Responses_to_vendor_questions__1.docx
DOCX document 12 KB Posted
- Attached to
- CCTV Enhancement -Mandatory Site Visit Federal contract opportunity
- Solicitation number
- HSBP1017Q0130
About this file
Responses to vendor questions
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| HSBP1017Q0130.pdf | ||
| 2015-4187_Rev_6.pdf | ||
| SOW_RFQ.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Are Scaled Drawings available? A. no
2. Are Ceilings Suspended? Or Hard Lid? A. both
3. Are there existing Cable Trays for wiring above ceilings? A. Not sure
4. Can Existing Wiring be utilized? A. No
5. Is a “UPS” required? If so, What Time/Power Duration is required? A. No UPS required
6. Are “Or Equal” Equipment substitutions allowed? A. no
7. Is “Plenum Wire” acceptable? A. Yes
8. Is “After Hours Access” for said work, available to contractor at no add’l cost to the Gov’t? A. The times are 8-5pm, Mon-Fri, no holidays, but the awardee might be able to work with the onsite management to work outside these times but cost will not change.
9. What is the height of Exterior Cameras? (If any) A. 10+ feet