FA9101-16-B-0006-0001 Amendment I Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA9101-16-B-0006-0002.pdf | ||
| FA9101-16-B-0006.doc.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
See Block #2
PAGE OF PAGES
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
29 JUN 2016
4. REQUISITION/PURCHASE REQ.NO.
5. PROJECT NO. (If applicable)
6. ISSUED BY AFTC PZI ARNOLD CODE FA9101 7. ADMINISTERED BY (If other than Item 6) CODE
AFTC/PZI (ARNOLD)
100 KINDEL DRIVE, SUITE A-345
ARNOLD AFB, TN 37389-1332
MALISA C. FORD 9314545139
malisa.ford@us.af.com
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
FA9101-16-B-0006
X
9B. DATED (SEE ITEM 11)
26 MAY 2016
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers X is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 0 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATION OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(X )
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: ( ) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. ITEM
10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Replace Lighting Woods Dam Questions and Answers 0001 (See Schedule)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print).
16A. NAME AND TITLE OF SIGNER (Type or print)
ROBERT A. GREENE
15B. CONTRACTOR/OFFEROR
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
16C. DATE SIGNED
(Signature of person authorized to sign)
BY________________________________________
(Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.10-83)
PREVIOUS EDITION UNUSABLE Prescribed by GSA ConWrite Version 6.15.0 FAR (48 CFR) 53.243 Created 29 Jun 2016 2:46 PM
SCHEDULE OF CHANGES
FA9101-16-B-0006 0001
Question 1: How will the winning contractor get access to the project? Will base furnish full time monitor or guard to open and shut gates or will contractor have keys to enter?
Answer: Contractor will have keys and be given code to gate lock.
Question 2: Where below dam could contractor launch rescue boat?
Answer: As long as work is being done within the dam or within the guard rails of the piers, a rescue boat is not required. Contractor will need to follow OSHA regulations if planning to work outside of the guard rails. If the contractor is required or just wants to have a rescue boat available there is an access drive on the on the North side of the dam.
Question 3: Where is the main disconnect for panel p1?
Answer: Panel P1 is fed from the service entrance through a service disconnect on the normal side and then through a transfer switch to panel P1 according to existing ATA drawing # TDT35531.E3. Drawing E3 of the contract drawing package indicates that P1 is fed from the main feeder entrance breaker. I do not know exactly where the enclosed breaker is located, but if needed we could go out there to locate it for them or get the low voltage system engineer to locate it.
Question 4: Need pics of panel P1 and P3 also ceiling of each landing in main stairway.
Pics of pier 22.55 and 24.35 showing floodlite ?
All photos are For Official Use Only (FOUO). Requested photos can be provided upon request to the Contract Specialist; malisa.ford@us.af.mil.
Question 5: Our lighting vendor asked to make sure you want dimming for fix X and fix D.
Answer: Fixtures D, F, and X do not require dimming controls.
File details come from the government source that posted it. Updated .