Specification_OSAGE_(WLR_65B)_DD_FQ4_BMM_16R0.pdf
PDF 2 MB Posted
- Attached to
- CGC OSAGE IRESS DRY DOCK Federal contract opportunity
- Solicitation number
- HSCG85-16-Q-P45A06
About this file
Specification Rev-0 dated 8 February 2016
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A0001_Amendment_to_a_Sol.pdf | ||
| Section_B_SOS.xls | XLS spreadsheet | |
| Solicitation_Amended_OSAGE_FY16DD.docx | DOCX document | |
| Past_Performance_Questionnaire_OSAGE.doc | DOC document | |
| Specification_OSAGE_(WLR_65B)_DD_FQ4_BMM_16R0.pdf | ||
| Solicitation_OSAGE_FY16_DD.pdf | ||
| Past_Performance_Questionnaire_OSAGE.doc | DOC document | |
| Section_B_SOS.xls | XLS spreadsheet | |
| Request_for_Clarification_doc.docx | DOCX document | |
| OSAGE_(WLR_65B)_DD_FQ4_BMM_16ER0_BLANK.xls | XLS spreadsheet | |
| OSAGE_(WLR_65B)_DD_FQ4_BMM_16R0_Specification.pdf | ||
| Pre_Solicitation.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC OSAGE (WLR 65505)
USCG 100 BARGE (99003)
SPECIFICATION FOR DRYDOCK REPAIRS
FY2016
Developed By: Benjamin M Mills
(Rev-0, 08 February 2016)
USCGC OSAGE (WLR-65B) DRYDOCK AVAILABILITY FY2016
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property .............................................................................. viii Consolidated List of Critical Inspection Items .......................................................................................... xiii Principal Characteristics - Tender .............................................................................................................. xiv Principal Characteristics - Barge ................................................................................................................. xv General Requirements WORK ITEM 1: Hull Plating (U/W Body), Inspect - Tender WORK ITEM 2: Hull Plating (U/W Body), Inspect - Barge WORK ITEM 3: Hull Plating (U/W Body), Ultrasonic Testing - Tender WORK ITEM 4: Hull Plating (U/W Body), Ultrasonic Testing - Barge WORK ITEM 5: Tanks (MP Fuel Stowage and Overflow), Clean and Inspect - Tender WORK ITEM 6: Voids (Non-Accessible), Leak Test - Tender WORK ITEM 7: Voids (Non-Accessible), Leak Test - Barge WORK ITEM 8: Voids (Non-Accessible), Internal Surfaces, Preserve - Tender WORK ITEM 9: Voids (Non-Accessible), Internal Surfaces, Preserve - Barge WORK ITEM 10: Keel Coolers, Clean, Inspect and Hydro - Barge WORK ITEM 11: Hull Fittings (Weight Handling Rigging Hardware), Inspect and Test - Barge WORK ITEM 12: Hull Fittings (Mooring and Towing), Inspect and Test - Tender WORK ITEM 13: Hull Fittings (Mooring and Towing), Inspect and Test - Barge WORK ITEM 14: Spuds, Overhaul - Tender WORK ITEM 15: Spuds, Overhaul - Barge WORK ITEM 16: Spud Wells, Preserve - Tender WORK ITEM 17: Spud Wells, Preserve - Barge WORK ITEM 18: Decks – Exterior (Buoy or Construction Deck), Preserve 100% WORK ITEM 19: U/W Body, Preserve (100%) - Tender WORK ITEM 20: U/W Body, Preserve (100%) - Barge WORK ITEM 21: U/W Body, Preserve (Partial - Condition A) - Tender WORK ITEM 22: U/W Body, Preserve (Partial - Condition A) - Barge WORK ITEM 23: U/W Body, Preserve (Partial - Condition B) - Tender WORK ITEM 24: U/W Body, Preserve (Partial - Condition B) - Barge WORK ITEM 25: Drydock - Tender WORK ITEM 26: Drydock - Barge WORK ITEM 27: Temporary Services, Provide – Tender and Barge WORK ITEM 28: Sea Trial Performance, Support, Provide WORK ITEM 29: Main Diesel Engine and Propulsion Shafting, Upgrade WORK ITEM 30: Steering System, Upgrade WORK ITEM 31: Weathertight Doors(External), Renew WORK ITEM 32: Boat Davit Winch, Shrink Wrap WORK ITEM 33: Buoy and Cargo Handling Crane, Shrink Wrap WORK ITEM 34: Bilges, Lead-Based Paint, 100% Abatement, Perform - Tender WORK ITEM 35: Hull Plating Freeboard, Preserve 100% - Barge WORK ITEM 36: Hull Plating Freeboard, Preserve “100%” - Tender WORK ITEM 37: Decks – Exterior (Barge Aft Main Deck), Preserve 100% WORK ITEM 38: Sewage Tank, Renew WORK ITEM 39: Pilot House Bulkhead, Repair WORK ITEM 40: Hull Repair (Barge) iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:
MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm
Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp
Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::
www.gpoaccess.gov
The Government is aware of the following internet web links where contractors may procure commercial specifications:
