. The trailer shall fit in a parking space of the dimensions defined above.
AMENDMENT 0006 PAGE 4 OF 4
16. NEW trailers / shipping containers are nearly impossible to find in the US. Most all ship from China filled. Most all trailers / containers available on the market are once used, but considered “new”.
Is this adequate for the Coast guard.
Answer: We want new trailers.
17. 2.8.2 Noise not to be in excess of 80 dpA. At what range?
Answer: Noise shall not exceed 80 dpA at a distance of 3'from the trailer.
18. 2.8.3 Calls for hose connections to be 1.5”, however, 2.1.11 calls for steam connection points to be 3”. Is this correct? Will government supply reducing fittings?
Answer: The contractor shall provide reducing fittings.
19. 2.1.1 states a Scotch Marine Type steam boiler. Is this a manufacturer of boilers?
Answer: No, it is a type of boiler