FA9101-16-B-0006.doc.pdf
PDF 2 MB Posted
- Attached to
- REPLACE LIGHTING WOODS DAM Federal contract opportunity
- Solicitation number
- FA9101-16-B-0006
About this file
FA9101-16-B-0006 Solicitation with attachments.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA9101-16-B-0006-0002.pdf | ||
| FA9101-16-B-0006-0001_Q_and_As.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
FA9101-16-B-0006
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
13 JUN 2016
PAGE OF PAGES
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUESTION/PURCHASE REQUEST NO.
6. PROJECT NO.
7. ISSUED BY AFTC PZI ARNOLD CODE FA9101 8. ADDRESS OFFER TO
AFTC/PZI (ARNOLD)
100 KINDEL DRIVE, SUITE A-345
ARNOLD AFB, TN 37389-1332
malisa.ford@us.af.com
See Block 7
9. FOR INFORMATION
CALL:
A. NAME
MALISA C. FORD
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
9314545139 X
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder”.
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no, date):
Requirement includes, but is not limited to, providing all materials, equipment, labor and tools to replace the interior and exterior light fixtures and electrical panels in the Woods Dam located at Arnold AFB, TN. Performance shall be in accordance with contract terms and conditions, to include AEDC Project Specification No. 13776-16-002, dated 05 February 2016 and associated drawings.
11. The Contractor shall begin performance within _10__ calendar days and complete it within __180__ calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See _ _.)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES”, indicate within how many calendar days after award in Item 12B.)
YES NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. This Acquisition is 100% Set-Aside for Small Business.
b. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
c. Bids must be firm for 60-Days from bid due date. Bids which are not firm for 60-Days will be rejected and deemed as nonresponsive and will not be considered for award.
d. The estimated total magnitude of this work is between $100,000- $250,000.
e. Sealed offers in original and zero (0) copies to perform the work required are due at the place specified in Item 7 by 2:00 PM CST, 15 July 2016. This is a sealed bid solicitation; offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
f. A 20% bid bond or other acceptable bid surety is required.
g. An organized site visit is scheduled for Tuesday, 21 June 2016, beginning at 10 AM CST. See provision FAR 52.236-27 Site Visit (Construction) in Section L of the solicitation for requirements of the site visit.
NSN 7540-01-155-3212
ConWrite Version 6.14.7 Created 13 Jun 2016 8:36 AM
1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within __ __ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation – give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER
(Type or print)
20B. SIGNATURE 20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
See Section G
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )
26. ADMINISTERED BY
CODE
27. PAYMENT WILL BE MADE BY
EFT:T
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return _______ copies to issuing office.)
Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award,
(b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation, is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN
(Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print)
ROBERT A. GREENE
30B. SIGNATURE 30C. DATE 31B. UNITED STATES OF AMERICA
BY
31C. AWARD DATE
STANDARD FORM 1442 PAGE 2 (REV. 4-85)
PART I - THE SCHEDULE
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
SECTION B FA9101-16-B-0006
Qty Unit Price ITEM SUPPLIES OR SERVICES Purch Unit Total Item Amount
Replace Lighting Woods Dam
0001 1 __________ Lot __________ Noun: Replace Lighting Woods Dam
PSC: Z2KA
NSN: N - Not Applicable Contract type: J - FIRM FIXED PRICE Inspection: DESTINATION Acceptance: DESTINATION
FOB: DESTINATION
Descriptive Data:
Contractor shall provide all materials, equipment, labor and tools to replace the interior and exterior light fixtures and electrical panels in the Woods Dam located at Arnold AFB, TN. Performance shall be in accordance with contract terms and conditions, to include AEDC Project Specification No. 13776-16-002, dated 05 February 2016 and associated drawings.
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
SECTION B FA9101-16-B-0006
NO CLAUSES OR PROVISIONS IN THIS SECTION
SECTION C - DESCRIPTION/SPECS./WORK STATEMENT
SECTION C FA9101-16-B-0006
SECTION D - PACKAGING AND MARKING
SECTION D FA9101-16-B-0006
SECTION E - INSPECTION AND ACCEPTANCE
SECTION E FA9101-16-B-0006
NOTICE: The following contract clauses pertinent to this section are hereby incorporated by reference:
FEDERAL ACQUISITION REGULATION CONTRACT CLAUSES
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
52.246-13 INSPECTION -- DISMANTLING, DEMOLITION, OR REMOVAL OF IMPROVEMENTS
(AUG 1996)
SECTION F - DELIVERIES OR PERFORMANCE
SECTION F FA9101-16-B-0006
SHIP MARK TRANS
ITEM SUPPLIES SCHEDULE DATA QTY TO FOR PRI DATE
0001 1 F1EESF FA9101 ASREQ
Noun: Replace Lighting Woods Dam Descriptive Data:
Mark For: FA9101-16-B-0006 Req No.: 527280 A.F. Project Manager: Mr. Nick Hibdon
SECTION G - CONTRACT ADMINISTRATION DATA
SECTION G FA9101-16-B-0006
NOTICE: The following contract clauses pertinent to this section are hereby incorporated in full text:
DEFENSE FAR SUPP CONTRACT CLAUSES IN FULL TEXT
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
(a) Definitions. As used in this clause-
“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.