American Welding Society (AWS): http://www.awspubs.com/index.php
ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/
NFPA: http://www.nfpa.org
SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace
COAST GUARD DRAWINGS
Coast Guard Drawing 65B WD 103-007, Rev C, Booklet of General Plans
Coast Guard Drawing 65 WD 436-001, Rev D, Mods to Pilothouse Alarm Panel
Coast Guard Drawing 65B WD 0500-001, Rev -, Lines and Offsets
Coast Guard Drawing 65 WD 700-004, Rev -, Docking Block Arrangement (“A” & “B” Class)
Coast Guard Drawing 65B WD 1101-001, Rev -, Shell Exp, Bulwk, Railing, Rub Rail, Chocks Bow
Fender
Coast Guard Drawing 65B WD 1101-002, Rev -, Hull Structure and Main Deck Plating
Coast Guard Drawing 65B WD 1101-009, Rev B, Grid Cooler Pockets to suit IF 1312 MDE
Coast Guard Drawing 65B WD 1107-1, Rev -, Main Deckhouse & Upper Deck Plating
Coast Guard Drawing 65B WD 1107-2, Rev -, Upper Deckhouse Wheelhouse and Stack
Coast Guard Drawing 65B WD 1107-003, Rev B, Stack Modifications to suit IF 1312 MDE
Coast Guard Drawing 65B WD 1112-004, Rev B, Main Engine Foundation Modifications to Suit 1312
MDE
Coast Guard Drawing 65B WD 1112-005, Rev B, Miscellaneous Foundations to Suit IF 1312 MDE
Coast Guard Drawing 65B WD 1112-011, Rev -, Pilothouse Console Modifications for JASTRAM
JQ081225A Steering System
Coast Guard Drawing 65B WD 1112-012, Rev -, Miscellaneous Foundation Modifications for JASTRAM
JQ081225A Steering System
Coast Guard Drawing 65B WD 1901-1, Rev -, Painting Insul Sheath and Deck Covering Sched http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace v (Rev-0)
Coast Guard Drawing 65 WD 2200-003, Rev A, Rudder Stock and Fittings for JASTRAM JQ081225A
Steering System
Coast Guard Drawing 65B WD 2200-004, Rev -, Hydraulic Steering System
Coast Guard Drawing 65B WD 2200-006, Rev E, Steering System Controls and Alarms for JASTRAM
JQ081225A
Coast Guard Drawing 65B WD 2200-007, Rev C, Diagram, Steering Hydraulics for JASTRAM
JQ081225A
Coast Guard Drawing 65B WD 2200-009, Rev B, Hydraulic Hose List for JASTRAM JQ081225A
Coast Guard Drawing 65B WD 2200-011, Rev D, Steering System Arrangement and Foundations for
JASTRAM JQ081225A
Coast Guard Drawing 65B WD 2200-012, Rev C, Rudder Post Installation for JASTRAM JQ081225A
Steering System
Coast Guard Drawing 65B WD 2200-013, Rev C, Arrangement, Steering Hydraulics for JASTRAM
JQ081225A
Coast Guard Drawing 65B WD 2402-001, Rev C, Propulsion Control System to suit IF 1312 MDE
Coast Guard Drawing 65B WD 2602-1, Rev -, Spud & Rigging
Coast Guard Drawing 65 WD 2901-003, Rev -, Curves of Form
Coast Guard Drawing 65B WD 3801-006, Rev D, Engine Room Ventilation System Power Mods to suit
IF 1312 MDE
Coast Guard Drawing 65B WD 3801-007, Rev C, Mods to Aft Hold Vent, Insulation and Painting for
JASTRAM JQ081225A
Coast Guard Drawing 65B WD 3801-008, Rev C, Aft Hold Ventilation Power Mods to suit JASTRAM
JQ081225A
Coast Guard Drawing 65B WD 3801-010, Rev -, Engine Room Vent Modifications to suit IF 1312 MDE
Coast Guard Drawing 65B WD 4000-004, Rev B, Machinery Arrgt Mods to suit IF 1312 MDE
Coast Guard Drawing 65B WD 4000-005, Rev B, Equipment Arrangement for JASTRAM JQ081225A
Steering System
Coast Guard Drawing 65B WD 4103-001, Rev -, Propulsion Engine Controls
Coast Guard Drawing 65B WD 4103-005, Rev -, Control Air Piping Mods Incidental to Main Engine
Replacement
Coast Guard Drawing 65B WD 4103-012, Rev A, Jacket Water Piping Mods to suit IF 1312 MDE
Coast Guard Drawing 65B WD 4103-013, Rev -, Misc Piping Mods to suit IF 1312 MDE
Coast Guard Drawing 65B WD 4105-001, Rev B, Remote Engine Shutdown to suit IF 1312 MDE
Coast Guard Drawing 65B WD 4302-001, Rev D, Propeller Shaft and Details
Coast Guard Drawing 65B WD 4302-004, Rev D, Shafting Installation to suit IF 1312 MDE
Coast Guard Drawing 65B WD 4808-3, Rev 1, Secondary Drain System (65505)
Coast Guard Drawing 65B WD 4808-5, Rev 2, Secondary Drainage System (65506)
Coast Guard Drawing 65B WD 4810-006, Rev -, Exhaust Piping Mods to suit IF 1312 MDE
Coast Guard Drawing 65B WD 4823-004, Rev -, Oily Water Holding Tank & Associated Piping
Coast Guard Drawing 65B WD 4903-006, Rev -, Compressed Air Mods to suit IF 1312 MDE
Coast Guard Drawing 65B WD 5501-007, Rev -, Fuel Oil Service Mods to suit IF 1312 MDE
