Responses to Questions regarding Technical Proposal and Date/Location of the Pre-proposal Conference.

View the file

Other files for this federal contract opportunity

Other files attached to Lobby Reconfiguration (JCK & MFB), newest first.
File Type Posted
Amendment_01.pdf PDF
Lobby_Sign_In_Sheet.pdf PDF
JCK_RHM_RFP.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lobby Reconfiguration at the John C. Kluczynski Federal Building 230 S. Dearborn Street and Ralph H. Metcalfe Federal Building 77 W. Jackson Boulevard in Chicago, Illinois

Solicitation # GS05P16GCC7004

1) Please clarify what is required for the Technical Proposal portion of the presentation.

The way I am reading the requirements is the Past Performance Questionnaire is submitted for Factor 1:

Past Experience for Similar Projects (at least 2 projects).

Then for Factor 2: Past Performance on Similar Projects, we provide the contact information of the two (2) contact persons who are listed on the PPQs in Factor 1.

Is this correct?

You should submit past experience for a minimum of two (2) similar projects. See C201SB, Section II.D. for definition of similar. The projects should be submitted on the Past Performance Questionnaire. We will conduct Past Performance for the two (2) similar projects you submit for the Past Experience evaluation factor. The contact information should be provided on the Past Performance Questionnaire.

2) Also, regarding Factor 1: Past Experience for Similar Projects, the Solicitation reads:Offeror’s must provide at least two (2) similar projects that were completed within the last ten (10) years in which the offeror performed as a traditional General Contractor.

Need to submit two (2) similar projects that meet following (reference C201SB, Section II.D. for further detail):

o Must exceed $400,000 in construction costs o Completed in the last ten (10) years (If not complete, should be at least 90% complete) o Represent or include some aspect/component of security infrastructure and/or installation and/or programming o Components may include but are not limited to passgates, turnstiles, access cards, security screening, etc.

Thus, a minimum of 2 similar projects. What is the maximum number of projects we can submit?

No minimum listed. There is however, a 30 page limit for the Technical Proposal.

3) Please verify the date and location of the preproposal conference.

A preproposal conference is schedule for July 20, 2016 at 10:30 AM (CDT).

We will meet in Northwest Corner of the Lobby in the Ralph H. Metcalfe Federal Building, 77 W. Jackson Blvd, Chicago, Illinois