INVITATION FOR BID TOTAL HUBZONE SET-ASIDE
Text of this file
NOTICE FOR FILING AGENCY PROTESTS
United States Coast Guard Ombudsman Program
It is the policy of the United States Coast Guard (USCG) to issue solicitations and make contract awards in a fair and timely manner. The Ombudsman Program for Agency Protests (OPAP) was established to investigate agency protest issues and resolve them without expensive and time-consuming litigation. OPAP is an independent reviewing authority that is empowered to grant a prevailing protester essentially the same relief as the Government Accountability Office (GAO).
Interested parties are encouraged to seek resolution of their concerns within the USCG as an Alternative Dispute Resolution (ADR) forum rather than filing a protest with the GAO or some external forum. Interested parties may seek resolution of their concerns informally or opt to file a formal agency protest with the Contracting Officer or Ombudsman.
Informal Forum with the Ombudsman. Interested parties who believe a specific USCG procurement is unfair or otherwise defective should first direct their concerns to the applicable Contracting Officer. If the Contracting Officer is unable to satisfy their concerns, interested parties are encouraged to contact the U.S. Coast Guard Ombudsman for Agency Protests. Under this informal process the agency is not required to suspend contract award performance. Use of an informal forum does not suspend any time requirement for filing a protest with the agency or other forum. In order to ensure a timely response, interested parties should provide the following information to the Ombudsman:
solicitation/contract number, contracting office, Contracting Officer, and solicitation closing date (if applicable).
Formal Agency Protest with the Ombudsman. Prior to submitting a formal agency protest, protesters must first use their best efforts to resolve their concerns with the Contracting Officer through open and frank discussions. If the protester’s concerns are unresolved, an Independent Review is available by the Ombudsman. The protester may file a formal agency protest to either the Contracting Officer or as an alternative to that, the Ombudsman under the OPAP program. Contract award or performance will be suspended during the protest period unless contract award or performance is justified, in writing, for urgent and compelling reasons or is determined in writing to be in the best interest of the Government. The agency’s goal is to resolve protests in less than 35 calendar days from the date of filing. Protests shall include the information set forth in FAR 33.103(d) (2). If the protester fails to submit the required information, resolution of the protest may be delayed or the protest may be dismissed. To be timely protests must be filed within the period specified in FAR 33.103(e). Formal protests filed under the OPAP program should be submitted to:
COMMANDANT (CG-9131)
U S COAST GUARD
OMBUDSMAN PROGRAM FOR AGENCY PROTESTS
2100 2ND ST SW STOP 7112
WASHINGTON DC 20593-7112
The Ombudsman Hotline telephone number is 202.372.3695.
PART I – THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM/INDEX
Table of Contents
PART I – THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM/INDEX
SECTION B - SUPPLIES OR SERVICES AND PRICES
SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
SECTION D - PACKAGING AND MARKING
SECTION E - INSPECTION AND ACCEPTANCE
SECTION F - DELIVERIES OR PERFORMANCE
SECTION G - CONTRACT ADMINISTRATION DATA
SECTION H - SPECIAL CONTRACT REQUIREMENTS
PART II – CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
PART III – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
SECTION J - LIST OF ATTACHMENTS
PART IV – REPRESENTATIONS AND INSTRUCTIONS
SECTION K - REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS
SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
SECTION M - EVALUATION FACTORS FOR AWARD
SOLICITATION OFFER
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
HSCG82-12-B-PMV138
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
04/12/2012
PAGE OF
PAGES
IMPORTANT - The "offer" section on page 2 must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
21-12-822PMV138
6. PROJECT NO.
3581358
7. ISSUED BY CODE 8. ADDRESS OFFER TO
CONTRACTING OFFICER
USCG CIVIL ENGINEERING UNIT MIAMI
15608 SW 117TH AVENUE
MIAMI, FLORIDA 33177-1630
SAME AS BLOCK 7
9. FOR INFORMATION
CALL
A. NAME
LESIA K. MOYER
B TELEPHONE NO. (INCLUDE AREA CODE) (NO COLLECT CALLS)
(305) 278-6725
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
THIS IS A HUBZONE SMALL BUSINESS CONCERN SET-ASIDE
SUMMARY OF WORK: CONTRACTOR SHALL PROVIDE ALL LABOR, EQUIPMENT, TOOLS, MATERIALS AND SUPERVISION NECESSARY TO PROVIDE AIRCRAFT HANGAR STRUCTURAL REPAIRS FOR U.S. COAST GUARD AIR STATION NEW ORLEANS, IN STRICT ACCORDANCE WITH THE SPECIFICATIONS (PROJECT NO.