Coast Guard Drawing 65B WD 6201-009, Rev C, Electrical One line Block & Elementary Wiring
Diagram (OSAGE)
Coast Guard Drawing 75 WAGL 4301-005, Rev N, Shafting Machining Details to suit IF 1312 MDE vi (Rev-0)
Coast Guard Drawing 75 WAGL 4301-006, Rev F, Shaft Brake to suit IF 1312 MDE
Coast Guard Drawing 75 WAGL 4400-003, Rev L, Propeller to suit IF 1312 MDE
Coast Guard Drawing 100B CGB 103-3, Rev -, Booklet of General Plans
Coast Guard Drawing 100B CGB 0500-001, Rev 1, Lines and Offsets
Coast Guard Drawing 100B CGB 0700-003, Rev -, Docking Block Arrangement
Coast Guard Drawing 100B CGB 1101-01, Rev 3, Barge Plating and Bill of Material
Coast Guard Drawing 100B CGB 1105-002, Rev 1, Longitudinal Bulkheads & Rake Truss Details
Coast Guard Drawing 100B CGB 1604-1, Rev 2, Ladders, Rails, and Misc Fittings
Coast Guard Drawing 100B CGB 2602-001, Rev 3, Spud Well
Coast Guard Drawing 100B CGB 4103-001, Rev 3, Engine Cooling System
Coast Guard Fleet Drawing FL 2602-10, Rev L, Spud Arrangements and Details
Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem
Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation For Compartments Installation
Details
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 0850 (SFLC Std Spec 0850), 2014, General
Requirements for Drawing Preparation
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2014, Shipboard
Electrical Cable Test
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2014, Shipboard
Electrical Cable Removal, Relocation, Splice, Repair, and Installation
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2014, Auxiliary
Machine Systems
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2014, Install Interior
Deck Covering Systems
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary
Services
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2014, Temporary
Hull Accesses
OTHER REFERENCES
American Welding Society (AWS) D1.1, 2008, Structural Welding Code
ASTM International (ASTM) D882, 2009, Standard Test Method for Tensile Properties of Thin Plastic
Sheeting vii (Rev-0)
ASTM International (ASTM) D1709, 2008, Standard Test Methods for Impact Resistance of Plastic Film by the Free-Falling Dart Method
ASTM International (ASTM) D1922, 2008, Standard Test Method for Propagation Tear Resistance of
Plastic Film and Thin Sheeting by the Pendulum Method
ASTM International (ASTM) D3359, 2009, Standard Test Methods for Measuring Adhesion by Tape
Test
ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component
Adhesives (An)
Commercial Item Description (CID) A-A-52624, Nov 2008, Antifreeze, Multi Engine Type, Ethylene
Glycol
Commercial Item Description (CID) A-A-59316, 2003, Abrasive Materials for Blasting
The Society for Protective Coatings (SSPC), May 2012, Paint Application Specification No. 2 (PA-2), Measurement of Dry Coating Thickness with Magnetic Gages
Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections
MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-D-16791, Jan 1993, Detergents, General Purpose (Liquid, Nonionic)
MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut Back, Cold Application
MIL-PRF-24613, Dec 1990, Deck Covering Materials, Interior, Cosmetic Polymeric
MIL-PRF-24647, Jun 2006, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2004, Solvent Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough
Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP WJ-4/NACE WJ-4, 2012, Waterjet Cleaning of Metals – Light Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation
Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 7/NACE No.4, 2007, Brush-Off Blast Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and
Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets viii (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
29 N **Propeller shaft
Assembly for MDE change out w/ Finished
Reduction Gear Shaft
Coupling and Associated
Bolting (Consisting of
Bill of Material listed on
75-WAGL-4301-005)
NSN: 2010-01-626-3392
2 ea. 27,720.00
29 N Propeller, RH NSN: 2010-01-534-9089
1 ea. 13,038.00
29 N Propeller, LH NSN: 2010-01-534-9095
1 ea. 13,038.00
N
Main Diesel Engine and
Reduction Gear Set complete with all attached accessories
(MDE & Gear
Unattached Accessories including fuel filters, starting air components, jacket water 220 v hotstart, control and alarm panels, etc).
