FP Concrete Spec 03 30 53_Pollinator_Plot.PDF
PDF 82 KB Posted
- Attached to
- Fort Peck Pollinator Plot Concrete Pad Federal contract opportunity
- Solicitation number
- W9128F23Q0076
About this file
This specification provides requirements for miscellaneous cast-in-place concrete work for a pollinator plot concrete slab project located at Fort Peck, Montana. The specification covers concrete mixture proportions, materials, formwork, reinforcement, placement, finishing, curing, and testing requirements. The concrete work must meet a minimum compressive strength of 4,500 psi at 28 days. Aggregates must meet ASTM C33 size 67, with a maximum water-cement ratio of 0.45. Reinforcement shall be ASTM A615 grade 60 deformed bars. Placement must comply with cold and hot weather concreting standards. Finishing requirements include broom finishing for exterior slabs. Curing, form removal, and testing standards are also provided in accordance with ACI specifications.
The related federal contract opportunity is a solicitation from the Department of the Army Corps of Engineers Engineering District Omaha for the Fort Peck Pollinator Plot Concrete Pad project. No further details are provided regarding response dates, pricing terms, or other procurement requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W9128F23Q0076_A00001.pdf | ||
| W9128F23Q0076_RFQ.pdf | ||
| W9128F23Q0076_RFQ.pdf | ||
| POLLINATOR_CONCRETE_PAD_PLANS.pdf | ||
| POLLINATOR_CONCRETE_PAD_Drawings S-101.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pollinator Plot-Concrete Slab Ft. Peck, MT
Section 03 30 53 Page 1
SECTION 03 30 53
MISCELLANEOUS CAST-IN-PLACE CONCRETE
05/14
PART 1 GENERAL
1.1 SUMMARY
This specification applies to concrete work for slab on grade construction including sidewalks, curbs, gutters, and roadway surfaces.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)
ACI 117 (2010; Errata 2011) Specifications for
Tolerances for Concrete Construction and Materials and Commentary
ACI 301 (2016) Specifications for Structural Concrete
ACI 304R (2000; R 2009) Guide for Measuring, Mixing, Transporting, and Placing Concrete
ACI 305R (2010) Guide to Hot Weather Concreting
ACI 306R (2016) Guide to Cold Weather Concreting
ACI 318 (2014; Errata 1-2 2014; Errata 3-5 2015;
Errata 6 2016) Building Code Requirements for Structural Concrete and Commentary
ACI 347 (2004; Errata 2008; Errata 2012) Guide to
Formwork for Concrete
ACI SP-66 (2004) ACI Detailing Manual
ASTM INTERNATIONAL (ASTM)
ASTM A1064/A1064M (2016b) Standard Specification for Carbon-
Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete
ASTM A615/A615M (2016) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM C1064/C1064M (2011) Standard Test Method for Temperature of Freshly Mixed Hydraulic-Cement Concrete
Section 03 30 53 Page 2
ASTM C143/C143M (2015) Standard Test Method for Slump of
Hydraulic-Cement Concrete
ASTM C150/C150M (2016; E 2016) Standard Specification for
Portland Cement
ASTM C1602/C1602M (2012) Standard Specification for Mixing
Water Used in Production of Hydraulic Cement Concrete
ASTM C172/C172M (2014a) Standard Practice for Sampling
Freshly Mixed Concrete
ASTM C231/C231M (2014) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method
ASTM C260/C260M (2010a; R 2016) Standard Specification for
Air-Entraining Admixtures for Concrete
ASTM C309 (2011) Standard Specification for Liquid
Membrane-Forming Compounds for Curing Concrete
ASTM C31/C31M (2015a; E 2016) Standard Practice for Making and Curing Concrete Test Specimens in the Field
ASTM C33/C33M (2016) Standard Specification for Concrete
Aggregates
ASTM C39/C39M (2016b) Standard Test Method for Compressive
Strength of Cylindrical Concrete Specimens
ASTM C494/C494M (2016) Standard Specification for Chemical
Admixtures for Concrete
ASTM C618 (2012a) Standard Specification for Coal Fly
Ash and Raw or Calcined Natural Pozzolan for Use in Concrete
ASTM C685/C685M (2014) Concrete Made by Volumetric Batching and Continuous Mixing
ASTM C920 (2014a) Standard Specification for
Elastomeric Joint Sealants
ASTM C94/C94M (2016a) Standard Specification for Ready-
Mixed Concrete
ASTM D1752 (2004a; R 2013) Standard Specification for
Preformed Sponge Rubber Cork and Recycled PVC Expansion
ASTM D75/D75M (2014) Standard Practice for Sampling
Section 03 30 53 Page 3
1.3 SUBMITTALS
Submit the following to the Fort Peck Project Office for Approval:
SD-03 Product Data
Air-Entraining Admixture Water-Reducing or Retarding Admixture Curing Materials Expansion Joint Filler Strips, Premolded Joint Sealants - Field Molded Sealants
SD-06 Test Reports
Concrete Mixture Proportions and Test Data Compressive Strength Testing Slump Air Content
SD-07 Certificates
Delivery Tickets
PART 2 PRODUCTS
2.1 SYSTEM DESCRIPTION
The Contractor is responsible for ensuring concrete meets contract specifications. The Government retains the option to sample and test aggregates and concrete to determine compliance with the specifications.
Provide facilities and labor as may be necessary to assist the Government in procurement of representative test samples. Obtain samples of aggregates at the point of batching in accordance with ASTM D75/D75M. Sample concrete in accordance with ASTM C172/C172M. Determine slump and air content in accordance with ASTM C143/C143M and ASTM C231/C231M, respectively, when cylinders are molded. Prepare, cure, and transport compression test specimens in accordance with ASTM C31/C31M. Test compression test specimens in accordance with ASTM C39/C39M.
2.1.1 Strength
The Government reserves the right to obtain and test specimens for acceptance. Acceptance test results are the average strengths of two 6x12 inch specimens tested at 28 days (90 days if pozzolan is used). The strength of the concrete is considered satisfactory so long as the average of the acceptance test results equal or exceed the specified compressive strength, f'c, but not more than 20 percent, and no individual acceptance test result falls below f'c by more than 500 psi.
2.1.2 Construction Tolerances
Work shall conform to all requirements of ACI 117, unless otherwise modified under this contract.
Section 03 30 53 Page 4
2.1.3 Concrete Mixture Proportions
Concrete mixture proportions are the responsibility of the Contractor.
Mixture proportions must include the dry weights of cementitious material(s); the nominal maximum size of the coarse aggregate; the specific gravities, absorptions, and saturated surface-dry weights of fine and coarse aggregates; the quantities, types, and names of admixtures; and quantity of water per yard of concrete. Provide materials included in the mixture proportions of the same type and from the same source as will be used on the project. The specified compressive strength f'c is 4,500 psi at 28 days (90 days if pozzolan is used). The maximum nominal size coarse aggregate is 3/4 inch (ASTM C33 Size 67), in accordance with ACI 304R. The air content must be between 4.5 and 7.5 percent with a slump between 2 and 5 inches. The maximum water-cementitious material ratio is 0.45. Submit the applicable test reports and mixture proportions that will produce concrete of the quality required, ten days prior to placement of concrete.
2.2 MATERIALS
Submit manufacturer's literature from suppliers which demonstrates compliance with applicable specifications for the specified materials.
2.2.1 Cementitious Materials
2.2.1.1 Portland Cement
ASTM C150/C150M, Type I or II ASTM C595, Type IL
2.2.1.2 Pozzolan
Provide pozzolan that conforms to ASTM C618, Class F, including requirements of Tables 1A and 2A.
2.2.2 Aggregates
For fine and coarse aggregates meet the quality and grading requirements of ASTM C33/C33M. Submit certificates of compliance and test reports for aggregates showing the material(s) meets the quality and grading requirements of the specifications under which it is furnished.
2.2.3 Admixtures
Provide admixtures, when required or approved, in compliance with the appropriate specification listed. Retest chemical admixtures that have been in storage at the project site, for longer than 6 months or that have been subjected to freezing, at the expense of the Contractor at the request of the Contracting Officer and will be rejected if test results are not satisfactory.
2.2.3.1 Air-Entraining Admixture
Provide air-entraining admixture that meets the requirements of ASTM C260/C260M.
Section 03 30 53 Page 5
2.2.3.2 Water-Reducing or Retarding Admixture
Provide water-reducing or retarding admixture meeting the requirements of ASTM C494/C494M, Type A, B, or D.
2.2.4 Water
Mixing and curing water in compliance with the requirements of ASTM C1602/C1602M; free of injurious amounts of oil, acid, salt, or alkali.
2.2.5 Reinforcing Steel
Provide reinforcing bars conforming to the requirements of ASTM A615/A615M, Grade 60, deformed. Provide welded steel wire reinforcement conforming to the requirements of ASTM A1064/A1064M. Detail reinforcement not indicated in accordance with ACI 301 and ACI SP-66.
2.2.6 Expansion Joint Filler Strips, Premolded
Expansion joint filler strips, premolded of sponge rubber conforming to ASTM D1752, Type I.
2.2.7 Joint Sealants - Field Molded Sealants
Conform to ASTM C920, Type M, Grade NS, Class 25, use NT for vertical joints and Type M, Grade P, Class 25, use T for horizontal joints. Provide polyethylene tape, coated paper, metal foil, or similar type bond breaker materials. The backup material needs to be compressible, nonshrink, nonreactive with the sealant, and a nonabsorptive material such as extruded butyl or polychloroprene foam rubber. Immediately prior to installation of field-molded sealants, clean the joint of all debris and further cleaned using water, chemical solvents, or other means as recommended by the sealant manufacturer or directed.
2.2.8 Formwork
Design and engineer the formwork as well as its construction in accordance with ACI 301 Section 2 and 5 and ACI 347. Fabricate of wood, steel, or other approved material.
2.2.9 Form Coatings
Provide form coating in accordance with ACI 301.
2.2.10 Curing Materials
Provide curing materials in accordance with ACI 301, Section 5. Provide curing compound conforming to ASTM C309. Follow manufactures instructions for placing curing compound.
2.3 READY-MIX CONCRETE
Provide ready-mix concrete with mix design data conforming to ACI 301 Part
2. Submit delivery tickets in accordance with ASTM C94/C94M for each ready-mix concrete delivery.
Section 03 30 53 Page 6
PART 3 EXECUTION
3.1 PREPARATION
Prepare construction joints to expose coarse aggregate. The surface must be clean, damp, and free of laitance. Construct ramps and walkways, as necessary, to allow safe and expeditious access for concrete and workmen.
Remove snow, ice, standing or flowing water, loose particles, debris, and foreign matter. Satisfactorily compact earth foundations. Make spare vibrators available. Placement cannot begin until the entire preparation has been accepted by the Government.
3.1.1 Embedded Items
Secure reinforcement in place after joints, anchors, and other embedded items have been positioned. Arrange internal ties so that when the forms are removed the metal part of the tie is not less than 2 inches from concrete surfaces permanently exposed to view or exposed to water on the finished structures. Prepare embedded items so they are be free of oil and other foreign matters such as loose coatings or rust, paint, and scale. The embedding of wood in concrete is permitted only when specifically authorized or directed. Provide all equipment needed to place, consolidate, protect, and cure the concrete at the placement site and in good operating condition.
3.1.2 Formwork Installation
Forms must be properly aligned, adequately supported, and mortar-tight.
Provide smooth form surfaces, free from irregularities, dents, sags, or holes when used for permanently exposed faces. Chamfer all exposed joints and edges, unless otherwise indicated.
3.1.3 Production of Concrete
3.1.3.1 Ready-Mixed Concrete
Provide ready-mixed concrete conforming to ASTM C94/C94M except as otherwise specified.
3.1.3.2 Concrete Made by Volumetric Batching and Continuous Mixing
Conform to ASTM C685/C685M.
3.2 CONVEYING AND PLACING CONCRETE
Convey and place concrete in accordance with ACI 301, Section 5.
3.2.1 Cold-Weather Requirements
Place concrete in cold weather in accordance with ACI 306R
3.2.2 Hot-Weather Requirements
Place concrete in hot weather in accordance with ACI 305R
3.3 FINISHING
Section 03 30 53 Page 7
3.3.1 Temperature Requirement
Do not finish or repair concrete when either the concrete or the ambient temperature is below 50 degrees F.
3.3.2 Finishing Formed Surfaces
Remove all fins and loose materials, and surface defects including filling of tie holes. Repair all honeycomb areas and other defects. Remove all unsound concrete from areas to be repaired. Ream or chip surface defects greater than 1/2 inch in diameter and holes left by removal of tie rods in all surfaces not to receive additional concrete and fill with dry-pack mortar. Brush-coat the prepared area with an approved epoxy resin or latex bonding compound or with a neat cement grout after dampening and filling with mortar or concrete. Use a blend of portland cement and white cement in mortar or concrete for repairs to all surfaces permanently exposed to view shall be so that the final color when cured is the same as adjacent concrete.
3.3.3 Finishing Unformed Surfaces
Finish unformed surfaces in accordance with ACI 301, Section 5. Unless otherwise specified on the drawings, surfaces shall be finished in accordance with the table below.
FINISH LOCATION
Broom All exterior slab on grade
3.3.3.1 Expansion and Contraction Joints
Make expansion and contraction joints in accordance with the details shown or as otherwise specified. Provide 1/2 inch thick transverse expansion joints where new work abuts an existing concrete. Provide expansion joints at a maximum spacing of 30 feet on center in sidewalks, unless otherwise indicated. Provide contraction joints at a maximum spacing of 6 linear feet in sidewalks and at a maximum spacing of 10 feet in slabs, unless otherwise indicated. Cut contraction joints at a minimum of 1/4 the slab thickness after the surface has been finished.
3.4 CURING AND PROTECTION
Cure and protect in accordance with ACI 301, Section 5.
3.5 FORM WORK
Provide form work in accordance with ACI 301, Section 2 and Section 5.
3.5.1 Removal of Forms
Remove forms in accordance with ACI 301, Section 2.
Section 03 30 53 Page 8
3.6 STEEL REINFORCING
Reinforcement must be free from loose, flaky rust and scale, and free from oil, grease, or other coating which might destroy or reduce the reinforcement's bond with the concrete.
3.6.1 Shrinkage and Temperature Reinforcement
Steel reinforcement shall satisfy the requirements of ACI 318 and ACI SP-66.
Unless otherwise specified, space the bars no farther apart than five times the slab thickness but no more than 18 inches. Provide a minimum ratio of reinforcement area to gross concrete area of 0.0020. Minimum clear cover shall be 1 1/2" on all faces.
3.6.2 Splicing
Perform splices in accordance with ACI 318 and ACI SP-66.
3.6.3 Supports
Secure reinforcement in place by the use of metal or plastic supports, spacers, or ties. Sufficient supports shall be used to prevent reinforcement from shifting during placement or excessive deflection from workers stepping or walking on the reinforcement.
3.7 EMBEDDED ITEMS
Before placing concrete, take care to determine that all embedded items are firmly and securely fastened in place. Provide embedded items free of oil and other foreign matter, such as loose coatings of rust, paint and scale.
Embedding of wood in concrete is permitted only when specifically authorized or directed.
3.8 TESTING AND INSPECTING
Report the results of all tests and inspections conducted at the project site informally at the end of each shift.
3.8.1 Field Testing Technicians
The individuals who sample and test concrete must have demonstrated a knowledge and ability to perform the necessary test procedures equivalent to the ACI minimum guidelines for certification of Concrete Field Testing Technicians, Grade I.
3.8.2 Preparations for Placing
Inspect foundation or construction joints, forms, and embedded items in sufficient time prior to each concrete placement to certify that it is ready to receive concrete.
3.8.3 Sampling and Testing
The Government shall perform the following tests at the start of the first placement. The Government reserves the right to sample and test concrete for conformance at any time to verify compliance with the specifications.
Section 03 30 53 Page 9
a. Sample fresh concrete for testing in accordance with ASTM C172/C172M.
b. The Government reserves the right to conform test specimens to ASTM C31/C31M, and perform compressive strength testing conforming to ASTM C39/C31M.
c. Test slump at the site of discharge for each design mix in accordance with ASTM C143/C143M.
d. Test air content at the final point of discharge for air-entrained concrete in accordance with ASTM C231/C231M.
e. Determine temperature of concrete at time of placement in accordance with ASTM C1064/C1064M.
3.8.4 Action Required
3.8.4.1 Placing
Do not begin placement until the availability of an adequate number of acceptable vibrators, which are in working order and have competent operators, has been verified. Discontinue placing if any lift is inadequately consolidated.
3.8.4.2 Air Content
Whenever an air content test result is outside the specification limits, adjust the dosage of the air-entrainment admixture prior to delivery of concrete to forms.
3.8.4.3 Slump
Whenever a slump test result is outside the specification limits, adjust the batch weights of water and fine aggregate prior to delivery of concrete to the forms. Make the adjustments so that the water-cementitious material ratio does not exceed that specified in the submitted concrete mixture proportion and the required concrete strength is still met.
-- End of Section --
| PART 1 GENERAL |
| 1.1 SUMMARY |
| 1.2 REFERENCES |
| 1.3 SUBMITTALS |
| PART 2 PRODUCTS |
| 2.1 SYSTEM DESCRIPTION |
| 2.1.1 Strength |
| 2.1.2 Construction Tolerances |
| 2.1.3 Concrete Mixture Proportions |
| 2.2 MATERIALS |
| 2.2.1 Cementitious Materials |
| 2.2.1.1 Portland Cement |
| 2.2.1.2 Pozzolan |
| 2.2.2 Aggregates |
| 2.2.3 Admixtures |
| 2.2.3.1 Air-Entraining Admixture |
| 2.2.3.2 Water-Reducing or Retarding Admixture |
| 2.2.4 Water |
| 2.2.5 Reinforcing Steel |
| 2.2.6 Expansion Joint Filler Strips, Premolded |
| 2.2.7 Joint Sealants - Field Molded Sealants |
| 2.2.8 Formwork |
| 2.2.9 Form Coatings |
| 2.2.10 Curing Materials |
2.3 READY-MIX CONCRETE
| PART 3 EXECUTION |
| 3.1 PREPARATION |
| 3.1.1 Embedded Items |
| 3.1.2 Formwork Installation |
| 3.1.3 Production of Concrete |
| 3.1.3.1 Ready-Mixed Concrete |
| 3.1.3.2 Concrete Made by Volumetric Batching and Continuous Mixing |
| 3.2 CONVEYING AND PLACING CONCRETE |
| 3.2.1 Cold-Weather Requirements |
| 3.2.2 Hot-Weather Requirements |
| 3.3 FINISHING |
| 3.3.1 Temperature Requirement |
| 3.3.2 Finishing Formed Surfaces |
| 3.3.3 Finishing Unformed Surfaces |
| 3.3.3.1 Expansion and Contraction Joints |
| 3.4 CURING AND PROTECTION |
| 3.5 FORM WORK |
| 3.5.1 Removal of Forms |
| 3.6 STEEL REINFORCING |
| 3.6.1 Shrinkage and Temperature Reinforcement |
| 3.6.2 Splicing |
| 3.6.3 Supports |
| 3.7 EMBEDDED ITEMS |
| 3.8 TESTING AND INSPECTING |
| 3.8.1 Field Testing Technicians |
| 3.8.2 Preparations for Placing |
| 3.8.3 Sampling and Testing |
| 3.8.4 Action Required |
| 3.8.4.1 Placing |
| 3.8.4.2 Air Content |
| 3.8.4.3 Slump |