3581358), DRAWINGS NUMBER (M1805-D), REFERENCE DRAWINGS SHEETS (1-10) AND THE CONTRACT.
LOCATION: U.S. COAST GUARD
AIR STATION
400 RUSSELL AVENUE, BLDG 309
NEW ORLEANS, LA 70143
11. The contractor shall begin performance within 10 calendar days and complete it within 120 calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See Section F).
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
YES NO
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and 1 copies to perform the work required are due at the place specified in Item 8 by 2:00 PM local time MAY 15, 2012. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d)
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
DUNS: _________________________________________
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each)
AMENDMENT NO.
DATE
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20b. SIGNATURE
20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
BLOCK 27
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 USC 2304(c) ( 5 ) 41 USC USC 253(c) ( )
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER
USCG CIVIL ENGINEERING UNIT MIAMI
15608 SW 117TH AVENUE
MIAMI, FLORIDA 33177-1630
COMMERCIAL INVOICES
U. S. COAST GUARD FINANCE CENTER
1430A KRISTINA WAY
CHESAPEAKE, VA 23326-0324
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return _____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE
30c. DATE
31b. UNITED STATES OF AMERICA
BY
31c. DATE
STANDARD FORM 1442 (REV. 4-85) BACK
HSCG82-12-C-______
SECTION B - SUPPLIES OR SERVICES AND PRICES
**ALL ITEMS ARE TO BE PRICED SEPARATELY**
BASE BID: Provide all labor, materials, tools, equipment and supervision necessary to provide structural strengthening of various areas of the structural steel framing of the roof and walls of the hangar. Work includes but is not limited to:
demolition, removal and disposal of the existing hangar doors; installation of two (2) new structural steel supports; and installation of a new electrical panel. All work shall be performed in accordance with the specifications and drawings.
ONE JOB COMPLETE $
UNIT PRICE ITEM: Provide all labor, materials, tools, equipment and supervision necessary to perform the following unit price items. Actual quantities shall be determined by the government. All work shall be performed in accordance with the specifications and drawings.
UNIT PRICE ITEM 1: Install structural steel grade ASTM A 36 wide flange W8x15 member coated.
ESTIMATED QUANTITY: 10 LF UNIT PRICE: $________________ ITEM TOTAL: $________________
UNIT PRICE ITEM 2: Install structural steel grade ASTM A 36 wide flange W8x35 member coated.
UNIT PRICE ITEM 3: Install structural steel grade ASTM A 36 channel section C12x20.7 member coated.
UNIT PRICE ITEM 4: Install structural steel grade ASTM A 36 angle section L6x6x3/8 Coated.
UNIT PRICE ITEM 5: Install ¼-inch fillet weld.
ESTIMATED QUANTITY: 1 LF UNIT PRICE: $________________ ITEM TOTAL: $________________
CEU MIAMI – IFB_Construction 3 (REV 03/05/2012 FAC 2005-56)
UNIT PRICE ITEM 6: Install galvanized steel sheet metal flashing.
ESTIMATED QUANTITY: 10 SF UNIT PRICE: $________________ ITEM TOTAL: $________________
UNIT PRICE ITEM 7: Install high gloss industrial enamel finish on hangar floor to match existing finish product.
UNIT PRICE ITEM 8: Coat metal surface with “High Performance Coating” as specified.
UNIT PRICE ITEM 9: Remove and dispose of paint containing lead as determined in the lead paint abetment survey.