PN: V1312T1MLH-KC
NSN: 3020-01-F11-2289
2 ea.
219,081.00
29 N Strut Bearing (5.5” O.D.
x 4.5” I.D. x 18” Long), DURAMAX bronze, rubber
NSN: 2840-01-F11-2275
2 ea. 446.84
29 N
Pedestal Pillow Block
Bearing
PN: COOPER 02-BCP-408-
EX-AT
NSN: 3130-01-F11-2242
2 ea. 2,889.00
Bulkhead Seal Assembly
PN: WARTSILA H73090
NSN: 5330-01-F13-3234
2 ea. 5,098.00
Stern Tube Seal
Assembly
PN: WARTSILA H74537-02
NSN: 2040-01-F11-2244
2 ea. 16,664.00
MDE Exhaust Muffler
PN: 49380U
NSN: 2990-01-F11-2245
2 ea. 422.00
SSDG Exhaust Muffler
PN: 49440U
NSN: 2990-01-F11-2246
2 ea. 322.62 ix (Rev-0)
MDE Grid Cooler
PN: SC-418DP-114
NSN: 2040-01-F11-2291
2 ea 10,582.00
29 N SSDG Grid Cooler
PN: SC-216DP-63
NSN: 2040-01-F11-2290
2 ea. 4,270.51
29 N Oily Water Pump & associated compressed air filter/regulator
SANDPIPER Model
P1FRS1FB1SBSYNS200
NSN: 4320-01-F11-2261
1 ea. 1889.00
N
Fan, Commercial Navy
Vaneaxial X-A5A2W6, 4
HP, 1800/900 RPM (2
speed – 2 winding), 240/3/60, Howden-
Buffalo
PN: 500706-9630
NSN: 1680-01-F11-2281
3 ea. 10,020.00
29 N Clear Command
Processor Elec. ENG, SOL GR, 4 Station
PN: MATHERS/ZF 96204
NSN: 5865-01-F11-2249
2,480.00
29 N Control Head-Heavy duty, Dual
PN: MATHERS/ZF 4200 01
NSN: 2010-01-598-5214
2 ea.
1,110.00
29 N Serial Communication
Harness, 30 Ft
PN: MATHERS/ZF 13316-30
NSN: 2995-01-F12-2658
1 ea.
122.00
29 N Wire Harness-Throttle
Current, 30 Ft
PN: MATHERS/ZF 13494-30
NSN: 2995-01-F12-2659
2 ea.
109.00
29 N Clutch Wiring Harness
20 Ft
PN: MATHERS/ZF 15719-20
NSN: 5995-01-F12-2660
2 ea.
148.00
29 N Backup Control Panel, 3000 series
PN: MATHERS/ZF 3200B
2090-01-F11-2254 1 ea.
735.20
29 N Processor Smart Backup
4-20mA
PN: MATHERS/ZF 3005BC
NSN: 5998-01-F11-2255
2,225.00
29 N Backup Panel Wiring
Harness, Control 10Ft
PN: MATHERS/ZF 3301B-10
NSN: 5995-01-F11-2256
130.80
29 N Wire Harness-Power and
Start Interlock, 30Ft
PN: MATHERS/ZF 13756-30
NSN: 5995-01-F12-2661
188.95
29 N Backup Control Panel
Wiring Harness, Power/Start Interlock
PN: MATHERS/ZF 71708
NSN: 5995-01-F11-2271
394.00
29 N Control Head Wiring
Harness, Double Ended, 20 Ft.
PN: MATHERS/ZF 14261-20
NSN: 2030-01-F11-2272
115.00
29 N Throttle Wire Harness, 4-
20ma, N Interlock
Interface, 20Ft
PN: MATHERS/ZF 3603B-20
NSN: 5995-01-F11-2258
210.00
29 N Smart Backup Clutch
Wire Harness 20Ft
PN: MATHERS/ZF 3501B-20
NSN: 5995-01-F11-2259
282.40
29 N Control Head Wire
Harness, Double Ended, 100 Ft.
PN: MATHERS/ZF 14261-
NSN: 2030-01-F11-2260
252.00 x (Rev-0)
Tachometer Sensor
Harness, 40 ft
PN: MATHERS/ZF 13239-40
NSN: 6680-01-F11-2248
104.00
29 N Plug, Cannon Connector
PN: Mathers/ZF 6029199081
NSN: 5935-01-F12-2676
2 ea.
61.00
29 N Controller, multispeed, NEMA, CUTLER-
HAMMER
PN: ECN3618BBA-
C42H5T15P27P27P27
NSN: 6110-01-F11-2274
3,165.00
29 N Fiberglass Wall Mount
Box
(30.25”x24.25”x10”)
PN: Hoffman
A30H2410GQRLP
NSN: 5670-01-599-2924
728.88
Panel (27”x21”)
PN: Hoffman A30P24
NSN: 5342-01-222-4898
75.83
29 N
Fiberglass Wall Mount
Box (17.5x14”x8.78”)
PN: Hoffman
A18149JFGQRR
NSN: 5975-01-598-4207
335.57
29 N
Panel (14.75”x12.88”)
PN: Hoffman A16P14
NSN: 5975-01-206-0968
16.80
29 N Battery, 12V, deep cycle, 55AH, 750CCA
PN: OPTIMA D34M
NSN: 6140-01-475-9355
205.00
29 N Battery Charger, 24V, 10A, 120VAC input, CHARLES
INDUSTRIES
PN: 93-24105SP-A
NSN: 6130-01-598-4704
430.83
29 N Battery Box, ABS polymer, Troll Fury
PN: OPTIMA TF1800
NSN: 6160-01-598-3619
81.24
Cable, 2 Conductor
PN: LSDSGU-4
NSN: 6145-01-202-2795
160 ft
.89
29 N Cable, 37 Conductor, Shielded
PN: LSMSCS-37
NSN: 6145-01-202-6964
50 ft
13.70
29 N Terminal Board, 20
Terminals, Barrier Type
NSN: 5940-00-983-6061
PN: 20-140DE
2 ea
9.96
Cable, 3 Conductor, PN: LSTSGU-4
NSN: 6145-01-201-9498
20 ft
1.06
29 N Cable, 3 Conductor, PN: LS3SJ-18
NSN: 6145-01-202-7750
1.09
29 N Cable, 2 Conductor, Shielded, PN: LS2SJ-14
NSN: 6145-01-202-7747
200 ft
1.10
29 N Cable, 4 Conductor, PN: LS4SJ-16
NSN: 6145-01-204-4867
100 ft
1.54 xi (Rev-0)
29 N Switchboard Wire, PN: M16878/3BJE0
NSN: 6145-00-756-2909
20 ft
.04
29 N Cable, 30 Conductor, PN: LSMSCS-30
NSN: 6145-01-202-6963
200 ft
10.72
29 N Cable, 2 Conductor, 16
AWG Stranded, TC
Drain Wire
NSN: 6145-01-598-4205
PN: Belden 8720 100 ft
1.12
29 N Cable, 3 Conductor, Shielded, 14 AWG
PN: Belden 9367
NSN: 4010-01-599-3191
2.00
Time Delay Relay
PN: TMR6X0024
NSN: 5945-01-F12-2671
2 ea
182.00
8 Pin Socket
PN: D3PA2
NSN: 5315-01-F12-2672
7.50
29 N
Hold Down Spring
PN: D65CHDS
NSN: 5360-01-F12-2673
8.32
Steel Din Rail, Perforated
PN: 801733
NSN: 5340-01-F12-2674
1 ea
5.74
29 N 24VDC Battery Cap
Meter
PN: BCM24
NSN: 6160-01-F12-2675
96.00
29 N Circuit Breaker, 2 Pole, 24 VDC, 10A, Phoenix
Contact
PN: 0915069
NSN: 5925-01-F12-2741
151.00
29 N Code Reader NSN: 2815-01-F11-2434 1 ea. 2,336.00
29 N Main Propulsion Parts
Kit NSN: 2815-01-F12-2787 2 ea.
3,826.00
30 N Steering Rudder
(Consisting of all components listed on elevation 10-B on sheet 2 of Coast Guard Drawing
65 WD 2200-003)
NSN: 2040-01-612-6981 2 ea. 39,393.20
30 N Seal Assembly, Rudder
Stock Face
P/N: Wartsila H75492-01
NSN: 5330-01-565-9776
2 ea. 7,243.00
30 N Hydraulic Steering
Cylinder Assembly
PN: JA-201000-1
NSN: 2530-01-F11-2269
2 ea. 3,481.00
30 N Manual Helm Pump PN: JA-301007-1
NSN: 4320-01-552-9503
1 ea. 1,856.00
30 N Tank, Header PN: JA-521011-1
NSN: 5430-01-F11-2287
1 ea. 537.00
30 N Valve, DARB Assembly PN: JA-401003-1
NSN: 4810-01-F11-2282
1 ea. 1,046.00
30 N Steering Control System NSN: 2030-01-F13-3190 1 ea. 20,015.00
30 N Motors, Starters & Alarm
Assembly
NSN: 6110-01-F13-3189
1 ea. 23,772.00
30 N Tiller PN: JQ-041096-06 1 ea. 3,837.00 xii (Rev-0)
NSN: 2010-01-F11-2283
30 N Tiller PN: JQ-041096-07
NSN: 2010-01-F11-2284
1 ea 7,210.00
30 N Stud Kit, Tie Bar PN: JQ-041096-08
NSN: 5307-01-F11-2285
1 ea. 3,175.00
30 N Hydraulic Power Units
Assemblies
PN: JQ-041096-31
NSN: 4920-01-F11-2461
1 ea. 16,294.00
30 N Valve, Shut-off, 3 Way, 4-Position
PN: JA-950068-2
NSN: 4810-01-F11-2286
4 ea. 509.00
30 N Bearing Heavy Duty, 4.3307-in I.D.
PN: SKF USA 23222C
NSN: 3110-01-F11-2241
2 ea. 495.00
30 N Fan, Centrifugal, Navy
Std Size: X-CC1-
4A2W6CCW-NS, ¼ HP,
Spray Tight Motor
Enclosure, 1800 RPM (1 speed – 1 winding), 240/3/60 (Howden-
Buffalo)
PN: 500896-286
NSN: 4140-01-F11-2280
1 ea 8,371.00
30 N Annunciator Alarm
Panels (Murphy
ST1OAS-F Modified to
Dwg 75WAGL-436-002, Rev C)
NSN: 6340-01-F11-2278
PN: ST1OAS-F
2 ea 3,056.00
30 N XTPB Enclosure PN: Eaton XTPBXENAS65
NSN: 1680-01-F11-2277
1 ea 54.17
30 N XTPB Pushbutton
Manual Motor
PN: Eaton XTPB1P6BC1
NSN: 5930-01-F11-2276
2 ea 57.46
31 N 26” x 69” Weather Tight
Door(Steel) w/ 12”
Window Port Hole
Model # 1213 1 $4,800.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xiii (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5
(Inspection report particulars)):
Work
Item Title
3 Hull Plating (U/W Body), Ultrasonic Testing - Tender
4 Hull Plating (U/W Body), Ultrasonic Testing - Barge
6 Voids (Non-Accessible), Leak Test - Tender
7 Voids (Non-Accessible), Leak Test - Barge
10 Keel Coolers, Clean, Inspect, and Hydro - Barge xiv (Rev-0)
PRINCIPAL CHARACTERISTICS - TENDER
65’ WLR (B-CLASS), SMALL BUOY RIVER TENDER
PHYSICAL
Length overall 65' 10"
Depth 7' 8"
Maximum beam 21' 0"
Frame spacing 1' 6"
Full load draft 5' 0 7/8" LCF Draft
Full load displacement 127.71 Long Tons Fresh Water
HULL
Hull material Steel
MACHINERY
Number of propellers 2
Number of blades 5
Diameter of propeller 48"
Pitch 46" fixed
RPM 410
TANK CAPACITIES
Fuel tanks 2034 Gals
Fresh water tanks 4229 Gals
Lube oil 55 Gals xv (Rev-0)
PC_CGB_100_1113
PRINCIPAL CHARACTERISTICS - BARGE
100' Barge (A & B CLASSES)
PHYSICAL CHARACTERISTICS
Length Overall 100' 0"
Depth 7' 0"
Maximum Beam 30' 0"
Full Load Draft 3’ 9 ¾”
Full Load Displacement 287.39 Long Tons SW
Shore Tie Voltage Requirements 230 Volts AC
1 (Rev-0)
00000_0315_FLT
REC_00000_FLT_ Commercial Project @ Contractor’ Facility (1212)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec
0000, in accomplishing the following task:
Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes
(provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at
Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.
