SOW_Waste_Water_Removal_JMTF_10Dec2015.pdf

PDF 47 KB Posted

Attached to
Waste Water Removal Federal contract opportunity
Solicitation number
HSCG32-16-Q-SAP008
Issued by
Department of Homeland Security US Coast Guard

About this file

Statement of Work revised 10 December 2015

View the file

Other files for this federal contract opportunity

Other files attached to Waste Water Removal, newest first.
File Type Posted
HSCG32-16-Q-SAP008(1).pdf PDF
Waste_Water_Test_Results.pdf PDF
SOW_Waste_Water_Removal_JMTF_31Dec2015.pdf PDF
WASTE_WATER_SOLICITATION_QUESTIONS_AND_ANSWERS.pdf PDF
SOW_Waste_Water_Removal_JMTF_3Dec2015.doc DOC document
Burn_Pan_Configuration_and_dimensions.pdf PDF
Drawing.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1: 12/10/15

DEPARTMENT OF HOMELAND SECURITY (DHS)

U.S. COAST GUARD

RESEARCH AND DEVELOPMENT CENTER (RDC)

STATEMENT OF WORK (SOW)

FOR

WASTE WATER REMOVAL FOR JOINT MARINE TEST FACILITY (JMTF)

1.1 Background

The U.S. Coast Guard (USCG) Research & Development Center (RDC) conducts a variety of research projects in the area of oil spill response. One of the specific topics is the use of in-situ burning. This is a technique which involves corralling the oil in a fire-resistant boom or enclosed area and igniting it. Although it creates a dark plume, it also removes the oil from the surface of the water. One of the research facilities owned by the RDC is a 40 foot by 100 foot open outdoor steel tank which is located at the Joint Marine Test Facility (JMTF) on Little Sand Island (LSI) in Mobile, AL. This facility was originally built in 1998 and a multiple of tests were conducted through 2002. At that time, the equipment was drained and the system placed inactive. A test series in November 2015 introduced an oil boom and diesel fuel into the tank for burning purposes. As a result the tank is currently holding contaminated waste water mixture (with Diesel Fuel #2 NR Dyed 15ppm) that must be removed and disposed of.

1.2 Scope

The scope of this order is to remove all waste water from the burn tank, decontaminate the tank and boom, and then remove any residual wash-down water. The scope also includes the disposal of the contaminated waste water in accordance with all applicable Federal, State, and local laws and regulations.

The Contractor is solely responsible for any and all spills, leaks, or releases during the performance of work under this order which occur as a result of the gross negligence of its agents, employees, or subcontractors.

The Contractor agrees to clean up such spills, leaks, or releases in a manner that complies with applicable Federal, State, and local laws, regulations, and procedures. Cleanup will be at no cost to the Government.

1.3 Applicable Documents

N/A file:///C:%5CUsers%5CJMCase%5CAppData%5CLocal%5CMicrosoft%5CWindows%5CTemporary%20Internet%20Files%5CContent.Outlook%5CAppData%5CLocal%5CMicrosoft%5CWindows%5CTemporary%20Internet%20Files%5CJMCase%5CAppData%5CLocal%5CMicrosoft%5CWindows%5CTemporary%20Internet%20Files%5CContent.Outlook%5CAppData%5CLocal%5CMicrosoft%5CWindows%5CTemporary%20Internet%20Files%5Cmfitzpatrick%5CAppData%5CLocal%5CMicrosoft%5CWindows%5CTemporary%20Internet%20Files%5CContent.Outlook%5CSCOPE%20PARAGRAPHS.doc

2 SPECIFIC REQUIREMENTS/TASKS

The contractor shall commence work on January 5, 2016. The contractor shall complete tasks

2.1 through 2.3 no later than six working days after work begins, and shall complete task 2.4 no later than nine working days after work begins. All tasks shall be completed on weekdays (Monday – Friday) between the hours of 7:00 AM and 3:30 PM excluding Federal holidays. All tasking shall be completed no later than 15 January 2016.

2.1 TASK 1: Removal of Waste Water

The contractor shall completely remove the waste water from the interior and outer wall sections of the tank and transfer it to a barge. The overall dimensions of the tank are 108 Ft Long x 40 Ft Wide x 5 Ft High. The tank will be filled to the 2.5’ mark in both the interior and outer wall sections.

The interior tank liquid load is estimated at 57,500 gallons and the outer wall section is estimated at 31,500 gallons, which results in a total waste water estimate of 89,000 gallons to be removed..

2.2 TASK 2: Wash-down of Interior Section of Tank

The contractor shall completely wash-down the interior section of the tank and the oil boom. The contractor shall then remove the residual wash-down water. The JMTF representative will indentify six locations within the interior of the tank and the contractor shall swipe six different locations with oil absorbent pads for JMTF representative inspection to verify all contamination has been removed.

The decontamination will be considered complete when there are no areas with a visible sheen on the walls or bottom of the tank’s surface and the absorbent pads contain no diesel fuel.

2.3 TASK 3: Wash-down of Outer Wall Section of Tank

The contractor shall completely wash-down the outer wall section of the tank and remove the residual wash-down water. The JMTF representative will indentify ten locations within the interior of the tank and the contractor shall swipe the ten different locations with oil absorbent pads for JMTF representative inspection to verify all contamination has been removed. The decontamination will be considered complete when there are no areas with a visible sheen on the walls and bottom of the tank’s surface; and the absorbent pads contain no diesel fuel.

2.4 TASK 4: Disposal of Waste Water

The contractor shall remediate and dispose of all waste and wash-down water in accordance with applicable laws and regulations. The contractor shall provide the government a manifest or bill of lading as proof of legal disposal of waste water. The contractor shall have all licenses and permits required by Federal, state and local laws to perform hazardous substance(s) removal or disposal services. The contractor will provide evidence of said documents to the Government representative prior to commencement of work under the order.

3 OTHER APPLICABLE CONDITIONS

3.1 Security

All information and deliverables under this order are Unclassified and will not require access to Sensitive but Unclassified (SBU) information.

3.2 Access to Government Facilities

The contractor shall be required to access JMTF’s Little Sand Island in Mobile, AL to complete removal of waste water and to complete decontamination procedures. .

3.3 Access to Government IT Systems

The contractor shall not require access to USCG IT Systems.

3.4 Facility at Little Sand Island

Little Sand Island is only accessible via boat. There are no dining or restroom facilities, refrigeration, fresh water sources, permanent power or pumps available. The contractor shall be responsible for providing any of the aforementioned facilities and amenities while completing tasking on Little Sand Island.

The contractor shall provide transportation to and from LSI. The contractor shall be required to access Little Sand Island via barge and moor alongside the ex-USS Shadwell in Mobile, AL.

Approximately 400 Ft of hose is required to reach the tank from the outboard side of the ex-USS Shadwell. US Coast Guard Sector Mobile facilities and spaces will not be available for use during any of the tasking within this order..

3.4.1 On-Scene Coordinators

JMTF on-scene coordinator(s): TBD NRL on-scene coordinator: TBD

JMTF on-scene coordinator(s) shall be contacted a minimum of 24 hours prior to arrival at ex USS Shadwell.

4 GOVERNMENT FURNISHED RESOURCES

The Government will provide the following information, data and documents to the contractor for work required under this task order:

• Existing JMTF Burn Pan Configuration

The contractor shall use Government Furnished Information, data and documents only for the performance of work under this order, and shall be responsible for returning all Government Furnished Information, data and documents to the Government at the end of the performance period. The contractor shall not release Government Furnished Information, data and documents to outside parties without the prior and explicit consent of the Contracting Officer.

5 CONTRACTOR FURNISHED PROPERTY/RESOURCES

The contractor shall furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this order, except for the Government Furnished Resources specified in SOW Paragraph 4. The contractor shall remove all equipment or supplies brought to LSI at the completion of work.

1.1 Background
1.2 Scope
1.3 Applicable Documents
1 SPECIFIC REQUIREMENTS/TASKS
1
1
1
2
2.1 TASK 1: Removal of Waste Water
2.2 TASK 2: Wash-down of Interior Section of Tank
2.3 TASK 3: Wash-down of Outer Wall Section of Tank
2.4 TASK 4: Disposal of Waste Water
3 OTHER APPLICABLE CONDITIONS
3.1 Security
3.2 Access to Government Facilities
3.3 Access to Government IT Systems
3.4 Facility at Little Sand Island
3.4.1 On-Scene Coordinators
4 GOVERNMENT FURNISHED Resources
5 CONTRACTOR FURNISHED PROPERTY/resources

File details come from the government source that posted it. Updated .