“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall—
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web- Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/
(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
Construction Invocie.
Note: If a “Combo” document type is identified but not supportable by the Contractor’s business systems, an “Invoice” (stand-alone) and “Receiving Report” (stand-alone) document type may be used instead.)
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
Inspection: F1EESF Acceptance: FA9101
SECTION G - CONTRACT ADMINISTRATION DATA
SECTION G FA9101-16-B-0006
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table* Field Name in WAWF Data to be entered in WAWF
Pay Official DoDAAC F03000 Issue By DoDAAC FA9101 Admin DoDAAC FA9101 Inspect By DoDAAC F1EESF Ship To Code F1EESF Ship From Code Inspection: F1EESF Acceptance: FA9101 Mark For Code FA9101 Service Approver (DoDAAC) N/A Service Acceptor (DoDAAC) N/A Accept at Other DoDAAC N/A LPO DoDAAC N/A DCAA Auditor DoDAAC N/A Other DoDAAC(s) N/A
(*Contracting Officer: Insert applicable DoDAAC information or “See schedule” if multiple ship to/acceptance locations apply, or “Not applicable.”)
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the e-mail address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.
malisa.ford@us.af.mil and Robert.Greene.17@us.af.mil
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.
malisa.ford@us.af.mil
(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.
SECTION H - SPECIAL CONTRACT REQUIREMENTS
SECTION H FA9101-16-B-0006
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
SECTION I FA9101-16-B-0006
Contract Clauses in this section are from the FAR, Defense FAR Sup, Air Force FAR Sup, and the Air Force
Materiel Command FAR Sup, and are current through the following updates:
Database_Version: 6.14.x.3800; Issued: 4/8/2016; FAR: FAC 2005-87; DFAR: DPN20160325; DL.: DL 98-021;
Class Deviations: CD 2016-O0006; AFFAR: 2002 Edition; AFAC: AFAC 2015-1001; IPN: 98-
I. NOTICE: The following contract clauses pertinent to this section are hereby incorporated by reference:
A. FEDERAL ACQUISITION REGULATION CONTRACT CLAUSES
52.202-01 DEFINITIONS (NOV 2013)
52.203-03 GRATUITIES (APR 1984)
52.203-05 COVENANT AGAINST CONTINGENT FEES (MAY 2014)
52.203-06 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (SEP 2006)
52.203-07 ANTI-KICKBACK PROCEDURES (MAY 2014)
52.203-08 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR
IMPROPER ACTIVITY (MAY 2014)
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS
(OCT 2010)
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO
INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS (APR 2014)
52.204-04 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT
PAPER (MAY 2011)
52.204-09 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT
AWARDS (OCT 2015)
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (JUL 2013)
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS
(DEC 2014)
52.209-06 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH
CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT
(OCT 2015)
52.209-09 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY
MATTERS (JUL 2013)
52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS
(NOV 2015)
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
(a) Number of calendar days is '10'
(c) Number of days or calendar date is '180'
52.214-29 ORDER OF PRECEDENCE -- SEALED BIDDING (JAN 1986)
52.219-06 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2011)
52.219-14 LIMITATIONS ON SUBCONTRACTING (NOV 2011)
52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)
52.222-01 NOTICE TO THE GOVERNMENT OF LABOR DISPUTES (FEB 1997)
52.222-03 CONVICT LABOR (JUN 2003)
52.222-06 CONSTRUCTION WAGE RATE REQUIREMENTS (MAY 2014)
52.222-07 WITHHOLDING OF FUNDS (MAY 2014)
52.222-08 PAYROLLS AND BASIC RECORDS (MAY 2014)
52.222-09 APPRENTICES AND TRAINEES (JUL 2005)
52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)
52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)
52.222-12 CONTRACT TERMINATION -- DEBARMENT (MAY 2014)
52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND
RELATED REGULATIONS (MAY 2014)
52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)
52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014)
52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015)
52.222-26 EQUAL OPPORTUNITY (APR 2015)
52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (APR
2015)
52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS
ACT (DEC 2010)
52.222-50 COMBATING TRAFFICKING IN PERSONS (MAR 2015)
52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (OCT 2015)
52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 (DEC 2015)
52.222-99 ESTABLISHING A MINIMUM WAGE FOR CONTRACTORS (DEVIATION) (JUN 2014)
52.223-02 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND
CONSTRUCTION CONTRACTS (SEP 2013)
52.223-03 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (JAN
1997) Para (b), Material Identification No: 'Unk'
52.223-05 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)
52.223-06 DRUG-FREE WORKPLACE (MAY 2001)
52.223-15 ENERGY EFFICIENCY IN ENERGY-CONSUMING PRODUCTS (DEC 2007)
52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND
CONSTRUCTION CONTRACTS (MAY 2008)
52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE
DRIVING (AUG 2011)
52.225-09 BUY AMERICAN - CONSTRUCTION MATERIALS (MAY 2014)
Para (b)(2). Insert excepted materials or "none". 'None'
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008)
52.227-01 AUTHORIZATION AND CONSENT (DEC 2007)
52.227-02 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT
INFRINGEMENT (DEC 2007)
52.227-04 PATENT INDEMNITY -- CONSTRUCTION CONTRACTS (DEC 2007)
52.228-01 BID GUARANTEE (SEP 1996)
Para (c). Percent is '20 %' Para (c). Dollar amount is 'N/A'
52.228-02 ADDITIONAL BOND SECURITY (OCT 1997)
52.228-05 INSURANCE -- WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
52.228-11 PLEDGES OF ASSETS (JAN 2012)
52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (MAY 2014)
52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)
52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION (OCT 2010)
52.229-03 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013)
52.232-05 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)
52.232-17 INTEREST (MAY 2014)
52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014)
52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (MAY 2014)
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER - SYSTEM FOR AWARD
MANAGEMENT (JUL 2013)
52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS
SUBCONTRACTORS (DEC 2013)
52.233-01 DISPUTES (MAY 2014)
52.233-03 PROTEST AFTER AWARD (AUG 1996)
52.233-04 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)
52.236-02 DIFFERING SITE CONDITIONS (APR 1984)
52.236-03 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)
52.236-04 PHYSICAL DATA (APR 1984)
Description of investigational methods used: 'surveys' Summary of weather records and warnings '
(1) The location of the work is subject to atmospheric temperature ranging from minus 10 degrees F to plus 105 degrees F. The average annual rainfall is about 54 inches and the average annual snowfall is about 4 inches.
