STATEMENT OF WORK FOR PORTABLE SHEDS

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK FOR PORTABLE STORAGE AND MAINTENANCE STRUCTURES FOR CAMP PENDLETON RANGE 116

1.0 OBJECTIVE

NSWG-1 Ranges requires portable storage units and maintenance space for materials storage and repair at Camp Joseph Pendleton Range 116.

2.0 SCOPE

Contractor is to provide three (3) 12’x 20’portable wood frame structures to be delivered to NSWG-1 Range 116, Camp Pendleton CA. The contractor shall provide buildings meeting the requirements below with buildings being of a “truly portable” wood construction. Contractor shall be capable of delivering storage units as a “turn-key” item constructed offsite and delivered completed on a truck ready to be off-loaded and placed into operation. The contractor shall be able meet the below requirement for storage units.

3.0 REQUIREMENTS

3.1 STORAGE STRUCTURES

3.1.1 Structures are to meet the following criteria.

· 12’ x 20’ nominal length by width dimensions. (to include overhang)

· Gable type roof construction with 2”x 12” roof rafters 24” O.C.

· Roofing to consist of 5/8” Roof sheathing, 15lb felt paper, with 30 year 3 tab asphalt composite shingles fastened in accordance with shingle manufacturer’s specs.

· 2” x 4” fascia with 6”overhang.

· 2” x 4” stud walls 8’ high, 16” O.C. constructed with single shoe plate, top plate, and double plate.

· ½” Primed DURATEMP 4’ x 8’ Exterior sheathing fastened 8” OC in the field and 6” OC on the edges.

· 2” x 4” floor joists 16” O.C. running perpendicular to building length. ¾” tongue and groove flooring fastened 8” OC in the field and 6” OC on the edges.

· Three or 4” x 6” pressure treated “skids” supporting the floor joists running full length parallel to building length.

· One attached center of building, two attached 4’ O.C. providing a remaining nominal 2’ cantilever on each side.

· One 8” x 6’ 6” canister roll up door on two of the sheds and two 8” x 6’ 6” canister roll up doors and one steel 36”x 80” RH pedestrian door on one of the sheds.

· Dual locks on all doors.

3.2 CONTRACTOR SUPPORT:

3.2.1 Contractor shall construct the buildings at their facility.

3.2.2 Contractor shall provide transportation from contractor facility to: NSWG-1 Range 116 Basilone Road Camp Joseph Pendleton California 92055.

4.0 GOVERNMENT SUPPLIED MATERIALS

The government will provide all equipment, material, and personnel to off-load structures and it is the government’s sole responsibility to unload and place buildings in position.

5.0 PERIOD OF PERFORMANCE

The contractor shall provide all labor and construction materials to construct the portable sheds as described above by 12 JULY 2010 but no later than 12 SEPTEMBER 2010.

6.0 DELIVERY

Delivery of portable storage units must be coordinated fourteen (14) days in advance with NSWG-1 Range 116 Manager, Gene Rucks, 760-936-2115. Delivery address is:

NSWG-1 Range 116 CJP

Range 116, Bldg 116-01

Basilone Road

Camp Pendleton, CA 92055

7.0 QUALITY CONTROL Requirements

Inspection of each structure is to be performed by NSWG-1 Range 116 Manager Gene Rucks Camp Joseph Pendleton 760-936-2115. Structures that do not meet the specifications as stated in 3.1.1 will not be accepted.