amendment 0004.pdf
PDF 24 KB Posted
- Attached to
- DoDDS Pacific Okinawa Minor Construction Federal contract opportunity
- Solicitation number
- HE1260-09-R-0028
- Issued by
- Department of Defense Education Activity
About this file
Amendment 0004
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| amendment0003.pdf | ||
| Amendment0002.pdf | ||
| 0001_to_.pdf | ||
| HE1260-09-R-0028.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HE600192110536
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions ofthe document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to change block 13. Additional Requirements B. An offer guarantee is required to An offer guarantee is not required.
As a result of this amenment:
1) Block 13B. is changed to is not required.
2) Question 4 from the previous amendment 0003 is removed.
3) The Government is not requiring a bid bond for this solicitation, nor for the project RFQs or RFPs once the contract is aw arded.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 18-Sep-2009
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X HE1260-09-R-0028
X 9B. DATED (SEE ITEM 11)
05-Sep-2009
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt ofOffer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one ofthe following methods:
(a) By completing Items 8 and 15, and returning 1 copies ofthe amendment; (b) By acknowledging receipt ofthis amendment on each copy of the offer submitted;
or (c) By separate letter or telegramwhich includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. Ifby virtue of this amendment you desire to change an offer already submitted, such change may be made by telegramor letter, provided each telegramor letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(Ifapplicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-Sep-2009
CODE
DODDS-P/DDESS-G - PROCUREMENT DIVISION
DIRECTOR'S OFFICE
PROCUREMENT DIVISION
UNIT 35007
APO AP 96376-5007
HE1260 7. ADMINISTERED BY (Ifother than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
HE1260-09-R-0028
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The offer guarantee has changed from is required to is not required.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
OKINAWA MINOR CONSTRUCTION-Q&A
Question 1: How does a multiple award Indefinite Delivery/Indefinite Quantity (IDIQ) work if we are awarded a contract?
Answer 1: This solicitation will result in multiple IDIQ contract awards. Each contract awardee (contractor) will compete with other awardees for minor construction project requirements. Each project requirement will be defined and described in the Statement of Work (SOW) section of either an RFQ or an RFP that is sent out only to the IDIQ contractors. (Whether the request will be for a simple quote or a price proposal, will depend on the dollar value and/or complexity of the project requirement). The contractors interested in submitting a quote or proposal will do so by a stated date & time deadline. A task order (TO) will then be issued against the IDIQ contract of the contractor chosen to undertake the project. The total price of the task order will be subtracted from the Not-To- Exceed (NTE) value of the IDIQ contract.
Question 2: How do we fill out the CLINS (i.e. ITEM NO: 0001, 1001, 2001, 3001 and 4001) for the base year and option years?
Answer 2: Calculate the total amount in your ELIN Worksheet for the corresponding base year and option years. Use those totals to fill out the CLINS.
Question 3: What is the square footage of the rooms in the Seed Project?
Answer 3: See the revised Seed Project Performance Work Statement (PWS) incorporated in this amendment.
(End of Summary of Changes)