(2) Time Extensions for Unusually Severe Weather
a. Based on data from the National Oceanic and Atmospheric Agency
(NOAA), the following number of adverse weather days can be anticipated at Arnold AFB, TN in the month indicated.
JAN 16 MAY 8 SEP 7
FEB 13 JUN 6 OCT 5
MAR 9 JUL 8 NOV 7
APR 7 AUG 5 DEC 13
b. From receipt of Notice to Proceed throughout the contract performance period, the Government Project Officer will record daily the actual number of adverse weather days which prevent work for at least 50 percent of the contractor's workday.
c. Only after the cumulative number of "adverse weather days" as defined in b., above, has reached the total calculated from the monthly figures listed in a., above, or the proportionate number for partial calendar months in the performance period, will the Contracting Officer consider a time extension in accordance with the clause entitled "Default (Fixed-Price Construction)." A time extension will be granted on a day-for-day basis if the Contracting Officer determines that additional adverse weather days prevent work for at least 50 percent of the contractor's workday and delay work critical to the timely completion of the contract.
d. The contractor's schedule must reflect the delays associated with the anticipated adverse weather days listed in a., above. The Contracting Officer will grant no time extensions for adverse weather days within the cumulative total of the monthly numbers listed.'
Summary of transportation facilities providing access from the site ' Transportation Facilities to AEDC Fenced Area
(1) Highways. U.S. Highway 41A is a paved road passing through
Tullahoma, Tennessee. U.S. Highway 41 and Interstate 24 are paved roads passing through Manchester, Tennessee. State Highway 55 is a paved road connecting U.S.
Highway 41 and 41A at Manchester and Tullahoma, respectively.
Access to the AEDC area can be gained from State Highway 55 near Tullahoma via new paved highway intersecting U.S. Highway 41, 5.5 miles southwest of Manchester and 3.8 miles from the area entrance, and Interstate 24, 3.5 miles southeast of Manchester and
2.5 miles from the area entrance. Concrete pavements have been constructed within the AEDC area and may be used subject to the restrictions set forth herein. Access to the sites of work from the paved areas and other routes shall be provided and maintained by and at the expense of the Contractor. The route for equipment which is not permitted to operate on the concrete pavement shall be as approved by the Contracting Officer. No construction truck or trailer vehicles shall be operated upon pavements of the AEDC area except within the following load limitations.
(d) Travel Within the AEDC Area
(1) Streets and Roadways. Streets have been constructed within the
AEDC area and may only be used subject to the restrictions set forth herein.
a. A "Special Permit" is required for the movement of all construction equipment, unless hereinafter provided otherwise, which is to be moved over streets or over areas containing underground ducting, piping, or overhead utilities. Application for the Special permit to move heavy equipment will be submitted to the Contracting Officer. Application for such movements will be made sufficiently in advance of the time needed to avoid delays in movement. Only wheel or tire vehicles which fall under the following maximum allowable load limitations may operate without permit upon AEDC streets:
DESIGN AXLE AND WHEEL LOADS ON STREETS
Maximum Allowable Loads in Pounds
*Truck or Trailer **Large Tire Equipment Streets Per Axle Per Wheel Per Axle Per Wheel
Avenues A, B, and C and 2nd Street 18,000 9,000 25,200 12,600 Avenue E 24,000 12,000 33,600 16,800 1st, 4th, and 5th Streets 24,000 12,000 36,600 16,800 3rd Street between Avenues B and C 18,000 9,000 25,200 12,600 3rd Street between C and E 24,000 12,000 33,600 16,000
*Axles must be spaced greater than 40" apart.