TOTAL OF ALL ITEMS $
CEU MIAMI – IFB_Construction 4 (REV 03/05/2012 FAC 2005-56)
SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
C.1 SPECIFICATIONS AND DRAWINGS:
(a) SEE SECTION J - “LIST OF ATTACHMENTS”
(b) DRAWINGS MEASUREMENTS SHOULD BE FIELD VERIFIED BY THE SUCCESSFUL CONTRACTOR
PRIOR TO ORDERING MATERIAL
(c) Failure to read the specifications in their entirety will not relieve the offerors from responsibility for properly estimating the difficulty or cost of successfully performing the work. Failure to do so will be at offeror’s risk.
(d) Each offeror shall furnish the information required by the solicitation. Any offer that does not conform to the requirements of this solicitation in every respect will be rejected as non-responsive. Deviations from, or exceptions to, the specifications or delivery schedule are causes for rejection. Offers for supplies or services other than those specified will not be considered unless authorized by this solicitation.
SECTION D - PACKAGING AND MARKING
THIS SECTION IS NOT APPLICABLE
CEU MIAMI – IFB_Construction 5 (REV 03/05/2012 FAC 2005-56)
SECTION E - INSPECTION AND ACCEPTANCE
E.1 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not –
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) below.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes re-inspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may (1) by contract or otherwise, replace or correct the work and charge the cost to the Contractor or (2) terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or non conforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
(End of clause)
E.2 CONTRACTOR INSPECTION SYSTEM
(a) Provide all necessary equipment, instruments, qualified personnel, facilities, and test fluids and gases, and perform all inspections, sampling, testing, and certifications specified in the individual Sections of the Specifications; fill out Daily
CEU MIAMI – IFB_Construction 6 (REV 03/05/2012 FAC 2005-56)
Construction Report forms as documentation and submit the forms to the Government inspector by 10:00 a.m. on the first working day following the day the work was performed. Sample forms are provided in Section J of this contract. Daily Construction Report forms will be furnished to the Contractor.
SECTION F - DELIVERIES OR PERFORMANCE
F.1 THE FOLLOWING CLAUSES ARE INCORPORATED BY REFERENCE:
52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)
52.242-14 SUSPENSION OF WORK (APR 1984)
F.2 IN ADDITION TO THE ABOVE CLAUSES INCORPORATED BY REFERENCE, THE FOLLOWING CLAUSES
ARE APPLICABLE TO THE SOLICITATION AND RESULTING CONTRACT:
52.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the NOTICE TO PROCEED, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days after receipt of the notice to proceed. The time stated for completion shall include final cleanup of the premises.
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work schedules for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance the Contracting Officer may require the Contractor to increase the number of shifts overtime operations days of work and/or the amount of construction plant and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.
CEU MIAMI – IFB_Construction 7 (REV 03/05/2012 FAC 2005-56)
F.3 CONTRACTOR’S SCHEDULE
A preliminary copy of the Contractor’s proposed schedule shall be prepared and submitted to the Contracting Officer prior to the preconstruction conference. Any questions or problems that might cause a delay in approval of the schedule can be addressed during this conference.
SECTION G - CONTRACT ADMINISTRATION DATA
G.1 SUBMITTALS/SHOP DRAWINGS:
Contractor shall provide a schedule of required submittals indicating the order in which the Contractor proposes to provide the required submittals and the dates on which the Contractor plans to provide said submittals. This schedule shall be provided prior to the preconstruction conference for review and discussion during the conference. The Contractor is to forward five (5) copies of applicable submittals to the Contracting Officer. The Contracting Officer will indicate his/her approval or disapproval of the submittals/shop drawings and if not approved as submitted shall indicate reasons thereof. Any work done prior to such approval shall be at the Contractor’s risk. Approval by the Contracting Officer shall not relieve the Contractor from responsibility for any errors or omissions in such drawings, nor from the responsibility for complying with the requirements of this contract.
G.2 PRECONSTRUCTION CONFERENCE:
As soon as practicable after the award of contract, a mutually agreeable time and date for a preconstruction conference between the representatives of the Government and the Contractor will be established. This conference will be held either by telephone or, if convenient, at the site or this office to discuss the terms and conditions of the contract. Below are some of the items to be discussed:
(a) Detailed procedures for the administration of the project,
(b) Identify the authorized representatives of the Government and the Contractor’s Superintendent(s),
(c) Contractor’s field office address and telephone number,
(d) Contractor’s draft Construction Progress Schedule (Section F (F.4))
The Notice to Proceed date will be established during this meeting.