3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The
Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
3 (Rev-0)
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste
Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the
Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to adequately accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40
CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the
Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For
Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy. None.
3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:
3.7.1 SFLC Standard Specification 6310, Requirements for Preservation of Ship Structures.
3.7.1.1 SFLC Std Spec 6310, page C-2, Section C1.5.1. Change from "lead-containing paint as 0.06%" to "lead-containing paint as 0.009%".
3.7.1.2 SFLC Std Spec 6310, page 4, Section 2 References, Group- Other References. Add “The Society for
Protective Coatings (SSPC) Paint Application Guide No. 11, 2008, Protecting Edges, Crevices, and Irregular Steel
Surfaces by Stripe Coating”
3.7.1.3 SFLC Std Spec 6310, page Appendix C-6, add "Hempel Hempadur Multi-Strength GF 35870" with FED-
STD-595 color "Black/Red" under ANTI-ABRASION COATING, ICE BREAKING CAPABLE VESSELS, <235’.
3.7.1.4 Standard Spec 6310, page Appendix A-7, Under "UNDERWATER (U/W) BODY/BOOT-TOP", Add line
Column 1: Option for U/W Body and Boot-Top, Steel Hulls, <154', in Salt Water. Column 2: Blank. Column 3:
SSPC-SP 10/NACE NO. 2 using grit conforming to MIL-A-22262 / (1.5-3.5) - or - SSPC-SP WJ-2(M)/NACE
WJ-2(M). Columns 4 and 5: Same as "U/W Body and Boot-Top, Aluminum Hull, High Speed (>30 knots)".
3.7.2 SFLC Standard Specification 0000 General Requirements.
3.7.2.1 SFLC Std Spec 0000, paragraph 1.3 ‘Acronyms and term definitions’, page 5, “PCL (Paint Containing
Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”
4 (Rev-0)
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
5 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
Vessel Name Hull # Work Item # Work Item Title
Location of Work (incl. frame #’s) Area (sqft)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down
(maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max.
threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Name of QP-1/NACE Inspector Signature Cert. # Date / Time
6 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE &
TIME
ACTIVITY
(Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION
(Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL.
HUMID-
ITY DEW
PT.
SURFACE AMBIENT
ΔT
| DP -
Surface |
7 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
Location of Work (Frame References) Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min Max Mean
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________
8 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min Max Mean
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Mean Mil Reading (IAW ASTM D4417-Method B) for above 10 readings (by column):
_____ mils _____ mils _____ mils _____ mils _____ mils
9 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15
DATE TEST LOCATIONS
CONDUCTIVITY
(microsiemens/cm)
10 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
Coating Mfg Product Name Batch # Induction
Time
Coating System Sequence
(Primer/Touchup/3rd Coat, etc.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL
READING (BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation
3 Before
Adjustments
After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation
3 Before
Adjustments
After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation
3 Before
Adjustments
After Adjustments
Avg.
Application Method (Airless, Conventional Spray, Rolled) Average DFT
11 (Rev-0)
11000_0815_FLT
REC_11000_UWHIB_FLT_65’ WLR (ALL) (1211)
WORK ITEM 1: Hull Plating (U/W Body), Inspect - Tender
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to inspect/survey the vessel’s
Under Water (U/W) hull plating, including U/W appendages and coating system.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 65 WD 700-004, Rev -, Docking Block Arrangement (“A” & “B” Class)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
OTHER REFERENCES
The Society for Protective Coatings (SSPC), May 2012, Paint Application Specification No. 2
(PA-2), Measurement of Dry Coating Thickness with Magnetic Gages
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all
12 (Rev-0) installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 Inspection. The Contractor shall accompany the Underwater Hull Inspection Board (UWHIB) in the performance of the below inspection tasks, as applicable, using the drawings listed in Section 2
(References) as guidance. The Contractor shall provide the following, to facilitate the UWHIB in assessing the condition of the designated U/W hull components and systems:
A hull repair supervisor and a marker.
Temporary staging and other necessary equipment, as applicable, for ensuring safe access to all areas of the U/W hull.
NOTES
1. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.
2. Some of the components and/or systems addressed in this work item may not be applicable to all vessel classes.
3.2.1 Hull plating.
3.2.1.1 The Contractor shall inspect the condition of the hull plating (including thruster tunnel plating, as applicable), for the presence of marine growth, deformation, and any evidence of major corrosion or electrolytic action.
3.2.1.2 The Contractor shall inspect the hull and keel areas, report on the condition of butt-welded seams, doubler plates, lap seams, and for any signs of damaged plating or unusual waviness in the plating.
3.2.2 Sea chests and all other cooling system intake components. The Contractor shall inspect all sea chests, tunnels, hull openings, and grates for general appearance, loose, damaged, or missing grates, loose or missing fasteners, condition of sea strainers and lockwire on bolts, marine growth on grating slots, and any obstructions in the openings that might prevent proper suction and discharge of water.
3.2.3 Rudders. The Contractor shall check general condition, condition around the drain plugs, and check for pitting, if any, on the leading and trailing edges.
3.2.4 Propeller and shaft associated components. The Contractor shall inspect the condition of propellers for propellers for signs of corrosion, pitting, erosion, fouling, cracks, dings, and nicks by side and blade;
inspect fairwaters, rope guards, shafts, and mechanical seals - look for missing screws, physical damage to the blades, pitting, condition of dunce caps, and condition of securing devices.
3.2.5 Transducers. The Contractor shall check general condition for cuts, cracks, corrosion, and surface defects around the openings. Check transducer securing nuts for tightness, and inspect cables for chafing and other damage.
3.2.6 Anodes.
13 (Rev-0)
3.2.6.1 The Contractor shall remove all marine growth and oxide coating from all hull, rudder, shaft strut, sea chest, z-drive, and thruster tunnel anodes, or water jet drives anodes, as applicable, using a light-wire brush.
3.2.6.2 The Contractor shall visually inspect all anodes; check the soundness of mounting strap and stud welds, missing fasteners, and percentage of remaining material.
3.2.7 Coating system inspections. The Contractor shall accomplish the below inspections, in conjunction with the underwater hull inspection conducted by the Underwater Hull Inspection Board (UWHIB).
Document the condition found as “Partial - Condition A”, “Partial - Condition B”, or “100%”, as applicable (see 4.1 (Definitions)). Submit a CFR.
NOTE
The following inspections are for determining the existing condition of the coating system for the underwater body surfaces, which are deemed “Critical-coated” surfaces; they must be carried out by a SSPC-QP-1 certified contractor/sub-Contractor or a NACE Inspector – see SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.2.7.1 Visual. Perform a visual inspection of the existing U/W body coating system.
3.2.7.2 Dry film thickness(DFT) measurements. Take total DFT measurements of the U/W body coating system, in accordance with SSPC-PA 2.
4. NOTES
4.1 Definitions.
4.1.1 "Partial – Condition A”: The condition that exists where the substrate is exposed in up to 33% of the entire U/W body.
4.1.2 "Partial - Condition B": The condition that exists where the coating system has incurred damage, but the substrate is not exposed in any location.
4.1.3 "100%”: The condition that exists where more than 33% of the U/W body hull substrate is exposed.
4.2 UWHIB convention. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.
14 (Rev-0)
11000_0815_FLT
REC_11000_UWHIB_FLT_100’ Barge (ALL) (1211)
WORK ITEM 2: Hull Plating (U/W Body), Inspect - Barge
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to inspect/survey the vessel’s
Under Water (U/W) hull plating, including U/W appendages and coating system.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 100B CGB 700-003, Rev -, Docking Block Arrangement
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
OTHER REFERENCES
The Society for Protective Coatings (SSPC), May 2012, Paint Application Specification No. 2
(PA-2), Measurement of Dry Coating Thickness with Magnetic Gages
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and contamination during the performance of work. Upon completion of work, the Contractor shall remove all
15 (Rev-0) installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 Inspection. The Contractor shall accompany the Underwater Hull Inspection Board (UWHIB) in the performance of the below inspection tasks, as applicable, using the drawings listed in Section 2
(References) as guidance. The Contractor shall provide the following, to facilitate the UWHIB in assessing the condition of the designated U/W hull components and systems:
A hull repair supervisor and a marker.
Temporary staging and other necessary equipment, as applicable, for ensuring safe access to all areas of the U/W hull.
NOTES
1. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.
2. Some of the components and/or systems addressed in this work item may not be applicable to all vessel classes.
3.2.1 Hull plating.
3.2.1.1 The Contractor shall inspect the condition of the hull plating (including thruster tunnel plating, as applicable), for the presence of marine growth, deformation, and any evidence of major corrosion or electrolytic action.
3.2.1.2 The Contractor shall inspect the hull and keel areas, report on the condition of butt-welded seams, doubler plates, lap seams, and for any signs of damaged plating or unusual waviness in the plating.
3.2.2 Sea chests and all other cooling system intake components.