**Equipment with tires wider than 16", such as large earth moving equipment.
These restrictions permit the operation of fully loaded DW-10's with No. 10 scrapers only on pavements with a maximum allowable load of 33,600 pounds. The axle load for large tire equipment shall be based upon the manufacturer's specified weights for fully loaded equipment.
b. If any equipment exceeds the above load limitations, or any track vehicles are used, the pavement must be protected with earth or fiber at the expense of the Contractor. Compliance with the above requirements does not preclude the Contractor's liability for any damage which results from his travel over AEDC streets.
(2) Other Routes. Routes for use of equipment which is not permitted on AEDC streets shall be as shown on the drawings, or as approved by the Contracting Officer. Access to the sites of work from the paved areas, and other routes, shall be provided and maintained by and at the expense of the Contractor.
(3) Traffic Regulations. The Contractor shall be cognizant of and comply with all AEDC traffic regulations as published and enforced on the AEDC Installation.'
Other pertinent information: 'None'
52.236-05 MATERIAL AND WORKMANSHIP (APR 1984)
52.236-06 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)
52.236-07 PERMITS AND RESPONSIBILITIES (NOV 1991)
52.236-08 OTHER CONTRACTS (APR 1984)
52.236-09 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,
AND IMPROVEMENTS (APR 1984)
52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984)
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)
52.236-12 CLEANING UP (APR 1984)
52.236-13 ACCIDENT PREVENTION (NOV 1991)
52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
52.236-17 LAYOUT OF WORK (APR 1984)
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)
52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)
52.242-13 BANKRUPTCY (JUL 1995)
52.242-14 SUSPENSION OF WORK (APR 1984)
52.243-04 CHANGES (JUN 2007)
52.243-06 CHANGE ORDER ACCOUNTING (APR 1984)
52.244-06 SUBCONTRACTS FOR COMMERCIAL ITEMS (FEB 2016)
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)
52.249-02 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR
2012)
52.249-02 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR
2012) - ALTERNATE I (SEP 1996)
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
52.253-01 COMPUTER GENERATED FORMS (JAN 1991)
B. DEFENSE FEDERAL ACQUISITION REGULATION SUPPLEMENT CONTRACT CLAUSES
252.203-7000 REQUIREMENTS RELATING TO COMPENSATION OF FORMER DOD OFFICIALS
(SEP 2011)
252.203-7001 PROHIBITION ON PERSONS CONVICTED OF FRAUD OR OTHER DEFENSE-
CONTRACT-RELATED FELONIES (DEC 2008)
252.203-7002 REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS (SEP
2013)
252.204-7000 DISCLOSURE OF INFORMATION (AUG 2013)
252.204-7003 CONTROL OF GOVERNMENT PERSONNEL WORK PRODUCT (APR 1992)
252.223-7004 DRUG-FREE WORK FORCE (SEP 1988)
252.223-7006 PROHIBITION ON STORAGE, TREATMENT, AND DISPOSAL OF TOXIC OR
HAZARDOUS MATERIALS - BASIC (SEP 2014)
252.223-7008 PROHIBITION OF HEXAVALENT CHROMIUM (JUN 2013)
252.227-7033 RIGHTS IN SHOP DRAWINGS (APR 1966)
252.232-7010 LEVIES ON CONTRACT PAYMENTS (DEC 2006)
252.236-7000 MODIFICATION PROPOSALS--PRICE BREAKDOWN (DEC 1991)
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
Para (e). Identify drawings. 'See Section J Attachments'
252.242-7006 ACCOUNTING SYSTEM ADMINISTRATION (FEB 2012)
252.243-7001 PRICING OF CONTRACT MODIFICATIONS (DEC 1991)
252.246-7003 NOTIFICATION OF POTENTIAL SAFETY ISSUES (JUN 2013)
252.247-7023 TRANSPORTATION OF SUPPLIES BY SEA - BASIC (APR 2014)
C. AIR FORCE FEDERAL ACQUISITION REGULATION SUPPLEMENT CONTRACT CLAUSES
5352.201-9101 OMBUDSMAN (NOV 2015)
Para (c). Ombudsmen names, addresses, phone numbers, fax, and email addresses.
'Air Force Test Center Vice Commander, 1 South Rosamond Blvd., Edwards AFB, CA, 93524-3784, Phone Number (661) 277-7593'
5352.223-9000 ELIMINATION OF USE OF CLASS I OZONE DEPLETING SUBSTANCES (ODS) (NOV 2012)
5352.242-9000 CONTRACTOR ACCESS TO AIR FORCE INSTALLATIONS (NOV 2012)
Para (b), Any additional requirements to comply with local security procedures 'None' Para (d). Additional requirements. 'AEDC Security Procedures'
II. NOTICE: The following contract clauses pertinent to this section are hereby incorporated in full text:
FEDERAL ACQUISITION REGULATION CONTRACT CLAUSES IN FULL TEXT
52.252-02 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): http://farsite.hill.af.mil/
52.252-06 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter
1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 2) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
PART III - LIST OF DOCUMENTS, EXHIBITS & ATTACHMENTS
SECTION J - LIST OF ATTACHMENTS
SECTION J FA9101-16-B-0006
DOCUMENT PGS DATE TITLE
ATTACHMENT 1 100 05 FEB 2016 SPECIFICATION 13776-16-002
ATTACHMENT 2 5 05 FEB 2016 DRAWINGS TST35531 G1, E1-E4
ATTACHMENT 3 5 11 MAR 2016 WAGE DETERMINATION TN160041 TN41
13776-16-002 NOT SENSITIVE
ANZY119025
SPEC NO. 13776-16-002
5 February 2016
CONSTRUCTION SPECIFICATION
TO
REPLACE LIGHTING WOODS DAM
ARNOLD ENGINEERING DEVELOPMENT CENTER (AEDC)
ARNOLD AIR FORCE BASE, TENNESSEE 37389-9998
NOT SENSITIVE
IRA-2324
ANZY119025 INDEX-1
INDEX
DIVISION 01 GENERAL REQUIREMENTS
01 10 00 Summary 01 33 00 Submittal Procedures 01 45 00 Regulatory Requirements 01 74 19 Construction Waste Management and Disposal
DIVISION 02 EXISTING CONDITIONS
02 08 00 Asbestos Removal 02 08 50 Lead and Heavy Metal Removal 02 41 26 Selective Electrical Demolition
DIVISIONS 03 - 25 NOT USED
DIVISION 26 ELECTRICAL
26 05 03 Equipment Wiring Connections 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 29 Hangers and Supports for Electrical Equipment 26 05 33 Raceways and Boxes for Electrical Equipment 26 05 53 Identification for Electrical Systems 26 24 16 Panelboards 26 27 26 Wiring Devices 26 51 00 Interior Lighting 26 56 00 Exterior Lighting
DIVISIONS 27 - 49 NOT USED
ANZY119025 01 10 00-1
SECTION 01 10 00
SUMMARY
PART 1 GENERAL
1. Synopsis: The work consists of providing all materials, equipment, labor, and tools to replace interior and exterior light fixtures and electrical lighting panels in the Woods Dam at Arnold Air Force Base, Tennessee. The extent of the work is contained in the drawings and specifications. The Contractor shall be responsible for procurement of all material, equipment, labor, transportation, storage, and disposal. Lead paint and asbestos contaminated material will be encountered when replacing panelboards and lighting branch circuits as indicated on the drawings. Contractor is responsible for all asbestos abatement. The work shall be coordinated in a scheduled manner to allow for minimum down time. The extent of the work includes, but is not limited to the following:
A. Remove incandescent light fixtures, electrical panels and light switches.
B. Provide new Light-Emitting Diode (LED), to include interior and outdoor industrial area fixtures.
C. Provide new conduit and wiring as indicated.
D. Provide new 120/208V lighting panels.
E. Provide new light switches as indicated.
F. Remove asbestos and lead: Treat and dispose of in accordance with Sections 02 08 00 and 02 08 50.
1.2 DEFINITIONS
A. Certain terms used in the contract documents are defined below.
Definitions and explanations contained in this section are not complete, but are general for the work to the extent that they are not stated more explicitly in another element of the contract documents.
1. Furnish. The term "furnish" means to supply and deliver to the project site, ready for unloading, unpacking, assembly, installation, and similar operations.
2. Install. The term "install" describes operations at the project site, including the actual unloading, unpacking, assembly, erection, placing, anchoring, applying, working to dimensions, finishing, curing, protecting, cleaning, and similar operations.
3. Provide. The term "provide" means "provide complete in place";
that is, "furnish and install.”
4. Indicated. Where "as indicated" or words of similar import are used, it shall be understood that the reference is made to the drawings accompanying this contract unless stated otherwise.
ANZY119025 01 10 00-2
5. Postconsumer material (FAR 52.223-9): a material or finished product that has served its intended use and has been discarded for disposal or recover, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered materials”.
6. Recovered material (FAR 2.101): waste materials and by-products recovered or diverted from solid waste. The term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
7. Biobased product (FAR 2.101): a product determined by the U.S.
Department of Agriculture (USDA) to be a commercial or industrial product (other than food or feed) that is composed, in whole or in significant part, of biological products, including renewable domestic agricultural materials (including plant, animal, and marine materials) or forestry materials.
8. USDA-designated item (FAR 233.401): a generic grouping of products that are or can be made with Biobased materials (1) that is listed by USDA in a procurement guideline (7 CFR 2902, Subpart B); and (2) for which USDA has provided purchasing recommendations.
1.3 CODES AND STANDARDS
A. AEDC Safety, Health, and Environmental (SHE) Standards latest version, available at http://www.aerospacetestingalliance.com/en/vendors/-site-work/safety-standards
1. A6 with Supplement User and Subcontractor Safety
(Mandatory Documents/Submittals).
2. A9 Hazard Communications.
3. A10 Job Safety Analysis.
4. B1 Master Work Permit.
5. B2 Lockout/Tagout (LOTO).
6. B3 Control of Hazardous Areas Using
Safety Signs, Tags, and Barricades.
7. B5 Confined Spaces.
8. B6 Low Voltage Electrical Safety Related
Work Practices.
9. D3 Identification of Piping Systems.
10. D6 Aerial Work Platforms.
11. D8 Portable Power Tools.
12. D9 Fixed and Portable Ladders.
13. D10 Scaffolds.
14. E7 Asbestos.
15. E17 Oil and Hazardous Substances Spill
Response.
Fixed and Portable Ladder.
16. E18 Managing Wastes Containing Chemical or Petroleum Products.
ANZY119025 01 10 00-3
17. E19 Lead and Heavy Metals.
18. F2 Personal Protection Equipment (PPE).
19. F6 Fall Protection.
B. Air Force Federal Acquisition Regulation:
1. AFFARS 2.101 Definitions of Words and Terms.
2. AFFARS 233.401 Use of Recovered Materials Definition.
3. AFFARS 52.223-9 Estimate of Percentage of Recovered
Material Content for EPA-Designated Items.
4. AFFARS 5352.223-9000 Elimination of Use of Class I Ozone Depleting Substances (ODS).
C. Code of Federal Regulations, latest version:
1. 7 CFR 2902 Subpart B Guidelines for Designating Biobased
Products for Federal Procurement, Designated Items.
2. 29 CFR 1926.1101 Asbestos.
3. 40 CFR 261 Identification and Listing of Hazardous
Waste.
4. 40 CFR 370 EPA Hazardous Chemical Reporting and Community Right to Know Requirement.
D. U. S. Army Corp of Engineers:
1. CoE EM 385-1-1 Safety and Health Requirements
Manual, 2008.
1.4 JOB CONDITIONS
A. Plan and execute this project in a manner to minimize downtime.
Schedule all work in advance with the Government Representative.
B. All work shall be accomplished between 1 Oct and 30 March.
C. Contractor shall submit a contract progress schedule showing dates and duration of each milestone with proposed duration and completion dates.
D. Furnish new components and devices, complete, with all necessary materials for installation to meet this objective.
E. Do not interrupt existing utilities or commence power outages without signed authorization from the Government Representative. Each utility outage request shall be submitted by the Contractor to the Government Representative for Government approval. Submit requests for each utility outage request for Government approval at least two (2) weeks prior to each requested outage date and are contingent upon Government approval. Outages may be granted on holidays or weekends depending
ANZY119025 01 10 00-4
upon the Government’s schedule for facility use, and may occur on weekends and /or holidays.
F. Keep work area clean and free from waste and debris. Dispose of waste as directed by the Government Representative.
G. Do not close or obstruct egress width to any building or site exit without written permission from the Government Representative.
H. Do not disable or disrupt building fire or life safety systems without written permission from the Government Representative.
I. Conform to applicable procedures when any hazardous or contaminated materials are discovered.
J. Cease operations immediately for any unsafe conditions and notify the Government Representative. Do not resume operations until authorized by the Government Representative.
K. Provide temporary barricades and other forms of protection as required to protect Government personnel and the general public from injury due to the work.
L. Provide protective measures as required to provide free and safe passage of Government personnel and the general public to and from occupied portions of the building.
M. Remove protections at the completion of work.
N. Do not close, block, or otherwise obstruct streets, walks, or other occupied or used facilities without written permission from the Contracting officer.
O. Submit sketches of proposed scaffolding, if utilized. All scaffolding shall be in accordance with AEDC SHE Standard D10 and shall be inspected, approved, and tagged by AEDC Safety Representative after it has been erected and prior to use.
P. Verify lighting circuits are as indicated on the drawings. Mark up the drawings to show any changes.
Q. Submit record as-built drawings.
R. Provide all tools and equipment necessary to work and transport materials to work areas at grade and on multiple levels of stairwell and building walls. Some light fixtures are accessible only by ladder, and some locations may require a mobile lift.
S. When working in locations above or outside the existing guardrails; on ladders outside the dam structure, where someone could fall into water, The Contractor shall provide their employee’s with the following: (1) The
ANZY119025 01 10 00-5
individuals shall wear U.S. Coast Guard-approved life jackets or buoyant work vests. (2) Ring buoys with at least 90 feet of line shall be provided and readily available for emergency rescue operations; the distance between ring buoys cannot exceed 200 feet. (3) At least on lifesaving skiff equipped with both a motor and oars shall be immediately available to affect a rescue.
1.5 OUTAGES AND TEMPORARY POWER REQUIREMENTS
A. The panel replacement shall be performed on weekdays, weekends, and/or holidays as coordinated with the Government.
B. Contractor shall restore power daily to lighting fixtures and all 120/208V panels between 1700 hours, and 0700 hours unless otherwise authorized in writing by the Government Representative.
C. Contractor shall provide required temporary power as necessary to perform work and meet all requirements specified herein. If necessary, Contractor shall provide supplemental power by portable generator.
Convenience outlets located in the work location are available for use by the Contractor at the discretion of the Government Representative.
1.6 PROTECTION OF EXISTING IMPROVEMENTS
A. Protection of the grounds, walkways and structures from deterioration due to excessive vehicular traffic, equipment disturbance, and material staging is critical to maintaining the quality appearance of AEDC. The contractor shall protect against damage incurred by service vehicles, construction activities, maintenance and repair, and all other work that detracts from the overall appearance of the grounds and increases the costs of grounds maintenance.
B. Prior to commencement of work, inspect areas in which work will be performed. File a report with the Contracting Officer listing existing conditions which could be construed as damage resulting from the work.
The Government Representative may also photograph or video tape areas or improvements susceptible to damage to document conditions prior to the start of work.
C. The activity of vehicles and equipment on the grounds shall be limited to only that which is essential and required for completing the work. The Government Representative will approve all access and haul routes required for the work prior to any on site operations to preclude damage to sensitive utilities or improvements which may not be readily apparent.
D. Minimize travel paths and staging areas to limit the impact and damage to work areas. Lay out the work site, material and equipment staging, and vehicle and equipment activity to minimize visibility and aesthetic impact of activities to surrounding areas.
ANZY119025 01 10 00-6
E. Protect above and below grade utilities, plant life, lawns, and other features or improvements to remain.
F. Protect benchmarks, existing structures, sidewalks, curbs, and pavements from excavation equipment and vehicular traffic.
G. Use protective materials, such as sheeting, steel plating, rigger pads, to protect grounds and pavement from heavy equipment activity and damage.
H. Implement a daily procedure for area clean up and organized parking of vehicles and equipment.
I. Provide temporary barricades, shoring, bracing, supports or other forms of protection as required to protect all existing improvements not scheduled to be demolished for both above and below ground improvements and to prevent movement, settlement, collapse or damage of any kind.
J. Maintain personnel and vehicular access and existing utilities to all buildings and other structures during the course of the work. Any changes or interruptions shall be coordinated and approved by the Government Representative well in advance. Temporary protections or services may be required as a condition of approval of any such change or interruption.
K. The contractor shall be responsible for damage caused by the work and shall repair or replace same to the satisfaction of the Government. Obtain Government Representative’s approval of methods, materials, equipment or products for repair or replacement prior to use. All such repair or replacement will be performed promptly at no additional cost to the Government. The Government will place special emphasis and requirements for repair or replacement of damage to underground utilities, lawns, grassed areas, existing structures, sidewalks, curbing, railings and pavements.
L. Remove all temporary barricades, shoring, bracing, supports or other forms of protection at completion of work. Restore all adjacent structures and surfaces to conditions existing prior to construction. Clean up all stockpiles and spoil areas, and restore all surrounding areas to conditions existing prior to construction.
1.7 SAFETY REQUIRMENTS
A. All work shall be accomplished in compliance with AEDC SHE Standards A6 with supplement, A9, A10, B1, B2, B3, B5, B6, D3, D6, D8, D9, D10, E7, E17, E18, E19, F2, and F6. Provide a safety and health plan in compliance with CoE EM 385-1-1.
ANZY119025 01 10 00-7
1.8 DISPOSAL OF CONTAMINATED EQUIPMENT
A. The Contractor shall clean equipment or material of contaminants prior to disposal at the AEDC Salvage Yard (with the exception of lead paint, unless the paint is flaking in which case the flaking paint shall be removed prior to transport to prevent contamination during transport). If cleaned equipment is to be turned-in to the Government for storage or excessing, a GC-1785, Special Material Turn-in Certification, shall be completed and submitted to the Government with the equipment or material prior to disposal. The Government Representative will assist the Contractor in filling out the form and in coordinating with Industrial Hygiene and Environmental Quality.
1.9 CONNECTIONS TO POTABLE WATER
A. Contractor shall not make any connections to an AEDC potable water system without specific approval from the Government Representative.
B. Notify Government Representative if connections to hose bibs are needed. Do not connect to any hose bibs without Government-supplied backflow preventer and specific approval from Government Representative.
1.10 DELIVERY, STORAGE, AND HANDLING
A. Deliver all equipment properly packaged in factory containers and/or mounted on shipping skids.
B. Provide and store all equipment in a clean, dry space, and protect from dirt, fumes, moisture, construction debris, and traffic. Ensure that all equipment is prepared for anticipated storage conditions.
C. Where equipment is stored outdoors, ensure electrical components are stored above grade and enclosed with watertight wrapping. Provide 120V temporary power to space heaters or provide temporary heat if required to protect equipment.
D. Notify Government Representative a minimum of two weeks prior to delivery of large equipment being stored on-site. Contractor shall offload equipment at a location designated by the Government Representative.
E. All handling, loading, and offloading of all equipment shall be done by the Contractor.
F. Handle and store all equipment in accordance with manufacturer’s instructions.
1.11 TOOL CONTROL: Coordinate tool control with the Government Representative.
ANZY119025 01 10 00-8
1.12 ELIMINATION OF ODS CHEMICALS
A. The use of Class I ozone depleting substances (ODS) is prohibited.
Reference text of AFFARS clause 5352.223-9000.
1.13 DISALLOWED PRODUCTS
A. Do not use products or materials that contain lead, chromium, mercury, cadmium, barium, selenium, beryllium, or arsenic on this project except as expressly authorized by the Contracting Officer. If no substitutes for products containing the listed materials are available, and the Contracting Officer approves the use of products containing the listed materials, highlight and detail their exact location on the drawings.