(e) Procedures for processing periodic pay estimates (Section G (G.3-6))
(f) Review of Submittal Schedule giving proposed dates Contractor will submit all required contract submittals
(Section G (G.1))
(g) Requirements and procedures for preparing work schedules and reporting programs,(Section E (E.2))
(h) Procedures for equal opportunity compliance,
(i) Information on delivery of Government-furnished property (If Applicable).
G.3 DESIGNATED BILLING OFFICE
(a) Submit original invoice to the following designated billing office via one of the following modes, listed in descending order of preference:
(1) FINCEN Website invoice receipt form:
http://www.fincen.uscg.mil/centralinv/central_inv_contr.cfm
CEU MIAMI – IFB_Construction 8 (REV 03/05/2012 FAC 2005-56) http://www.fincen.uscg.mil/centralinv/central_inv_contr.cfm
(2) Fax: 757-523-6900
(3) Mailed to: Commercial Invoices U.S. Coast Guard Finance Center 1430A Kristina Way Chesapeake, VA 23326
(b) Submit a copy of the invoice with any required supporting documentation to the Contracting Office:
CONTRACTING OFFICER
U. S. COAST GUARD
CIVIL ENGINEERING UNIT MIAMI
15608 S. W. 117TH AVENUE
MIAMI, FLORIDA 33177-1630
(c) To facilitate processing, all proper invoices and any supporting information submitted electronically using the FINCEN web based invoice submission capability must be submitted as a single Adobe (.pdf) formatted file, or as otherwise specified in the contract.
(d) Web based submission by the contractor and receipt confirmation does not reflect Government review or acceptance of the invoice.
(e) Payment inquiries and status may be obtained - at the following website: -https://www.fincen.uscg.mil/secure/payment.htm.
G.4 INVOICE
(a) To be accomplished on the form provided by the Coast Guard. See Section J for copy of said form.
(b) In addition to the items required for a proper invoice under FAR 52.232-5 and 52.232-27, the invoice must also include the following information:
1. Invoice Routing Code: CEU-MIAMI
2. Name of the Contract Specialist
3. Indication that the contractor represents a small business for accelerated payment purposes.
(c) To facilitate the approval and processing of an invoice, contractor shall furnish an advance copy of the invoice to the Contracting Officer’s Technical Representative for review of the invoice amount and estimates of work accomplished prior to submission to the billing office.
G.5 GOVERNMENT REPRESENTATIVES
The Government may, upon contract award or thereafter, name representatives with titles such as Project Engineer, Contracting Officer’s Technical Representative(s), Inspector(s), and so on. Such individuals will be named in writing by the Contracting Officer, with individual responsibilities set forth at that time.
In any event, no such named individual has the authority to issue any direction under this contract either technical or otherwise, which constitutes a change to the terms, conditions, and price or delivery schedule of the contract. Only the Contracting Officer is authorized to alter the contract in any manner.
CEU MIAMI – IFB_Construction 9 (REV 03/05/2012 FAC 2005-56) http://www.fincen.uscg.mil/electron.htm http://www.fincen.uscg.mil/electron.htm
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H.1. JOB SUPERINTENDENT
Special attention is called to the requirement for superintendence by the Contractor, FAR Clause 52.236-6. The contractor shall provide a job superintendent on the site at all times during contract performance that is able to read, write, understand, and speak English.
H.2 MODIFICATION PROPOSALS - PRICE BREAKDOWN
The contractor, in connection with any proposal made for a contract modification, shall furnish a price breakdown, itemized as required by the Contracting Officer. Unless otherwise directed, the breakdown shall be in sufficient detail to permit an analysis of all material, labor, equipment, subcontract, and overhead costs, as well as profit, and shall cover all work changed. Any amount claimed for subcontracts shall be supported by a similar price breakdown. In addition, if the proposal includes a time extension, a justification therefore shall also be furnished. The proposal, together with the price breakdown and time extension justification, shall be furnished by the date specified by the Contracting Officer. Once a contract modification has been authorized, the contractor shall submit an updated progress schedule that includes all changes implemented by the modification.
H.3 SANITATION
Adequate sanitary conveniences of an approved type for the use of persons employed on the work, and properly secluded from public observation, shall be constructed and maintained by the Contractor in such a manner and at such points as shall be required or approved by the Contracting Officer. These conveniences shall be maintained at all times without nuisance and their use shall be strictly enforced. Upon completion of the work they shall be removed from the premises, leaving the premises clean and free from nuisance.
H.4 WORK OUTSIDE REGULAR WORK HOURS
If the contractor desires to perform work under this contract outside regular work hours or on Saturdays, Sundays or holidays, a written request shall be made, to the Contracting Officer no less than 10 calendar days prior to the planned start of such work. Regular work hours are, for the purpose of this clause, those hours the activity or Command, where the work is to be performed, normally works on a day-by-day basis. Application by the Contractor does not imply consent by the Government. Each application will be considered, and a decision made, on the potential benefit of permitting such work. Approval of a Contractor’s application under this clause will be, unless otherwise agreed in writing, at no additional cost to the Government.
H.5 STATEMENT AND ACKNOWLEDGMENT FORM (SF 1413)
Special attention is called to the requirement for insertion of and compliance with various labor clauses called out in FAR Clause 52.222-11 in any subcontracts regardless of tier. Within 14 days after contract award of the prime contract, an executed SF-1413 is required for each subcontract. This also applies to any subsequently awarded subcontract.
H.6 REQUIRED BONDING –
PERFORMANCE BOND (Standard Form 25) will be required as follows: 100% of total amount of contract;
CEU MIAMI – IFB_Construction 10 (REV 03/05/2012 FAC 2005-56)
PAYMENT BOND (Standard Form 25a) will be required as follows: 100% of total amount of contract;
Performance and payment bonds placed with a surety or sureties acceptable to the Government and in the amounts indicated shall be submitted within ten (10) calendar days after receipt of award and shall be maintained for the entire contract.
H.7 REQUIRED INSURANCE
(a) The contractor shall procure and maintain insurance during the entire period of performance under this contract, in accordance with Federal Acquisition Regulation Clause 52.228-5, INSURANCE - WORK ON A GOVERNMENT INSTALLATION (JAN 1997) (See Section I). FAR 28.307-2 states the following minimum amounts of liability:
MINIMUM COVERAGE REQUIRED
(1) Workers’ Compensation and Employer’s Liability - at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit workers’ compensation to be written by private carriers.
(2) General Liability. - bodily injury liability insurance coverage written on the comprehensive form of policy of at least $500,000. per occurrence.
(3) Automobile Liability. - automobile liability insurance written on the comprehensive form of policy of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage.
(b) As evidence that the specified insurance has been obtained, the contractor shall furnish the contracting officer with a certificate of insurance. Such certificate shall be furnished prior to commencement of work and shall provide for thirty
(30) calendar days written notice to the Contracting Officer.
CEU MIAMI – IFB_Construction 11 (REV 03/05/2012 FAC 2005-56)
PART II – CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if it was given in full text. Upon request, the Contracting Officer will make full text available. Also, the full text of a clause may be assessed electronically at this/these address(es): http://www.arnet.gov/far/
I.2 FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.202-1 DEFINITIONS (JAN 2012)
52.203-3 GRATUITIES (APR 1984)
52.203-5 COVENANT AGAINST CONTINGENT FEES (APR 1984)
52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (SEPT 2006)
52.203-7 ANTI-KICKBACK PROCEDURES (OCT 2010)
52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER
ACTIVITY (JAN 1997)
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (JAN 1997)
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (OCT
2010)
52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER
(MAY 2011)
52.204-7 CENTRAL CONTRACTOR REGISTRATION (FEB 2012)
52.204-9 PERSONNEL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS
(FEB 2012)
52.209-6 PROTECTING THE GOVERNMENT’S INTEREST WHEN SUBCONTRACTING WITH
CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (DEC 2010)
52.214-26 AUDIT AND RECORDS - SEALED BIDDING (OCT 2010)
52.214-27 PRICE REDUCTION FOR DEFECTIVE CERTIFIED COST OR PRICING DATA—
MODIFICATIONS—SEALED BIDDING (AUG 2011)
52.214-28 SUBCONTRACTOR COST OR PRICING DATA - MODIFICATIONS - SEALED BIDDING (OCT
2010)
52.214-29 ORDER OF PRECEDENCE – SEALED BIDDING (JAN 1986)
52.219-3 NOTICE OF HUBZONE SET-ASIDE OR SOLE SOURCE AWARD (NOV 2011)
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (JAN 2011)
52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REPRESENTATION (APR 2009)
52.222-3 CONVICT LABOR (JUNE 2003)
52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS ACT-OVERTIMECOMPENSATION
(JULY 2005)
52.222-6 DAVIS-BACON ACT (JULY 2005)
52.222-7 WITHHOLDING OF FUNDS (FEB 1988)
52.222-8 PAYROLLS AND BASIC RECORDS (JUNE 2010)
52.222-9 APPRENTICES AND TRAINEES (JULY 2005)
52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)
52.222-11 SUBCONTRACTS (LABOR STANDARDS) (JULY 2005)
52.222-12 CONTRACT TERMINATION-DEBARMENT (FEB 1988)
52.222-13 COMPLIANCE WITH DAVIS-BACON AND RELATED ACT REGULATIONS (FEB 1988)
CEU MIAMI – IFB_Construction 12 (REV 03/05/2012 FAC 2005-56) http://www.arnet.gov/far/
52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)
52.222-15 CERTIFICATION OF ELIGIBILITY (FEB 1988)
52.222-21 PROHIBITION OF SEGREGATED FACILITIES (FEB 1999)
52.222-26 EQUAL OPPORTUNITY (MAR 2007)
52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (FEB 1999)
52.222-35 EQUAL OPPORTUNITY FOR VETERANS (SEPT 2010)
52.222-36 AFFIRMATIVE ACTION FOR WORKERS WITH DISABILITIES (OCT 2010)
52.222-37 EMPLOYMENT REPORTS VETERANS (SEPT 2010)
52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT
(DEC 2010)
52.222-50 COMBATING TRAFFICKING IN PERSONS (FEB 2009)
52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (JAN 2009)
52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND
CONSTRUCTION CONTRACTS (DEC 2007)
52.223-3 HAZARDOUS MATERIAL IDENTIFICATION & MATERIAL SAFETY DATA (JAN 1997) ALT I
(JULY 1995)
52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)
52.223-6 DRUG-FREE WORKPLACE (MAY 2001)
52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING
(AUG 2011)
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUNE 2008)
52.227-1 AUTHORIZATION AND CONSENT (DEC 2007)
52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT (DEC
2007)
52.227-4 PATENT INDEMNITY - CONSTRUCTION CONTRACTS (DEC 2007)
52.227-17 RIGHTS IN DATA - SPECIAL WORKS (DEC 2007)
52.228-1 BID GUARANTEE (SEPT 1996)
(c) The amount of the bid guarantee shall be twenty percent (20%) of the bid price.
52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)
52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
52.228-11 PLEDGES OF ASSETS (JAN 2012)
52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (OCT 1995)
52.228-14 IRREVOCABLE LETTER OF CREDIT (DEC 1999)
52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION (OCT 2010)
52.229-3 FEDERAL, STATE, AND LOCAL TAXES (APR 2003)
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (SEPT 2002)
52.232-17 INTEREST (OCT 2010)
52.232-23 ASSIGNMENT OF CLAIMS (JAN 1986)
52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (OCT 2008)
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER – CENTRAL CONTRACTOR REGISTRATION
(OCT 2003)
52.233-1 DISPUTES (JULY 2002)
52.233-3 PROTEST AFTER AWARD (AUG 1996)
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)
52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)
“The Contractor shall perform on the site and with its own organization work equivalent to at least 12 percent of the total amount of work to be performed under the contract.”
52.236-2 DIFFERING SITE CONDITIONS (APR 1984)
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)
52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)
CEU MIAMI – IFB_Construction 13 (REV 03/05/2012 FAC 2005-56)
52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)
52.236-8 OTHER CONTRACTS (APR 1984)
52.236-9 PROTECTION OF EXISTING VEGETATION STRUCTURE, EQUIPMENT, UTILITIES AND
IMPROVEMENTS (APR 1984)
52.236-10 OPERATIONS AND STORAGE AREA (APR 1984)
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)
52.236-12 CLEANING UP (APR 1984)
52.236-13 ACCIDENT PREVENTION, ALT I (NOV 1991)
52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)
52.236-17 LAYOUT OF WORK (APR 1984)
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)
52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)
52.242-13 BANKRUPTCY (JULY 1995)
52.243-4 CHANGES (JUNE 2007)
52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS (DEC 2010)
52.246-21 WARRANTY OF CONTRUCTION (MAR 1994)
52.247-64 PREFERENCE FOR PRIVATELY OWNED U.S. FLAG COMMERCIAL VESSELS (FEB 2006)
52.248-3 VALUE ENGINEERING - CONSTRUCTION (OCT 2010)
52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED PRICE) (MAY 2004) –
ALT I (SEPT 1996)
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
52.253-1 COMPUTER GENERATED FORMS (JAN 1991)
I.3 DEPARTMENT OF HOMELAND SECURITY REGULATION (HSAR) (48 CFR CHAPTER 30) CLAUSES
3052.211-70 INDEX FOR SPECIFICATIONS (DEC 2003)
3052.222-70 STRIKES OR PICKETING AFFECTING TIMELY COMPLETION OF THE CONTRACT WORK
(DEC 2003)
3052-222-71 STRIKES OR PICKETING AFFECTING ACCESS TO A DHS FACILITY (DEC 2003)
3052.223-70 REMOVAL OR DISPOSAL OF HAZARDOUS SUBSTANCES - APPLICABLE LICENSES AND
PERMITS (JUNE 2006)
3052.223-90 ACCIDENT AND FIRE REPORTING (DEC 2003)
3052.228-70 INSURANCE (DEC 2003)
3052.228-90 NOTIFICATION OF MILLER ACT PAYMENT BOND PROTECTION (USCG) (DEC 2003)
3052.236-70 SPECIAL PRECAUTIONS FOR WORK AT OPERATING AIRPORTS (DEC 2003)
3052.242-71 DISSEMINATION OF CONTRACT INFORMATION (DEC 2003)
3052.242-72 CONTRACTING OFFICER’S TECHNICAL REPRESENTATIVE (DEC 2003)
I.4 IN ADDITION TO THE ABOVE CLAUSES INCORPORATED BY REFERENCE, THE FOLLOWING CLAUSES
ARE APPLICABLE TO THE SOLICITATION AND RESULTING CONTRACT:
52.204-1 APPROVAL OF CONTRACT (DEC 1989)
This contract is subject to the written approval of Senior Field Contracting Officer, Civil Engineering Unit Miami and shall not be binding until so approved.
(End of Clause)
CEU MIAMI – IFB_Construction 14 (REV 03/05/2012 FAC 2005-56)
52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY
MATTERS (FEB 2012)
(a) The Contractor shall update the information in the Federal Awardee Performance and Integrity Information System (FAPIIS) on a semi-annual basis, throughout the life of the contract, by posting the required information in the Central Contractor Registration database via https://www.acquisition.gov.
(b) As required by section 3010 of the Supplemental Appropriations Act, 2010 (Pub. L. 111-212), all information posted in FAPIIS on or after April 15, 2011, except past performance reviews, will be publicly available. FAPIIS consists of two segments—
(1) The non-public segment, into which Government officials and the Contractor post information, which can only be viewed by—
(i) Government personnel and authorized users performing business on behalf of the Government; or
(ii) The Contractor, when viewing data on itself; and
(2) The publicly-available segment, to which all data in the non-public segment of FAPIIS is automatically transferred after a waiting period of 14 calendar days, except for—
(i) Past performance reviews required by subpart 42.15;
(ii) Information that was entered prior to April 15, 2011; or
(iii) Information that is withdrawn during the 14-calendar-day waiting period by the Government official who posted it in accordance with paragraph (c)(1) of this clause.
(c) The Contractor will receive notification when the Government posts new information to the Contractor’s record.
(1) If the Contractor asserts in writing within 7 calendar days, to the Government official who posted the information, that some of the information posted to the non-public segment of FAPIIS is covered by a disclosure exemption under the Freedom of Information Act, the Government official who posted the information must within 7 calendar days remove the posting from FAPIIS and resolve the issue in accordance with agency Freedom of Information procedures, prior to reposting the releasable information. The contractor must cite 52.209-9 and request removal within 7 calendar days of the posting to FAPIIS.
(2) The Contractor will also have an opportunity to post comments regarding information that has been posted by the Government. The comments will be retained as long as the associated information is retained, i.e., for a total period of 6 years. Contractor comments will remain a part of the record unless the Contractor revises them.
(3) As required by section 3010 of Pub. L. 111-212, all information posted in FAPIIS on or after April 15, 2011, except past performance reviews, will be publicly available.
(d) Public requests for system information posted prior to April 15, 2011, will be handled under Freedom of Information Act procedures, including, where appropriate, procedures promulgated under E.O. 12600.
52.223-11 OZONE-DEPLETING SUBSTANCES (MAY 2001)
(a) Definition. “Ozone-depleting substance,” as used in this clause, means any substance the Environmental Protection Agency designates in 40 CFR Part 82 as—
(1) Class I, including, but not limited to, chlorofluorocarbons, halons, carbon tetrachloride, and methyl chloroform;
or
(2) Class II, including, but not limited to, hydrochlorofluorocarbons.
(b) The Contractor shall label products which contain or are manufactured with ozone-depleting substances in the manner and to the extent required by 42 U.S.C. 7671j (b), (c), and (d) and 40 CFR Part 82, Subpart E, as follows:
Warning Contains (or manufactured with, if applicable) *_______, a substance(s) which harm(s) public health and environment by destroying ozone in the upper atmosphere.
* The Contractor shall insert the name of the substance(s).
(End of clause)
CEU MIAMI – IFB_Construction 15 (REV 03/05/2012 FAC 2005-56) https://www.acquisition.gov/ https://www.acquisition.gov/far/current/html/Subpart 42_15.html#wp1075411 https://www.acquisition.gov/far/current/html/52_207_211.html#wp1145644 http://uscode.house.gov/uscode-cgi/fastweb.exe?getdoc+uscview+t41t42+250+1286++%2842%29%20%20AND%20%28%2842%29%20ADJ%20USC%29%3ACITE%20%20%20%20%20%20%20%20%20
52.225-9 BUY AMERICAN ACT—CONSTRUCTION MATERIALS (SEPT 2010)
(a) Definitions. As used in this clause— “Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 ( 46 U.S.C. App. 1702), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
“Cost of components” means—
(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
“Domestic construction material” means—
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
“Foreign construction material” means a construction material other than a domestic construction material.
“United States” means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements the Buy American Act (41 U.S.C. 10a - 10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
[Contracting Officer to list applicable excepted materials or indicate “none”]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
CEU MIAMI – IFB_Construction 16 (REV 03/05/2012 FAC 2005-56) https://www.acquisition.gov/far/current/html/Subpart 2_1.html#wp1145508 http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/ https://www.acquisition.gov/far/current/html/Subpart 12_5.html#wp1077123
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American Act.
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
FOREIGN AND DOMESTIC CONSTRUCTION MATERIALS PRICE COMPARISON
Construction Material Description Unit of Measure Quantity Price (Dollars)* Item 1:
Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______
Item 2: _______ _______ _______ Foreign construction material _______ _______ _______ Domestic construction material [List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.] [* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]
CEU MIAMI – IFB_Construction 17 (REV 03/05/2012 FAC 2005-56)
CEU MIAMI – IFB_Construction 18 (REV 03/05/2012 FAC 2005-56)
3052.204-71 CONTRACTOR EMPLOYEE ACCESS (JUN 2006)
(a) Sensitive Information, as used in this Chapter, means any information, the loss, misuse, disclosure, or unauthorized access to or modification of which could adversely affect the national or homeland security interest, or the conduct of Federal programs, or the privacy to which individuals are entitled under section 552a of title 5, United States Code (the Privacy Act), but which has not been specifically authorized under criteria established by an Executive Order or an Act of Congress to be kept secret in the interest of national defense, homeland security or foreign policy.
This is the start of the file's text. The full file is on GovTribe.
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract of Offers | — | |
| Amendment 0001 | — |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .