Abate/Encapsulate Interiors in Hangar #2 Federal contract opportunity
Solicitation number
HSCG37-15-Q-PQQ103
Issued by
Department of Homeland Security US Coast Guard

View the file

Other files for this federal contract opportunity

Other files attached to Abate/Encapsulate Interiors in Hangar #2, newest first.
File Type Posted
FAR.CLAUSES.SERVICE.CONTRACTS.doc DOC document
SOW.Abate.Encapsulate.docx DOCX document
SCA.WD.Abate.Encapsulate.doc DOC document
SF1449_Sector_San_Diego.Abate.Encapsulate.PQQ103.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

What are work schedule interactions with USCG personnel and vendor employee’s?

Upon award, this will be discussed in detail with the Contracting Officer’s Representative (COR).

As per the Statement of Work (SOW), Page 2, 1.02.C, the vendor is responsible for proposing a, “Phasing & Lay Down Plan of how they intend to perform the work within the scheduled construction period”.

Is there hallways/ alternate ways to egress in the spaces impacted?

Yes

Is Air Monitoring being provided by USCG?

No, it is the vendor’s responsibility.

Are there Dry Wall Specifications?

Yes, dry wall and pain to match existing.

Can all three areas be worked on at one time?

Yes, if the entire space does not have to be vacated or impact operations.

Has the drywall been tested for asbestos?

No

Has the “Popcorn Ceiling” been tested for Asbestos?

Yes

If abatement/encapsulation is conducted without disturbing the dry wall, does the dry wall need to be replaced?

No

Does the vendor need to remove the HVAC unit in the Supply Closet location?

No, USCG personnel will take care of this.

What is the finish for the ceiling spaces?

Knock Down finish is sufficient