1.14 ASBESTOS PRODUCTS
A. Do not use products or materials that contain asbestos on this project except as expressly authorized by the Contracting Officer. If no substitutes for asbestos products are available, and the Contracting Officer approves the use of asbestos products, highlight and detail their exact location on the drawings and identify their location in the field following 29 CFR
1926.1101 guidelines.
1.15 HAZARDOUS WASTE
A. Where hazardous waste (as identified in 40 CFR 261) is generated, follow the procedures in AEDC SHE Standard E18, Chemical and Petroleum Products Waste Management, for storing and turning in hazardous waste.
These procedures include the requirement to complete Forms GC-565 and GC-1337, which will be furnished by the Government Representative.
1.16 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA
A. The following procedures shall be followed to meet 40 CFR 370, EPA Hazardous Chemical Reporting and Community Right to Know Requirement.
1. Procedures:
a. The contractor shall furnish information on the hazardous materials he brings on AEDC property prior to beginning on-site work. Hazardous materials may include solvents, paints, adhesives, acids, or any other substance which could be included within the definitions in paragraph 2.
b. The information required is:
1) Company name, point of contact, and phone number.
2) Brief statement indicating how the hazardous material will be used within the scope of the contract.
3) List of all hazardous materials to be used (product name, manufacturer’s name, and address).
ANZY119025 01 10 00-9
4) Amount of each material to be stored on site and where it will be stored.
5) Where the product Material Safety Data Sheets (MSDS) will be maintained.
c. All unused product is the responsibility of the contractor and shall be removed from AEDC property at the completion of the project.
d. The contractor shall coordinate with the Government Representative and the Hazardous Waste Operations Group (454-3628) if any hazardous waste is to be generated.
2. Definitions
a. Hazard communication standard. A chemical right-to-know law under OSHA that requires chemical manufacturers and importers to assess the hazards of chemicals they make or import and to distribute this information to inform workers of the hazards associated with these chemicals. This written information is a Material Safety Data Sheet (MSDS).
b. Hazard classes. Hazardous materials that have been grouped into classes by the Department of Transportation (DOT). These classes include explosives, flammables, oxidizers and organic peroxides, compressed gases, corrosives, and poisons.
c. Hazardous material. Any substance that may be harmful when used. Specific substances have been designated as hazardous under the Clean Water Act, the Resource and Conservation and Recovery Act, and the hazardous air pollutants under the Clean Air Act.
d. Hazardous waste. Any waste that may cause or significantly contribute to serious illness or death or that may pose a substantial threat to human health or the environment, if not properly managed. Hazardous wastes may be solids, liquids, semi-solids, or compressed gases.
1.17 PROPRIETARY AND BRAND NAMES: Proprietary and brand names used in this document are meant to describe physical, performance, and quality characteristics of items and materials, and are not meant to limit competition or exclude Contractors, Vendors, or Manufacturers from submitting like products to the Contracting Officer for approval.
END OF SECTION
ANZY119025 01 33 00-1
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 DESCRIPTION OF REQUIREMENTS. This section specifies procedural requirements for non-administrative submittals, including but not limited to shop drawings, product data, manufacturer’s certificate, design data, calculations, and verifications, manufacturer’s instructions, manufacturer’s field service reports, samples, operation and maintenance manuals, and other miscellaneous work-related submittals. These submittals are required to amplify, expand, and coordinate other information contained in the contract. This section describes the type and content of submittals that may be required for this work. The required submittals are included in the Statement of Work or Specification.
Non-work-related submittals are addressed elsewhere in the contract rather than in the specification and may include items such as: contract progress schedule, permits, payment applications, performance and payment bonds, insurance certificates, and progress reports.
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections of the specification or statement of work.
1.2 SUBMITTAL PROCEDURE
A. Definition: For the purposes of this section, the term “Contractor” denotes the prime Contractor.
B. Listing: At the end of this section is a summarized listing of item submittals requiring approval for the work. The listing is included for the convenience of users of the contract documents. The listing may not be all inclusive and additional item submittals may be required. Within 14 calendar days after receiving contract award, Contractor shall submit a copy of the summarized submittal listing with calendar dates assigned to each item submittal indicating when submittal will be received by the Government. If contract requires a pre-construction conference, Contractor may submit completed submittal listing at the conference.
C. Risk: Do not proceed with the part of the work covered by an item submittal including purchasing, fabricating, and delivering until approval is received. Machinery, equipment, material, and articles that do not have the required approval shall be installed or used at the risk of subsequent rejection. Any fabrication or other work performed in advance of the receipt of accepted item submittals and approvals shall be entirely at the Contractor’s risk and expense.
D. Transmittal Timing: Coordinate the preparation and processing of item submittals with the performance of the work. Prepare and transmit each
ANZY119025 01 33 00-2
item submittal to the Contracting Officer sufficiently in advance of the performance of related work and other applicable activities. Transmit related item submittals for the same unit of work so that processing will not be delayed by the Government's need to review submittals concurrently for coordination.