Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Pre-ProposalMTG-_Q A.pdf | ||
| Civil_-_Drawings.pdf | ||
| Reps_and_Certs.pdf | ||
| Solicitation_-_Sally_Port.pdf | ||
| Structural_Drawings.pdf | ||
| Architectural_Drawings.pdf | ||
| MEP_Drawings.pdf | ||
| Specs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GSA
STATEMENT OF WORK
FOR
Bob Casey Sallyport/Elevator
Bob Casey Federal Courthouse 515 Rusk Avenue
HOUSTON, TX 77002
10/10/2014
1.0 PROJECT OVERVIEW
This task order is for the construction of a sallyport/elevator at the Bob Casey Federal Courthouse, Houston, TX 77002. The project will require parts and labor as specified below.
2.0 GENERAL INFORMATION
Specific work items are listed below.
EXECUTIVE SUMMARY
The United States Marshals Service addition of a security sallyport and elevator to the northwest corner of the existing Bob Casey Federal Courthouse Building is an important opportunity to reduce vehicular congestion within the existing north security wall perimeter parking lot where the judges and government officials park and where the transport buses currently unload and load prisoner’s for processing, detainment, and court appearances. The newly proposed USMS Sallyport will allow the transport buses to utilize the newly attained easement property directly to the west of the Bob Casey Federal Building for the construction of a secure sallyport and prisoner elevator from grade level directly to the 10th floor (directly into the USMS secured level). A new secure elevator will allow the current Bob Casey judges/freight elevators within the courthouse to be used as intended for the judges and the movement of freight while removing the element of a security detail to escort prisoners to the 10th floor as the facility is currently being utilized. There are multiple factors that the USMS Sallyport must contend with. The first is the amount of existing underground utilities within the easement property that has been attained from the city for the construction of this project. The utilities range from an existing 6” water supply line for the city to electrical and data cables for the Theater District, as well as street light electrical systems and light poles. All of these utilities will have to be properly identified during construction and re-routed within the very tight site constrictions with the new sallyport structure. The second factor is the existing stairwell that allows access from the underground parking garage to the surface at Capital Street.
Measures have been taken to ensure that the City of Houston has sufficient vertical access in other areas that the removal of this stairwell will not present a problem to GSA. The third issue is the current Metro Light Rail expansion work on Capital and Rusk streets where the street configuration and underground utilities are being altered and will present an additional challenge in coordination.
At this time, Metro’s construction team is willing to make minor revisions to accommodate the Government’s requirements since the Metro Light Rail expansion work is already under way. This should allow minor work by GSA to finalize this area during construction. The fourth issue is the design restrictions in accordance with the State Historic Preservation Office (SHPO). The proposed design has gone through multiple design changes reviewed by GSA and SHPO where the final accepted design dictates the use of a lower elevator shaft with an MRL Elevator and the use of polished white concrete masonry units.
OBSERVATIONS AND ANALYSIS The USMS has a range of requirements and specifications for special purpose and support spaces that must be met. The sallyport consists of several key spaces: 1) Vehicle Sallyport, 2) Weapons Closet, 3) Prisoner Circulation, 4) Elevator, and 5) Mantrap Sallyport.
Standards require a vehicle sallyport to be screened from public view or views from any adjacent properties, be paved in concrete, and to have intercoms and cameras monitoring. The sallyport must have a roof, solid walls, and high-speed rolling overhead doors in accordance with USMS Requirements and Specifications for Special Purpose and Support Space Manual (Publication #64).
USMS Guidelines call for the vehicle sallyport to accommodate at least one of the largest vehicles typically used (50ft. bus) or two smaller transport vans and provide for a covered and secured area for prisoners to be unloaded and loaded and for minor vehicle maintenance and washing. This space is to be sprinklered, and monitored by security cameras controlled from the USMS command and control center. There was a specific request by the USMS to provide for a weapons closet with a minimum of 36 square feet in which a variety of weapons lockers can be stored for the Marshals use. This space is to be a moderately conditioned space with a security rated ceiling and scramble pad detention grade door access. The prisoner circulation area must be a minimum of 5 feet wide with glazed CMU walls and a security rated ceiling with duress alarms and security cameras monitored from the USMS command and control center. The configuration of the sallyport at the Bob Casey Federal building has created a space that allows for greater than 5 feet of width as well as a small additional area for a US Marshal to guide the prisoners into the elevator while not impeding the prisoner traffic flow. This space is a moderately conditioned space with a security rated ceiling and scramble pad detention grade door access.
The elevator has several specific requirements, among them being a sliding detention door and security screen within the cab to divide the US Marshals from the prisoners being transported vertically. The smaller deputy compartment contains the control panel operated by a deputy who is connected by intercom to the USMS command and control center. All surfaces within the cab are stainless steel with security rated light fixture and an access panel in the deputy compartment. The type of elevator is not directly dictated but in this case an MRL (Machine-room-less Elevator) was selected in order to minimize the space requirements for a separate Machine Room. Due to site constraints a traditional traction elevator would have forced the machine room to be located above the elevator with access to the roof since the judge’s chambers could not be impacted on the 11th and 12th floors of the Federal Building. The use of an MRL allowed for a shorter elevator shaft and was ultimately accepted by the State Historic Preservation Office (SHPO) since the Bob Casey Federal Building is now considered a Historic structure. The “Mantrap” Sallyport is a man-sized vestibule with a door at either end and functions as an interlock. The mantrap sallyport is the transition space between the prisoner and restricted or public space and is to be equipped with glazed CMU walls and a security rated ceiling with duress alarms and security cameras monitored from the USMS command and control center and is a moderately conditioned space with security rated ceiling and scramble pad detention grade door access. This sallyport exits out into the existing Bob Casey Secured parking lot where additional security is already in place.
DESIGN PROGRESSION
The original design of the elevator system was to utilize a traditional traction elevator system. Being that the grade level was very restricted, the elevator machine room would have to be located either under the elevator (which was quickly eliminated due to severe cost implications) or locating the machine room at the top of the elevator shaft, requiring either access from a floor level above the 10th floor to the roof. The 11th and 12th floors were both determined to be inaccessible due to the locations interfering with existing Judges Chambers, forcing the traction elevator system to reach above the existing roof line for an accessible Machine Room. The exterior materials of this design have had multiple transitions. The original architectural approach was to enforce the use of shellstone panels at corner edges to integrate with the existing Federal Courthouse materials (white shellstone) while using a different material at the vertical transition of the elevator shaft against the Courthouse to differentiate the two structures. The transition materials ranged in concepts from tempered dark glass panels to dark split-face CMU. The USMS did not want any glass panels in the design and preferred to see solid materials. At the time of the 35% submission, the design was utilizing shellstone panel corners and darker toned split-face cmu at the transition. Based on the projected cost of running the elevator to the roofline, it was determined that the elevator type would have to be changed to remove the machine room altogether. From this direction an MRL (Machine-Room-Less) elevator system would have to be used and the design shifted to this type during the 35% to 65% submission, requiring a substantial plan revision. Multiple exterior design options resulted from this configuration, also using a darker toned split-face cmu at the vertical transition between the two buildings to separate the two structures. Several submissions to the State Historic Preservation Office were made in conjunction with GSA and the ultimate design materials were driven by those entities, changing from shellstone (which matched the existing building) to polished cmu. Costs of using oversized masonry were found to be more economical than standard sized cmu as well. The use of white oversized polished CMU units was selected for the entire exterior surface of all new structures, including the in-set vertical transition.
The design at this point has less of a visual impact, no differentiation and matches the existing building in color only, but was approved by SHPO.
Initial concept rendering with access to the 11th floor using a traditional traction elevator with shellstone panels and a dark glass vertical transition or dark split-face cmu vertical transition. The design of the elevator shaft using a traditional traction elevator with access to the roof with shellstone panels and dark split-face cmu at the vertical transition. This rending now shows the use of an MRL elevator with limited shellstone panels and a larger use of split-face cmu with a dark vertical transition between the two structures. The final submitted rendering of the new sallyport uses oversized white polished cmu units in its entirety, including the inset vertical transition.
Civil Design Storm Drainage: The existing drainage pattern at the location of the proposed Bob Casey Sallyport is from south to north. The grade of the proposed driveway follows the existing grading and drainage patterns. Trench drains the full driveway width, are called for, between Rusk Street and the sallyport structure to intercept storm water runoff. Between the sallyport structure and Capital Street, storm water run-off is collected by a series of Junction boxes / Type ‘A’ Inlets and a Type ‘BB’ Grate Inlet. The trench drains have been sized to capture all of the anticipated storm water run-off generated, from the proposed driveway and the immediate surrounding area, between the North right of way line of Rusk and the sallyport. Storm water collected by the trench drains is conveyed under the sallyport via an 18-inch diameter reinforced concrete pipe to a series of Junction Boxes / Type ‘A’ Inlets located north of the sallyport. The storm water is then routed through the junction boxes to the City of Houston storm sewer on Capital Street via a 24-inch reinforced concrete pipe. The storm drain connection to the City of Houston storm sewer system is at an existing Type ‘BB’ Inlet located along the south curb line of Capital Street. The existing Type ‘BB’ Inlet will be adjusted and converted to a Type ‘BB’ Grate inlet to accommodate the proposed sallyport driveway. Water: A 6-inch water main is being relocated to accommodate the proposed sallyport structure, associated storm drainage, sanitary sewer lines and sewer appurtenances. The City of Houston has determined that the 6-inch water main, located in the existing utility easement along the west side of the Bob Casey Federal Building, must remain in service.
Sections of the new 6-inch water main must be encased in a 12-inch diameter steel casing to comply with City of Houston requirements and Texas Commission of Environmental Quality, (TCEQ) regulations. The 6-inch water main will be connected to existing water lines located in the Capital and Rusk Street rights of ways. An existing fire hydrant, located at the intersection of the proposed sallyport driveway and Rusk Street, is within the proposed drive and will be relocated. The fire hydrant will be relocated to the east side of the sallyport driveway.
Sanitary Sewer: A sanitary sewer service connection is required to serve the internal floor drains and elevator sump drain. A proposed 6-inch sanitary sewer line will run from the sallyport to an existing sanitary sewer stub located within the Capital Street right of way. The sallyport floor drain and elevator sump drains are routed through an oil and grit separator prior to the connection of the City of Houston sanitary sewer main. A portion of the sanitary sewer will be encased in a 12-inch diameter steel casing due to its proposed location and to comply with TCEQ regulations. A portion of the sanitary sewer is located parallel to and below the proposed 24-inch RCP storm sewer.
Structural Design
2. Design Criteria
The structure will be designed for the following loads.
1st Floor 100 psf live load Roof 20 psf live load Wind Load 110 mph, 3 second gust per IBC 2006 In addition to the live loads the roof structure will be designed for 10-psf ceiling and mechanical.
Reductions in live loads will be taken as prescribed in the IBC Code.
To meet ISC security requirements all of the exterior walls on the first level are 8" CMU fully grouted and all interior walls are 6" CMU walls. Elevator tower walls on first and tenth levels are also 8" CMU walls fully grouted, this are the floor that the elevator will service. The rest of the floors will have 6" metal stud walls attached to structural steel.
The roofs over all the spaces will be steel deck attached to structural beams and joist.
3. Structural System
The roof structure will consist of steel beams and type B 1 ½”roof deck.
The steel beams will also bear on 8” CMU walls. Ground floor slab will be slab on grade.
The tower structural system will consists of steel tubes for columns and wind braces.
4. Lateral System
The lateral system consists of wind braces.
5. Foundations
The foundations were designed based on the soil report prepared by A.R.M Soil Testing dated February 24, 2012. The first floor slab will be 6” thick slab on grade with perimeter grade beams. Typical columns to be supported by straight shaft piers and the tower columns will be supported on straight shafts piers. Drilled pier locations where determined based on the location of existing building foundations, existing retaining wall and existing building location. Since area of new garage and sally port is very compact and there are existing elements the locations of the piers were determine based on locations where foundation system will work and will not interfere with any of the existing items.
6. CODES AND STANDARDS
The design and construction of structural systems will conform to, but are not limited to the following codes and standards.
International Building Code, latest edition, International Code Council, with City of Houston Amendments.
Minimum Design Loads for Buildings and Other Structures, ASCE / SEI 7-05, American Society of Civil Engineers.
Manual of Steel Construction, Load and Resistance Factor Design, Thirteenth Edition, American Institute of Steel Construction.
Building Code Requirements for Masonry Structures, ACI 530-02, and Specifications for Masonry Structures, ACI 530.1-03, and American Concrete Institute.
ACI 318, latest edition, American Concrete Institute.
MEP DESIGN
Mechanical Systems:
1. Cooling/Heating: Cooling and heating of the Prisoner Circulation Area, Weapon Closet, Mantrap, Electrical Room and Control Closet are accomplished through a VRV (Variable Refrigeration Volume) heat pump system. Each area is independently controlled through separate AHU’s controlled via infra-red remote control devices. Although simultaneous heating/cooling is not available, each area can be controlled to a different temperature within a heating or cooling mode.
2. Garage Exhaust: The Vehicle Sallyport has 1-1400 cfm garage exhaust fan.
This fan draws air in from 2 separate air intake louvers and is controlled via a CO (carbon monoxide) sensor which cycles the fan on and off.
3. Elevator Shaft Exhaust: The elevator shaft is provided with an air circulation and exhaust system. Air, 1,200 cfm, is drawn in from the top of shaft and exhausted at an elevation of 84” above grade. This air will tend to keep the shaft fresh and will work in tandem with the elevator cab ventilation fan provided with the elevator.
4. Fire Sprinkler Piping Freeze Control: The main Vehicle Sallyport is equipped with 4-5KW electric fan heaters. These heaters are designed to maintain the Sallyport temperature above freezing in the winter time as to not allow the fire sprinkler lines to freeze.
Electrical Systems:
1. Power: The main power is supplied via a 200A 480V, 3-phase, 4w feed from a main buss duct located in the main buildings first floor electrical room. This feed is brought to a 480V 200A panel in the main sallyport electrical room. This primary 480V power is used to power the new elevator and the 4 new vehicle area electric heaters. It also supplies a new 45KVA 120/208V transformer and 120/208V panels which supplies power to lighting, HVAC components, exhaust fans, gate openers, elevator cab lights, roll up doors, elevator sump pump, elevator auto rescue system, security system and general receptacles.
2. Emergency Power: Emergency power is taken from an existing 200A, 120/208V, 3-phase emergency panel located in the basement electrical room. A 100A feed is brought to a new 100A, 120/208V 3-phase panel located in the new electrical room. This panel provides emergency power to the sallyport lighting and security cameras.
3. Security Features: The new sallyport is equipped with an extensive array of fixed and motor operated security cameras. A vehicle sensing system (imbedded loop) operates security gates in and out of the sallyport. A scramble pad controls movement between various areas of the sallyport such as weapons vault, control room, man trap etc. There is also a signal system which alerts the prisoner-bus driver of oncoming traffic when leaving the sallyport and a system which interfaces with Metro to coordinate the Metro Rail bus’ and the prisoner bus.
Fire Alarm System:
There are fire alarm horn strobes in the Prisoner Circulation Area, Weapon Closet, Mantrap, Electrical Room and Control Closet to alert of fire hazard. The elevator shaft has a smoke and heat detector located at the top of the shaft. The elevator lobby has a smoke and heat detector and a phone receptacle for communication by firemen. The elevator has an auto rescue feature which, upon notice of an event from the main fire alarm system, will bring the elevator down to the next accessible level.
Plumbing Systems:
1. Water: Water is supplied from an existing 1” supply line located at an existing restroom adjacent to the new sallyport. This water line supplies water to a new hose bib, to be used for vehicle washing, and new trap primers.
2. Sanitary System: New sanitary waste piping from the sallyport floor drains and the elevator pit pump run to a new 8” sanitary branch line via a new sand and oil separator. The new 8” sanitary line, provided on the Civil Engineering plans connects the sallyport waste system to an existing City of Houston sanitary sewer.
3. Storm Piping; New storm piping from new roof drains on the elevator and circulation area roofs and any storm runoff collected in 3 new trench drains will be routed to an existing City of Houston storm sewer.
3.0 WORK IN OCCUPIED SPACE
The Contractor is required to work in a space that is currently occupied parking lot. It will be necessary to work around the existing vehicles. Extreme care must be taken to safeguard these vehicles from construction damage. All damage will be repaired at the contractor’s expense. When the work is completed the contractor will be responsible for any cleaning, parking lot repairs and stripping repairs.
4.0 DELIVERY AND STORAGE
Materials delivered to the site shall be inspected for damage, unloaded, and stored in the designated space provided by the Government. At the time of inspection, materials that are determined to be damaged, defective, or otherwise fail to meet specification requirements shall be removed from the job site and replaced, at no additional cost to the Government.
5.0 CLEAN-UP
Clean-up shall be performed on a continuous basis, without allowing trash or construction debris to pile up in the work site or any other location inside the building. On-site dumpsters may be used for disposal of trash and construction debris. The contractor shall leave the work site in “broom-clean” condition at the end of each work day.
If the contractor fails to comply with the requirements specified in this paragraph, the Government shall direct the cleaning contractor to clean the public area, and all associated costs will be deducted from the price of the task order.
Upon completion of the project, all trash, discarded material, or other refuse shall be collected and removed from the site and disposed of as approved by the
COTR.
6.0 SPECIAL REQUIREMENTS
All work shall conform to the contract specifications and the best practices of the trades involved in the work. All materials used in the work shall be free of defects in workmanship or finish, and shall be installed in accordance with the manufacturer’s specifications.
7.0 SUBMITTAL DATA
The contractor shall provide any necessary submittals in accordance with the Statement of work and other technical documents, prior to ordering materials.
The contractor shall submit a proposed construction schedule for all phases of work. The schedule is subject to review and approval by the Government.
8.0 PERIOD OF PERFORMANCE
The period of performance shall begin upon issuance of the Notice to Proceed (NTP) from the GSA Contracting Officer. The contractor shall order all necessary materials within 30 days upon review and approval of any required submittals, and shall begin the work within 30 Day. All work and shall be completed within 365 calendar days of issuance of the NTP.
In the event that the contractor feels the work cannot be completed by the scheduled date, a written justification shall be submitted to the Contracting Officer as soon practicable, but no later than 3 days prior to the scheduled completion date. The Contracting Officer shall make a final determination whether a time extension shall be granted.
9.0 PERFORMANCE HOURS OF PERFORMANCE
A. The contractor may be required to work during evening and weekend hours.
For the purpose of this task order, these hours are defined as 5:00 PM CST through 7:00 AM CST.
The Contractor could possibly be required to work on Government holidays.
Work may not disrupt normal business operations. The occupant of the work space may be present during the time that contractors are working in the space, and every effort shall be made by the contractor to complete the work without any undue disruption to the occupant. The Contractor shall notify the Project Manager for prior coordination if it is necessary for the occupant to temporarily vacate the work space while certain demolition or construction activity is being performed.
B. Courthouse: The facility is a Federal Courthouse that frequently conducts federal court hearings and trials. As such, the courtroom staff, attorneys, plaintiffs, and federal judges are extremely sensitive to any type of disruption of the courtroom proceedings. The Contractor shall provide the following:
1. The contractor shall coordinate all demolition and constructions activities with the courts’ liaison(s) to minimize disruptions.
2. All jack hammering, impact drilling, or other impact type activities shall be done after hours.
3. All demolition and constructions activities that generate noise above 70db shall be done after hours, including but not limited to:
a. Sub-soil lime treatment.
b. Saw-cutting.
c. Concrete pumping.
d. Bull dozer and other heavy equipment operations.
10.0 PRECONSTRUCTION CONFERENCE
The contractor shall attend and participate in a Preconstruction Conference prior to starting the work. All work shall be coordinated and scheduled with the GSA Project Manager and/or Property Manager. The construction schedule, means of access to the work site, delivery of materials, safety precautions, security clearances, cleanup practices and other topics will be discussed and agreed to at this conference.
11.0 WORKMANSHIP
Any damage caused by the contractor, to the building or any of its contents or to any tenant’s property, shall be the sole responsibility of the contractor.
Work remaining in place which is damaged or defaced by reason of work done with this contract shall be restored to its original condition at the time of the award of this task order.
QUALITY ASSURANCE: All contractor personnel must possess the appropriate technical skills, including journeyman licenses or trade certifications, as necessary to perform the work being accomplished.
12.0 SAFETY AND HEALTH
The contractor is responsible for compliance with all applicable regulations pertaining to the health and safety of building occupants and contractor personnel during the execution of the work.
The contractor shall provide all necessary safety equipment and ensure that such equipment and related safety procedures are adequate for the work being performed, and that all contractor personnel are properly trained in the use of such safety equipment.
13.0 SECURITY
The contractor shall be responsible for the security of the work-site. The contractor shall coordinate the continued use of the work space by the occupant, and shall provide adequate safety measures such as warning signs, barriers, dust protection, or other measures as required to secure the site and protect building occupants from any hazards associated with the work.
SECURITY CLEARANCE REQUIREMENTS
All contractor personnel performing working on premises at GSA owned and operated buildings are required to pass a security background check conducted by the Office of Personnel Management (OPM). Each contractor employee shall submit a contractor information worksheet (CIW) provided by the Project Manager. When prompted by OPM (via e-mail), each contractor will be required to complete fingerprinting, e-QIP (SF 85, security investigation application), OF306 (Declaration for Federal Employment), and GSA 3665 (Authorization to Obtain Credit Report) all on-line. No contractor employee will be allowed to perform work on the building premises until employee has been determined to be suitable to work on a GSA contract by the OPM.
The contractor is responsible for completing all the necessary paperwork to obtain a background investigation for contractor personnel who will work on the project. Workers without completed security investigations will not be permitted on the work site.
14.0 ADDITIONAL REQUIREMENTS
The contractor shall notify the GSA Project Manager and/or Property Manager of any conditions that prevent the satisfactory completion of the work, such as:
1. Incorrect parts or materials.
2. The presence of hazardous material.
3. Other safety or procedural issues that might prevent or delay the completion of the work.
The contractor must receive written approval from the GSA Contracting Officer, prior to continuation of the work, when any of the above conditions have been found.
15.0 INSPECTION AND ACCEPTANCE
The Government will review and comment on all deliverables within 10 working days of receipt. Acceptance or rejection of deliverables shall be made by the
Contracting Officer’s Technical Representative (COTR), giving the specific reason(s) for the rejection. The Contractor shall correct the rejected deliverable and return it on the date specified to the Contracting Officer’s Technical Representative (COTR).
Upon completion of the work, and as required during the performance of the project, the Government shall inspect and verify that the work is performed in accordance with this Statement of Work. Acceptance or rejection of all work shall be made by the Project Manager, giving the specific reason(s) for the rejection. All work found to be unacceptable shall be removed, replaced, and reinstalled, at the contractor’s expense. The Contractor shall correct the unacceptable work by the date specified and notify the Project Manager of its completion.
Final payment will not be made until all defects and omissions have been corrected and the GSA Project Manager and/or Property Manager have inspected and accepted the work and filed Form 220, Inspection Report with the Contracting Officer.
16.0 CONTRACTUAL RELATIONSHIPS
Contracting Officer - Only the Contracting Officer (CO) has the legal authority to bind the Government, approve payments, or make changes to the task order by executing written modifications.
Project Manager – Services ordered by the Contracting Officer (CO) will be coordinated through a designated Project Manger (PM). The Contractor shall coordinate all efforts through and direct all inquiries to the CO or PM. The Contractor shall not accept any direction from building occupants or from building management.
Government Oversight - Oversight, reviews and approvals performed by the Government in connection with the services provided by the Contractor will be performed from the standpoint of the regulatory responsibilities of the Government, and not from the standpoint of providing managerial, or technical reviews to support the Contractor’s efforts. The Government reviews will be general in nature. The Government will insist on high quality professional performance by the Contractor and Contractor personnel under this contract.
17.0 CLOSE OUT REQUIREMENTS
Distribute deliverables from Construction Phase
Operation and Maintenance Manuals: Two copies provided to the project manager for distribution to the property manager, one for use by building system managers (which is typically provided to O&M Contractors) and one copy for their own use and verification of O&M requirements.
Warranties: Recommend include as section in O&M Manuals.
Spare Parts: Distribute to property manager for distribution to buildings O&M Contractors. Be sure O&M Manuals note appropriately when spare parts are provided.
Training Meetings/Videos: If required, meeting or CD include with distribution of O&M Manuals.
As-Built Drawings and Specifications: Shall be provide to the Project Manager when applicable.
Abatement Documents: If applicable shall be supplied .
Other: Refer to project specifications for other deliverables relevant to this project.
GOVERNMENT CONTACTS
GSA Contract Officer Isaac Karto GSA/ Public Buildings Service Non-Prospectus Projects Branch (7PQC) 1919 Smith Street Ste. 1600 Houston, Texas 77002-8049 832-397-8464 (office) 281-228-5613 (fax) 817-505-5020 (cell) Isaac.karto@gsa.gov
GSA Property Manager Tuan Nguyen GSA/Public Buildings Service 1919 Smith Street, Ste. 1600 Houston, TX 77002-8049 832-397-8425 (office) 713-545-4942 (cell) 832-397-8466 (fax)
GSA Project Manager Larry R. Saravo GSA/Public Buildings Service 1919 Smith Street, Ste. 1600 Houston, TX 77002-8049 832-397-8459 (office) 713-817-3839 (cell) 832-397-8466 (fax)