HSCEMS-17-Q-00005_-_Questions_and_Answers.docx
DOCX document 18 KB Posted
- Attached to
- Generator Replacement Federal contract opportunity
- Solicitation number
- HSCEMS-17-Q-00005
- Issued by
- Immigration and Customs Enforcement
About this file
Gov't responses to questions received by the deadline of 3/17/2017, 2:00pm EST.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| WD_2015-5469_rv3.pdf | ||
| Florence_Generator_SOW_(Final).docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HSCEMS-17-Q-00005
Questions and Answers
Questions and Answers
HSCEMS-17-Q-00005
Question
Question/Comment/Clarification
Response
| 1) |
| Confirm the following: |
Power supply to generator.
Power supply to the panel for trailer is 480V 3 phase, with a transformer to split the feed into 208V 3 phase also.
Power supplied to the 800a transfer switch is 480 3 PH from the transfer switch 120/240 Power supplied to the panel is 240/480 3PH and step down transformer is stepped down to 120/240 to trailer.
| 2) |
| Confirmation that you want a 1200A transfer switch to replace the existing 800A transfer switch? |
| We are asking that the transfer switch be compatible with the GEN SET, whether it is an 800a or 1200a. |
| 3) |
| What are the current loads at the Foxtrot bldg and Radiology Trailer? |
| Loads for today at 1200 were PH1-65a, PH2 58a, PH3 62a. Trailer- PH1, PH2 and PH3- read 0, no X-Raying today. From transformer to X-ray PH1 27a and PH2 25a |
| 4) |
| Confirmation that this is a design-build project and the contract is responsible for all engineering and design? |
This is a design-build project.
| 5) |
| Will there be a 1wk extension of the bid due date? |
| The Gov’t does not intend to extend the response due date. |
| 6) |
| Will there be an extension of the performance period (~180 days) if this is a design-build project? |
The Government does not intend to extend the period of performance.
File details come from the government source that posted it. Updated .