Elevator_Modernization_Solicitation.pdf
PDF 622 KB Posted
- Attached to
- New Orleans Elevator Modernization Federal contract opportunity
- Solicitation number
- GS-07-P-16-UT-C-7001
About this file
Elevator Modernization Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_06.pdf | ||
| Amendment_5.pdf | ||
| Amendment_04.pdf | ||
| Amendment_03.pdf | ||
| C301_GC_Reps_ _Certs.docx | DOCX document | |
| Amendment_02.pdf | ||
| Elevator_Modernization_Solicitation_Amend_01.pdf | ||
| NOLA_5th_Court_14210_Elev._No._1-2_3-4_REVISED_2-3-16.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
GS-07P-16-UT-C-7001
GENERAL SERVICES ADMINISTRATION
PUBLIC BUILDING SERVICES
500 POYDRAS ST. RM 1010
NEW ORLEANS, LA 70130
ATTN: ALBERT THIBODEAUX
SEE ATTACHED
SEE BLOCK 7
EQ7PMB-16-5003
7PSA-NO
ALBERT THIBODEAUX (504)206-8757 or albert.thibodeaux@gsa.gov
RLA08003
02/16/2016
03/16/2016
3:00
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
ORDER FOR SUPPLIES AND
THIS NUMBER MUST APPEAR ON ALL PACKAGES AND PAPERS
RELATING TO THIS ORDER
PAGE
OF
SERVICES (Continuation) PDN NUMBER DATE ORDER NUMBER PAGES
ITEM NO.
(a)
SUPPLIES OR SERVICES
(b)
QUANTITY
ORDERED
(c)
UNIT
(d)
UNIT PRICE
(e)
AMOUNT
(f)
01 Perform elevator modernization for the John __1__ LS _________________ ___________________ Minor Wisdom Courthouse (Nos.3-4) New Orleans, LA.
All work shall be performed in accordance with attached scope of work and specifications
02 Option for elevator modernization for elevators (Nos 1-2) __1__ LS _________________ ___________________
03 Maintenance IAW Scope of Work and Specifications __1__ LS _________________ ___________________
GENERAL SERVICES ADMINISTRATION GSA 300-A (REV. 5/2010)
U.S. General Services Administration
Public Buildings Service
Greater Southwest Region
2-16-2016
Scope of Work
1. Project Title: NOLA Wisdom CH GSA Elevator Replacement
2. Project Location: LA0035ZZ JM Wisdom Courthouse 600 Camp Street New Orleans, LA 70130
3. Building Location Hours: To the greatest extent possible work is to be performed during normal business hours 6:00 AM to 6:00 PM. Coordination and approval from GSA COR is required for work performed other than normal hours. Any disruptive work, (i.e. noise, demolition of existing equipment, etc. is to be performed during other than normal working hours.
4. Purpose: Modernize two (2) existing geared traction Passenger elevators (Nos. 3-4) operating in one group. Provide option to modernize existing passenger elevator Nos. 1-2 within proposal. Provide new: AC motor, solid state microprocessor controls, cab, doors, and all associated work to provide four complete new passenger elevators. All work performed under this contract shall meet or exceed the current ASME-A17.1 Elevator Code and the Uniform Federal Accessibility Standards.
5. Points of Contact:
5.1 Contracting Officer: Brian Dwyer
819 Taylor Street, Room 12B Federal Building Fort Worth, TX 76102 Phone #: 817-978-7336 Brian.dwyer@gsa.gov
5.2 Contract Specialist: Albert Thibodeaux
500 Poydras St Ste 1010
New Orleans, LA 70130 Phone#: 504-249-6435 Albert.thibodeaux@gsa.gov
5.3 GSA PM/COR: Scott Cumby
819 Taylor St Fort Worth, TX 76102 Phone#: 817-978-7336 Scott.cumby@gsa.gov mailto:Albert.thibodeaux@gsa.gov
Greater Southwest Region
5.4
6. Notice to Proceed:
6.1 The Contracting Officer is the ONLY individual from the Government that can give the contractor a notice to proceed.
6.2 Before any of the work within the scope of the contract is started, the Contractor shall confer with the COR (Contracting Officer Representative) and agree on a sequence of procedure; means of access to premises and building; delivery of material and use of approaches; use of corridors, stairways, elevators, and similar means of communications; and the location partitions, eating spaces for spaces for Contractor’s employees and the like.
7. Period of Performance: 365 calendar days from the Notice to Proceed.
8. Description of Work: Contractor shall provide all materials, labor, tools, equipment and supervision to accomplish tasks as outlined in contractor documents.
8.1 All work performed for the passenger elevators shall conform to specification number 14210
9. Liquidated Damages: Failure to complete the work in a timely manner will result in assessment of liquidated damages in the amount of $250.00 per calendar day beyond the contract completion date, inclusive of properly executed contract modifications.
10. Other Requirements:
10.1 Security: All personnel performing work on the project needing access to the building shall have a GSA “Contractor” badge.
10.1.1 Personnel without a GSA Contractor Badge performing work can be escorted by a GSA badged contractor on a temporary basis.
10.2 Waste Diversion: Waste diversion is not a contract requirement for this project, however in keeping with GSA’s waste reduction initiatives 90% waste diversion is a goal for this project.
10.2.1 Provide proof (i.e. recycle tickets) of all waste diversion efforts.
11. Submittal:
11.1 Pre-Construction Submittals:
11.1.1 Submit for approval four samples of all finishes, car floor materials, operating and signal system fixtures, hoistway entrance and door materials, sills, protection pads, and light fixture lenses.
11.1.2 Written Project Schedule
11.1.3 Waste Diversion Plan
11.2 Post-Construction Submittals:
11.2.1 As Built Drawings
11.2.2 Three (3) sets of operating and maintenance manuals shall be furnished in bound form. Manuals shall include:
Greater Southwest Region
11.2.2.1 Description of the elevator system’s method of operation and control including the functions of signals, door devices and other specified features.
11.2.2.2 Written instructions for the adjustment and care of the equipment.
11.2.2.3 Replacement parts list with part numbers.
11.2.2.4 Type of lubricant required for each lubricated part.
11.2.2.5 Complete set of as-built wiring diagrams.
11.2.3 The identification label for each manual shall include the subject, building name and location, government contract number and the specified elevator numbers to which the manual applies.
11.2.4 One set of manuals shall be provided in tool cabinet in elevator machine room unless otherwise directed. The two additional sets shall be delivered to the Contracting Officer’s Technical Representative. Also, one copy of each on CD-ROM.
12. Attachments: The following items will become part of the Scope of Work.
12.1 Specification number 14210
13. Closeout Plan:
13.1 Customer Acceptance
13.2 Final Punch List Complete
13.3 Financial Closeout
13.4 Warranty Received
13.5 Onsite Training Conducted
Document: C201 / OCT 2015 (The Solicitation) Pages 1 of 21
GSA Solicitation No. GS-07-P-16-UT-C-7001 Construction Contract for John Minor Wisdom Building Elevator Modernization Solicitation 552.219-71 Notice to Offerors of Subcontracting Plan Requirements (MAR 2012)
The General Services Administration (GSA) is committed to assuring that maximum practicable opportunity is provided to small, HUBZone small, small disadvantaged, women-owned, veteran-owned, and service-disabled veteran owned small business concerns to participate in the performance of this contract consistent with its efficient performance. GSA expects any subcontracting plan submitted pursuant to FAR 52.219-9, Small Business Subcontracting Plan, to reflect this commitment. Consequently, an offeror, other than a small business concern, before being awarded a contract exceeding $700,000 ($1,500,000 for construction), must demonstrate that its subcontracting plan represents a creative and innovative program for involving small, HUBZone small, small disadvantaged, women-owned, veteran-owned, and service-disabled veteran owned small business concerns as subcontractors in the performance of this contract.
Table of Contents
I. General Information A. The Solicitation and Contract B. List of Solicitation Documents C. Authorized Representatives D. Pre-Proposal Conference E. Estimated Price Range F. FAR 52.228-1 Bid Guarantee G. FAR 52.236-27 Site Visit - Construction H. Receipt of Offers
II. Proposals A. Proposal Contents B. Proposal Format
C. Price Proposal D. Technical Proposal E. Other Information to Submit with Proposal F. Requirements for Joint Venture Offerors
III. General Provisions A. Availability of Funds B. Requests for Clarification or Interpretation C. Notice to Small Business Firms D. Information Concerning the Disclosure of Solicitation Results E. Affirmative Procurement Program F. Notice Concerning Preparation of Proposals
GSA Solicitation No. GS-07-P-16-UT-C-7001
(The Solicitation) Pages 2 of 21
G. Contractor Performance Information H. Safeguarding Documents Designated as Sensitive But Unclassified I. Additional Security Requirements
IV. FAR/GSAR Solicitation Provisions A. FAR 52.215-1 Instructions to Offerors—Competitive Acquisition B. FAR 52.216-1 Type of Contract C. FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work D. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal
Employment Opportunity for Construction E. FAR 52.233-2 Service of Protest F. Buy American G. Buy American Exceptions H. Small Business Subcontracting Plan I. Project Labor Agreements J. GSAR 552.252-5 Authorized Deviations in Provisions K. FAR 52.252-1 Solicitation Provisions Incorporated by Reference L. GSAR 552.102 Incorporating Provisions and Clauses by Reference
V. Additional Solicitation Provisions and Instructions A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal
Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 B. FAR 52.211-3 Availability of Specifications Not Listed in the GSA Index of Federal
Specifications, Standards and Commercial Item Descriptions C. Additional Provisions D. Cost or Pricing Data
VI. Method of Award A. Evaluation of Offers B. Determination of Responsibility C. Price Reasonableness / Price Realism D. Unbalanced Prices E. Total Evaluated Price F. Non-Price Factors G. Evaluation of Joint Venture Offerors
I. General Information I.A. The Solicitation and Contract
(1) This Solicitation sets forth requirements for proposals for a Contract to construct the Project described in the Solicitation Documents. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein. The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.
(2) Neither the Solicitation nor any part of an Offeror's proposal shall be part of the Contract except to the extent expressly incorporated therein by the Contracting Officer.
(The Solicitation) Pages 3 of 21
(3) The Offeror's proposal submitted in response to this Solicitation shall constitute a firm offer. No contract shall be formed unless and until the Contracting Officer has countersigned the SF 1442 submitted by an Offeror, and delivered to the Contractor a copy of the SF 1442 with original signatures together with the Agreement reflecting the Offeror's proposed prices.
I.B. List of Solicitation Documents
The Solicitation Documents are comprised of:
(1) The Solicitation
(2) Offeror Representations and Certifications Form
(3) Other Forms Required For Submission with Proposals
(4) Standard Form (SF) 1442 – Solicitation Offer and Award
(5) The Agreement and Attachments to the Agreement
(6) Scope of Work, dated 7 July 2015
(7) Section 14210 – Electric Elevators
(8) Wage Determination LA160045, dated 15 January 2016
I.C. Authorized Representatives
The following individuals are designated as the authorized GSA representatives under this Solicitation:
(1) Contracting Officer
Brian Dwyer 819 Taylor Street – Federal Building Rm 12B01 – 7PQC Fort Worth, Texas 76102 (817)978-7336 Brian.dwyer@gsa.gov
(2) Alternate Point of Contact
Albert Thibodeaux 500 Poydras St.
Rm 1010 – 7PQC New Orleans, LA 70130 (504)249-6435 Albert.thibodeaux@gsa.gov
I.D. Pre-Proposal Conference A pre-proposal conference regarding this Solicitation is scheduled as follows:
Date: Feb 17, 2016
Time: 1:00 p.m. CDT Location: Wisdom Courthouse, New Orleans, LA
Interested parties must notify the Contracting Officer for further information about attendance and to confirm location, time, and date. Only those parties who have notified the Contracting
(The Solicitation) Pages 4 of 21
Officer and provided necessary information in advance of the meeting will be allowed to attend.
To request a reasonable accommodation due to a disability, contact the Contracting Officer.
I.E. Estimated Price Range
The estimated price range for the Project is between $1,000,000 and $ 5,000,000.
I.F. FAR 52.228-1 Bid Guarantee (SEP 96)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
I.G. FAR 52.236-27 Site Visit - Construction (FEB 95)
(1) The clauses at FAR 52.236-2, Differing Site Conditions, and FAR 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation and are in the attached Agreement. Accordingly, Offerors are urged and expected to inspect the site where the work will be performed.
(2) Site visits will be held at the following dates and times:
Date: [Feb 17, 2016 ] Time: [1:00 p.m. CDT – at the Wisdom Courthouse New Orleans, LA ] http://www.acquisition.gov/far/current/html/52_233_240.html#wp1113365 http://www.acquisition.gov/far/current/html/52_233_240.html#wp1113375
(The Solicitation) Pages 5 of 21
(3) Pre-registration is required for all attendees to the pre-proposal Site Visit. The Site Visit shall be limited to not more than four (4) representatives from each Offeror. Offerors shall submit a Visit Authorization Request (VAR) identifying all attendees from their respective team.
Participants must have a valid, Government issued picture identification, driver’s license preferred, to gain access for the pre-proposal Site Visit. Notification of the location of entry, where attendees are required to meet, and all other requirements for the Site Visit will be issued to the Offerors. Submit the VAR to the point of contact listed below.
For further information about the site visit or access requirements, please contact:
Name: [ Greg Lee ] Address: [500 Poydras St. Room 1044 ]
Telephone: [ 504-288-5960 ] Email: [Gregory.lee@gsa.gov ]
I.H. Receipt of Offers
(1) In order to be considered for award, offers conforming to the requirements of the solicitation must be received at the following office no later than 3:00 pm local time on the following date and at the following address:
March 16, 2016 General Services Administration – PBS 500 Poydras Street Room 1010 – ATTN: Albert Thibodeaux New Orleans, LA 70130
(2) Offers sent by commercial package delivery and hand delivery shall be deemed received as of the date and time of delivery to the office designated for receipt of offers.
(3) Offers sent by United States Mail shall be deemed timely if delivered to the address of the government installation designated for receipt of offers on or before the date established for receipt of offers.
II. Proposals
II.A. Proposal Contents Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:
(1) Price Proposal
(2) Technical Proposal
(3) Representations and Certifications
(4) Bid Guarantee, using Standard Form 24
(5) Subcontracting Plan
(6) GSA Form 527 – Contractor’s Qualification and Financial Information
(The Solicitation) Pages 6 of 21
(7) Other Documents as Required
II.B. Proposal Format Offers in original and three (3) copies and one (1) electronic copy to perform the work are due at the place and time specified in Section I.H. of this solicitation. Proposals shall be submitted on 8 ½” X 11” size paper with no smaller than 11 font (type size) and shall be clear, concise, typewritten, legible, and presented in a professional manner. The proposal shall be organized by volumes so as to clearly delineate and separate the price proposal and technical proposal from each other for ease in review, labeled as follows: Price Proposal – Volume II.
II.C. Price Proposal
(1) Contents
The Price Proposal shall consist of the SF 1442 and the Agreement, with prices and/or rates indicated for each price element shown on the pricing form included in Section II of the Agreement. Indicate the Base Contract Price, or if no such distinction is made, the Contract Price, in Block 17 of the SF 1442, which must be fully executed by the Offeror.
(2) Qualifications, Exclusions and Conditions
If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.
II.D. Technical Proposal The Technical Proposal shall include the information requested below for the non-price factors described in Section VI.
(1) Technical Approach.
a) In a narrative, address/state your understanding of the overall nature of the project and the major elements of work required: In the narrative include a description of the proposed elevator data listed below:
• Elevator rated load lifting capacity in pounds.
• Elevator car rated speed in feet per minute.
• Car travel in feet.
• Number of landings.
• Number of openings.
• Platform size.
• Class of service, i.e., passenger or freight.
• Type of machine, i.e., geared or gearless.
• Type of control, i.e., static, 3vf Drive or SCR.
• Type of drive system, i.e., AC regenerative, AC non – regenerative, SCR
• Type of operation, i.e., two stop single car selective collective, two car selective collective or group automatic.
• Type of hoistway doors.
• Type of car door or gate.
• Type of signal system.
• Characteristics of power supply.
• Finishes.
(The Solicitation) Pages 7 of 21
• Fixture design, hoistway door and entrance treatment.
b) Submit a proposal for the following elevator performance criteria:
• Estimated energy savings over existing equipment.
c) Describe proposed methods for reviewing the following related work for compliance with the latest Codes, inspecting and evaluating for necessary alterations or repairs, and recommending replacements or repairs.
• Temporary guards at all hoistway openings as required under "Accident
Prevention" clause of the Agreement.
• Existing smoke detectors and Annunciator Panel for Emergency Elevator Recall will be retained and any new devices added shall be connected into the new elevator control system by the Elevator Contractor.
d) Describe proposed treatment of hoistway entrances and doors showing their method of operation, details of construction and method of fastening to the structural members of the building. Provide details of recommended treatment for doors and fixtures, i.e., to match existing elevator lobbies.
(2) Experience
Provide evidence of at least five (5) projects in the past 6 years (from the final proposal due date of this solicitation) installing or modernizing elevators comparable in scope and complexity and number of elevators operating successfully for at least 2 years under the contractor's maintenance (1 year under the warranty plus 1 additional year of maintenance).
For purposes of this solicitation, a group of two elevators operating together shall be considered comparable in number.
Provide project title, description of project and work performed, name and telephone number of reference.
To demonstrate experience, offerors shall submit a minimum of 3 recent projects involving both modernization and maintenance. If 3 modernization projects submitted do not include requirements for both modernization and maintenance, offerors shall submit additional elevator maintenance projects so at least 3 elevator maintenance projects/contracts are submitted. On additional elevator maintenance contracts that did not include installation, offeror shall show that they provided maintenance for at least 1 year on each maintenance contract.
Provide details for all elevator modernization projects completed within the last 3 years.
(The Solicitation) Pages 8 of 21
For each project, submit the names, addresses, and current telephone numbers of representatives representing the following entities. Provide fax numbers and e-mail addresses, if available.
Owner Principal Tenant Organization, if applicable Construction General Contractor, if applicable
(3) Schedule
Describe proposed work schedule for quality enhancement of the conveying systems in a timely, well planned manner, including phasing to provide the best possible elevator service while avoiding excessive shut down time.
Provide a bar chart, line chart or other suitable method of scheduling, indicating the major construction milestones and the planned sequence of activities.
Include schedule for providing operation and maintenance services for the one year warranty period.
(4) Past Performance
The Government will contact references from comparable projects listed under “Experience” to determine the quality of the offeror’s past performance. The Government may consider references regarding the offeror’s performance on contracts not submitted by the offeror, whether similar or not, that the Government is aware of during the evaluation process. The Government will not be responsible if reference telephone numbers provided by the offeror are not current; if reference declines to comment, or if references cannot be contacted within four (4) attempts.
Provide information on any past or current contracts, including Federal, State and local government that had small business disadvantaged business (SDB) subcontracting requirements. Provide a reference (name, title, phone number) of an owner representative who is familiar with your compliance with any SDB subcontracting plan goals, monetary targets for SDB participation and compliance with reporting requirements. Provide a written narrative, describing your past outreach efforts to utilize small businesses, including small disadvantaged businesses and describe the extent that small disadvantage businesses concerns will be used in the performance of this contract.
(5) Preventive Maintenance Approach
Describe how your firm will perform the full service maintenance described in Section 14210.
Describe the overall program, which must identify the equipment to be maintained, the frequencies for maintenance on each piece of equipment, the maintenance to be performed and the location of the equipment. Include proposed work plan for responding to routine as well as
(The Solicitation) Pages 9 of 21 emergency calls during and outside normal working hours, and for performing repairs as well as needed tests of equipment and systems. Also please describe whether free service warrantee period will be contracted or in-house.
II.E Other Information to Submit with Proposal
(1) Representations and Certifications
Offerors submitting a proposal in response to this Solicitation shall complete electronic Annual Representations and Certifications in conjunction with required Entity registration in the System for Award Management accessed via https://www.sam.gov. Offerors shall also submit with their proposal, the Annual Representations and Certifications (FAR 52.204-8), using the attached Offeror’s Representations and Certifications (C301).
II.F. Requirements for Joint Venture Offerors
(1) All offers submitted by joint ventures must include a copy of an executed joint venture agreement (with original signatures) which fully discloses the legal identity of each member of the joint venture, the relationship between the members, the form of ownership of each member, and any limitations on liability or authority for each member.
(2) An authorized representative of each member of the joint venture must sign the SF 1442 accompanying an offer regardless of any agency relationship established between the members.
(3) In the case of corporations that are joint venture members, the corporation secretary must certify that the corporation is authorized to participate in the joint venture, either by so certifying in the joint venture agreement, or by submitting a separate certification to the Government. The joint venture must also provide a certificate that identifies a principal representative of the joint venture with full authority to bind the joint venture.
(4) Representations and certifications, financial information, and past performance information must be submitted for each member of the joint venture.
III. General Provisions
III.A. Availability of Funds Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the contract shall be subject to the availability of appropriated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of contract award.
III.B. Requests for Clarification or Interpretation
The Government will attempt to answer all requests for clarifications or interpretations of the Solicitation Documents prior to the date set for receipt of offers, but does not warrant that all such requests will be answered within 15 calendar days. Therefore, prospective offerors should make such requests not less than 15 calendar days prior to the date set for receipt of offers.
III.C. Notice to Small Business Firms https://www.sam.gov/
(The Solicitation) Pages 10 of 21
A program for the purpose of assisting qualified small business concerns in obtaining certain bid, payment, or performance bonds that are otherwise not obtainable is available through the Small Business Administration (SBA) (www.sba.gov). For information concerning SBA's surety bond guarantee assistance, contact your SBA District Office.
III.D. Information Concerning the Disclosure of Solicitation Results
This acquisition is being conducted under the provisions of FAR Part 15 as a negotiated procurement. In accordance with FAR 3.104 and FAR 15.207, after receipt of proposals, no information regarding the identity of those submitting offers, the number of offers received, or the information contained in such offers will be made available until after award except as provided by FAR 15.503.
III.E. Affirmative Procurement Program
GSA has implemented an Affirmative Procurement Program (APP) intended to maximize the use of recovered materials, environmentally preferable, and bio-based products. Offerors should familiarize themselves with the requirements for using and reporting on the use of such materials in performance as set forth in the Agreement. Refer to clauses FAR 52.204-4 requiring double sided printing on recycled paper for all reports and FAR 52.223-10 encouraging vendors to practice waste reduction.
III.F. Notice Concerning Preparation of Proposals
Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract contemplated by the Solicitation in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out; that all pricing and other numerical data is accurately calculated; and that all copies of the Offer contain the same information.
III.G. Contractor Performance Information
(1) Evaluating Contractor Performance: The General Services Administration is using the Contractor Performance Assessment Reporting System (CPARS) module as the secure, confidential, information management tool to facilitate the performance evaluation process.
CPARS enables a comprehensive evaluation by capturing comments from both GSA and the contractor. The website for CPARS is http://www.cpars.gov
Completed CPARS evaluations are sent to the Past Performance Information Retrieval System (PPIRS) which may then be used by Federal acquisition community for use in making source selection decisions. PPIRS assists acquisition officials by serving as the single source for contractor past performance data.
(2) CPARS Registration: Each award requiring an evaluation must be registered in CPARS.
The contractor will receive several automated emails. Within thirty days of award, the contractor will receive an e-mail that contains user account information, as well as the applicable contract and order number(s) assigned. Contractors will be granted one user account to access all evaluations.
(3) Contractor CPARS Training: Contractors may sign up for CPARS training. A schedule of classes will be posted to the CPARS training site (http://www.cpars.gov/allapps/cpcbtdlf.htm) and updated as needed.
http://www.sba.gov/ http://www.cpars.gov/ http://www.cpars.gov/allapps/cpcbtdlf.htm
(The Solicitation) Pages 11 of 21
(4) Contractor Representative (CR) Role: All evaluations will be sent the Contractor Representative (CR) named on your award. The CR will be able to access CPARS to review and comment on the evaluation. If your CR is not already in the CPARS system, the contracting officer will request the name and email address of the person that will be responsible for the CR role on your award.
Once an evaluation is ready to be released the CR will receive an email alerting them the evaluation is ready for their review and comment. The email will indicate the time frame the CR has to respond to the evaluation; however, the CR may return the evaluation earlier than this date.
GSA shall provide for review at a level above the contracting officer (i.e., contracting director) to consider any disagreement between GSA and the contractor regarding GSA’s evaluation of the contractor. Based on the review, the individual at a level above the contracting officer will issue the ultimate conclusion on the performance evaluation.
Copies of the evaluations, contractor responses, and review comments, if any, will be retained as part of the contract file.
III.H. Safeguarding Documents Designated as Sensitive But Unclassified
Certain information contained in the Solicitation Documents may have been designated as Sensitive but Unclassified (SBU) building information. With respect to such information, Offerors shall agree to the terms for receipt of such information, as set forth in the provision “Administrative Matters” in Section III of the Agreement, as a condition of receipt of such information.
III.I. Additional Security Requirements
(1) FAR 52.204-2, Security Requirements, August 1996
(2) FAR 52.204-9, Personal Identity Verification of Contractor Personnel, January 2011
(3) GSAR Clause 552.204-9, Personal Identity Verification Requirements, October 2012
This project is classified as Sensitive But Unclassified (SBU) .
IV. FAR/GSAR Solicitation Provisions
IV.A. FAR 52.215-1 Instructions to Offerors—Competitive Acquisition (JAN 04)
(a) Definitions. As used in this provision— “Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer’s discretion, result in the offeror being allowed to revise its proposal.
“In writing,” “writing,” or “written” means any worded or numbered expression that can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.
(The Solicitation) Pages 12 of 21
“Proposal modification” is a change made to a proposal before the solicitation’s closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
“Time,” if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.
(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).
(c) Submission, modification, revision, and withdrawal of proposals.
(1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and
(ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror. Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.
(2) The first page of the proposal must show—
(i) The solicitation number;
(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation; and
(v) Name, title, and signature of person authorized to sign the proposal.
Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.
(3) Submission, modification, revision, and withdrawal of proposals.
(i) Offerors are responsible for submitting proposals, and any modifications or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and—
(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(The Solicitation) Pages 13 of 21
(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government’s control prior to the time set for receipt of offers; or
(3) It is the only proposal received.
(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.
(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225- 17, Evaluation of Foreign Currency Offers, is included in the solicitation.
(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.
(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.
(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).
(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall—
(1) Mark the title page with the following legend:
This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed—in whole or in part—for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of—or in connection with—the submission of this data, the Government shall have the right to duplicate, (The Solicitation) Pages 14 of 21 use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and
(2) Mark each sheet of data it wishes to restrict with the following legend:
Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.
(f) Contract award.
(1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.
(2) The Government may reject any or all proposals if such action is in the Government’s interest.
(3) The Government may waive informalities and minor irregularities in proposals received.
(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.
(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government’s best interest to do so.
(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government. (f)(4) The Government intends to evaluate proposals and award a contract after conducting discussions with offerors whose proposals have been determined to be within the competitive range. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals. Therefore, the offeror's initial proposal should contain the offeror's best terms from a price and technical standpoint.
(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more contract line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.
(The Solicitation) Pages 15 of 21
(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.
(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:
(i) The agency’s evaluation of the significant weak or deficient factors in the debriefed offeror’s offer.
(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.
(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.
(iv) A summary of the rationale for award.
(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.
(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.
IV.B. FAR 52.216-1 Type of Contract (APR 84)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
IV.C. FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work
(MAY 14)
(a) (1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b) (1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.
IV.D. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (FEB 1999) (Applicable to solicitations resulting in construction contracts in excess of $10,000.)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
(The Solicitation) Pages 16 of 21
Goals for Minority Participation for Each Trade Goals for Female Participation for Each Trade
31.0%. 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed.